|
Cooper River Bridge Replacement Project
Owner: South Carolina Department
of Transportation
Location: Charleston, S.C.
Cost: $540 million
Contractor: Palmetto Bridge
Constructors, a joint venture of Tidewater Skanska, Norfolk,
Va., and Flatiron Constructors, Longmont, Colo.
Designer of Record: Parsons
Brinckerhoff, New York
Palmetto Bridge Constructors and the South Carolina Department
of Transportation recently completed the $540 million Cooper
River Bridge, which features North America's longest cable-stayed
span.
The team had to design and build it to withstand a Category
5 hurricane, an earthquake measuring 7.3 on the Richter scale
and any impact from some of the world's largest cargo ships.
Additionally, the Cooper River Bridge - known formally as
the Arthur J. Ravenel Jr. Bridge - one of the largest design-build
bridge projects undertaken in the United States.
The SCDOT has estimated that by using the design-build approach,
it saved roughly $150 million due to the reduced time associated
with this procurement method.
The design-build contract was signed in July 2001, at which
point the final design began while PBC began to plan and mobilize
for construction. Fieldwork began in April 2002 with the construction
of drilled shafts.
Bridge-deck construction began in September 2003. By spring
2004, the towers were under construction and by midsummer
of that year nearly one half of the bridge deck spans were
completed. By mid-2004, the towers were completed.
The main span superstructure was completed in March, and
the bridge was opened in July.
The 1,546-ft.-long main span hangs from two "diamond-shaped"
towers, with 128 individual cables anchoring it to the hollow
interior core of the 575-ft.-tall structures. The deck is
approximately 200 ft. above the median high-tide mark.
The towers were built with cast-in-place concrete, while
the main-span deck consists of structural steel framing and
precast concrete panels constructed and barged in from Savannah,
Ga. A latex concrete overlay is then applied over the precast
panels.
Key to compressing the schedule was breaking down the project
into five smaller components: the main span, Charleston interchange,
Charleston high-level approach, Mount Pleasant interchange
and Mount Pleasant high-level approach. Each segment had its
own general superintendent, budget and schedule, while a management
team at the corporate level managed resources and provided
support across all five projects.
The team also took an innovative and flexible approach to
sequencing. For example, the main-span team began building
the bridge deck before completion of the two towers - an approach
the Skanska team had utilized successfully on two previous
projects in Sweden.
Like other federal-aid highway projects, the Cooper River
Bridge contract required the contractors and DOT to provide
on-the-job training opportunities. But the team took this
requirement and incorporated it into a broader community outreach
effort.
The project team recruited more than 80 unemployed and underemployed
citizens. Approximately 62 of the recruits eventually were
able to obtain journeyman status.
|