|
MetroPointe Lofts
Owner: Technology Housing,
Atlanta
Location: Atlanta
Contractor: W.G. Yates &
Sons Construction Co., Atlanta
Architect: Ai Group, Atlanta
MetroPointe Lofts is a 1,216-bed student housing project
designed to serve the Georgia Institute of Technology, Georgia
State University and Atlanta University System students.
The eight-story building consists of two- and four-bedroom
loft-style apartments. Amenities include a swimming pool;
volleyball and basketball courts; business center; night/maintenance
facility; and seven-story, 1,786-space parking deck connected
to the building with three cast-in-place concrete bridges.
Notably, the first footing for the 559,000-sq.-ft. project
wasn't poured until July 2004, and the construction team was
still able to complete the contract by Aug. 5.
The first challenge was to complete the project - including
installation of all furniture - prior to students arriving
for this year's fall semester. This prohibited any schedule
delays.
Also, a shift in the building just as footings were to begin
created a hurdle, as well as a "pinch point," and
caused the finished grade to be 12 ft. below the adjacent
property - and leaving only 7 ft. between the building and
the adjacent property.
This building shift caused a change in the location of the
footings and also affected site utilities and site logistics.
To resolve the problem, the footings were accelerated and
work was resequenced due to the limited site access.
The team also design-built a zero-lot-line, cast-in-place
concrete retaining wall to expedite resolution and protect
adjacent fiberoptics.
Poor subsurface conditions had initially caused the owner
to consider deep foundations as a requirement for the project.
However, Yates suggested utilizing dynamic compaction to improve
the soil. Ultimately, this method won out and the team was
able to use spread footings as a foundation, which reduced
this portion of the overall budget by $500,000.
The building was designed to have a loft-style atmosphere,
with exposed concrete floors and an exposed MEP system in
the ceiling. A chain-link fence corridor ceiling was designed
during preconstruction to limit student access to the exposed
MEP systems. This system proved to be not only cost effective
but also visually appealing and a complement to the loft atmosphere.
|