|
Vertical Circulation Cores, Landside Elevator
Improvements, Orlando International Airport
Owner: Greater Orlando
Aviation Authority, Orlando
Location: Orlando International
Airport, Orlando
Cost: $20 million
Contractor: Hensel Phelps
Construction Co., Orlando
Architect: KBJ Architects,
Orlando
On this project, Hensel Phelps Construction Co. was responsible
for making vertical circulation improvements at the terminal
end of four pedestrian tunnels connecting the garages to the
landside terminal.
The objective was to enhance the terminal and increase the
capacity of the North Terminal Complex so it could sufficiently
handle passenger requirements until the first phase of the
South Terminal Complex was completed.
The vertical circulation improvements were accomplished by
replacing the two existing hydraulic elevators with three
traction elevators in each tunnel at the terminal end. This
involved removing the existing roof above the elevator shaft
and four floors of 1-ft.-thick, cast-in-place concrete elevator
shaft walls and the elevators through an occupied building.
The existing elevator pits were removed and new pits installed
at a lower elevation.
Public access was maintained at all times to all sides of
the project and existing escalators.
This construction extended into the rental car lobbies on
level one, which were required to remain open and operational.
The enlarging of the elevator shafts affected all levels of
the terminal.
Portions of the structural bays adjacent to the elevator
shafts needed to be demolished so that the new elevator shaft
width could be accommodated and the escalators relocated.
The demolition work required on level two impacted the baggage-claim
operation, while the work on level three impacted curbside
operations.
Additionally, the fabric canopies, skylights and roof above
level three were modified to accommodate the new elevator
shaft, and new elevator penthouses were added.
The project scope also included providing and installing
an independent elevator, escalator and moving-walk monitoring
system for all 89 elevators, 68 escalators and 16 moving sidewalks
in the North Terminal Complex. This system was custom designed
to meet the requirements of the project owner, the Greater
Orlando Aviation Authority.
|