|
Martin-Manatee Power Plant Expansion Projects
Owner: Florida Power &
Light, Miami
Location: Indiantown, Fla.,
and Parrish, Fla.
Cost: $300 million, combined
construction cost; $1 billion total cost
Contractor: Martin-Manatee
Power Partners, a joint venture of Black & Veatch, Overland
Park, Kan., and Zachry Construction Corp., San Antonio
Engineer: Black and Veatch
Martin-Manatee Power Partners achieved an industry milestone
in 2005 with the completion of two $500 million power projects
within 12 hours of one another.
This achievement was the culmination of a complex, two-year
construction schedule that began in June 2003 for project
owner Florida Power & Light.
The 800 MW addition and conversion of existing simple-cycle
units at the Martin Power Plant in Indiantown and the addition
of a 1,100 MW unit at the Manatee Power Plant in Parrish provide
a combined additional 1,900 MW of generating capacity to FPL's
system, enabling the utility to serve an additional 400,000
customers.
The Manatee project required the installation of a new cooling
water intake and discharge system and piping that tied into
the existing dam surrounding Manatee's above-ground cooling
pond. This work was sensitive because extra precautions were
required to minimize risks to the dam.
During construction, any mistakes that might have occurred
had the potential to shut down the existing plant if the dam
had been breeched.
Due to this concern, MMPP collaborated with FPL and its Dam
Safety Review Board to develop a design that minimized the
potential for jeopardy to the dam. Over the course of a year,
MMPP conducted numerous flow model studies and geotechnical
modeling and analyses to address all dam safety concerns.
At the Martin project, MMPP tied into the two existing simple-cycle
units and converted all four units into a single combined-cycle
generating unit. MMPP was led to execute a series of outages
to perform their tie-ins based on FPL's power demand periods.
This distinction from Manatee was meaningful because the
outages could have derailed the projects from tracking together.
MMPP kept both projects tracking for a simultaneous completion
by using a lead-lag approach. Lessons learned from the lead
project helped improve processes at the lagging project to
create efficiencies. The construction team was able to execute
its work at both projects without disruption to plant operations.
Both projects achieved a high degree of safety. Clay Lassen,
safety facilitator on the Manatee project, summed up the approach:
"Safety first. Once you have that squared away, everything
else can be taken care of."
|