$668M Waste-to-Energy Project Moves Ahead Despite Protest

Text size: A A

Despite a formal protest from the second-place bidder for a 3,000-ton-per-day waste-to-energy facility, the Solid Waste Authority of Palm Beach County awarded a $668-million design-build contract to a team of Babcock & Wilcox and BE&K to design, construct and operate the facility.

Image: courtesy SWA
----- Advertising -----

B&W’s design-build estimate of $668 million was roughly $62 million higher than that of Wheelabrator, the division of Waste Management Corp. that placed second. However, SWA factored in the value of electrical generation and recoverable materials that each team guaranteed that their respective designs would deliver to the authority for a net present value calculation, according to Ray Schauer, SWA’s director of engineering and public works.

Under that calculation, because B&W’s proposal guaranteed the greatest amount of electrical generation and material recovery, its bid was considered the lowest cost, with a value of nearly $500.5 million. The net present value of Wheelabrator’s proposal was calculated at $626.6 million.

Construction should start by late 2012, with commercial operation planned by May 2015.

In a ranking of the competing proposals on “non-cost” issues, such as labor hiring pans, however, Babcock & Wilcox ranked third overall, while a proposal from Covanta was rated highest.

Wheelabrator issued a formal protest of the awarding of the contract to Babcock & Wilcox, asserting that B&W’s partnership with BE&K to build the facility violated SWA’s requirement for a single entity to manage the project. The company also cited technical issues with B&W’s design.

The contract covers design, construction, start-up, acceptance testing and long-term operation and maintenance of a new mass burn waste-to-energy facility that will process approximately 3,000 tons per day of municipal solid waste. SWA is mandating that the facility be operational by 2015 or sooner.

The new facility will complement SWA’s existing 2,000-tpd waste-to-energy facility, which is operated by the Palm Beach Resource Recovery Corp., a subsidiary of B&W. The latest project addresses the SWA’s plan to manage solid waste through source reduction, recycling, composting, combustion and landfilling.

 

----- Advertising -----
  Blogs: SE Staff   Blogs: Other Voices    
Our blog delivers the latest news, insights, and opinions about ENR Southeast.
Reader Photos
Photos from ENR Southeast Photo Showcase
----- Advertising -----
 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.