Alpharetta High School
Project Team
Owner: Fulton County Schools
Location: Alpharetta, Ga.
Cost: $55.9 million
Contractor: Skanska USA Building,
Atlanta
Architect: Perkins & Will
Architects, Atlanta
Fulton County Schools needed a large school, built quickly,
but it also required that the new facility be a state-of-the-art
educational environment. That was because it's estimated that
more than 90 percent of high-school students in this community
are expected to pursue a postsecondary education. The new
school will accommodate about 1,850 students.
The new, 335,000-sq.-ft. Alpharetta High School features
four two-story classroom wings, with three of these each containing
17 classrooms, two science classrooms, two science labs, two
business labs, one foreign-language lab, one math lab, one
geography lab, a conference room and teacher's lounge. The
fourth wing is designated for special education and contains
six classrooms, two speech therapy classrooms, a teacher's
workroom, home-living lab, six therapy rooms and psychology
education classrooms.
Connecting the four wings is a three-story commons area that
contains a full-service kitchen and cafeteria, media production
rooms, conference room, administrative areas, technology lab,
nutritional foods lab, professional foods lab, multimedia
classrooms, professional foods lab and seminar rooms.
The school also features a performing arts center with orchestra
pit and stage, set-storage and -construction rooms, dressing
rooms, band and choral rooms, orchestra room, photography
lab and two art classrooms.
The gymnasium features a competition basketball court and
practice court, climbing wall, elevated running track, weight
room, locker rooms, fitness center and indoor rifle range.
The sports complex includes a football field with home/visitor
stadium, softball field, baseball field with stadium seating,
practice field and four tennis courts. Ball fields were completed
by August 2003, allowing them a one-year growing period prior
to the start of school in 2004.
Skanska USA Building utilized a structural steel system for
the classroom wings, commons area and performing-arts center,
and a reinforced concrete structure for the gym. The facility
is clad with a combination of ground-face block, brick and
more than 70,000 metal siding shingles. Flying buttress columns
punctuate the building's exterior and serve aesthetic as well
as functional purposes, incorporating downspouts for the gutter
system.
The downspouts route rainwater into a bioretention "rain
garden" that captures and cleans water runoff before
it enters nearby Big Creek.
The project's design incorporates the natural surroundings
into the building's environment, with extensive window systems
flooding the school with natural daylight - a factor reportedly
shown to enhance the learning process. Classroom windows start
42 in. from the floor, allowing sufficient daylight in but
eliminating any other distractions at the ground level. Floor-to-ceiling
windows in common areas provide views of the nearby forest.
One of the rainiest seasons in Georgia's history fell within
the project's 24-month schedule. Over the course of roughly
three months in 2002, 24 in. of rain fell in Atlanta.
During this time, the Skanska-led team was focused on foundation
work. To stay on schedule, a massive dewatering operation
was implemented, with more than 7,000 manhours spent pumping
or otherwise dealing with excessive water. Additionally, approximately
2,700 tons of rock were used to drain excavated areas.
The project also included a $5 million road-widening package
for two main thoroughfares abutting the school's property.
Soon after work began, Skanska discovered a sinkhole that
threatened the stability of Webb Bridge Road. To maintain
the integrity of the roadway, the project team relocated a
30-in. water main and then worked with subcontractors and
other entities to repair the sinkhole.
The 73-acre site featured more than 100 ft. of elevation
change and thus required a $3 million, 330,000-sq.-ft. retention-wall
system constructed of a combination of earthen and block walls.
Finally, the Skanska team used a "Stretch and Flex"
program as part of its Incident-Free Environment program.
Every morning the team stretched with every trade to get ready
for the workday. The program resulted in no soft-tissue injuries
throughout the project.
|