Ben Sawyer Swing Bridge Replaced within 11 Days

Text size: A A

PCL Civil Contractors of Tampa led the replacement of a swing-span bridge in Sullivan’s Island, S.C., in 11 days. The new Ben Sawyer Bridge was reopened in February after the 250-ft replacement swing span was floated in place and the approach spans rolled in place onto the existing substructure.

The $32.5-million project is being executed under a design-build contract for the South Carolina Dept. of Transportation. PCL and its design team of Hardesty & Hanover, and Florence & Hutcheson replaced the approach span superstructure and swing span utilizing the existing substructure of the nearly 70-year-old bridge.

PCL expects to complete the project by this summer.

----- Advertising -----
  Blogs: SE Staff   Blogs: Other Voices    
Our blog delivers the latest news, insights, and opinions about ENR Southeast.
Reader Photos
Photos from ENR Southeast Photo Showcase
----- Advertising -----
 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.