Presbyterian Women's Center Expansion
and Renovation
Project Team
Owner: Novant Health/Presbyterian
Healthcare System
Location: Charlotte.
Cost: $65 million
Contractor: Rodgers Builders,
Charlotte
Architect: McCulloch England
Associates Architects, Charlotte
The Presbyterian Women's Center Expansion Renovation Program
on the campus of Presbyterian Hospital in Charlotte, N.C.,
included a 60,000-sq.-ft. vertical expansion atop an existing
eight-story precast parking deck, a 20,000-sq.-ft. north wing
addition above an existing two-story children's hospital and
a 17,000-sq.-ft. adjoining connector bridge to the existing
hospital.
The new Women's Center includes 39 postpartum beds, a newborn
nursery, 16 labor-and-delivery rooms, three C-section rooms,
14 high-risk antepartum beds and various support spaces. Work
on the seventh floor of the adjacent hospital included renovations
that create a 38-position intensive-care unit and 20 new GYN
beds.
Before any work could begin, Rodgers Builders needed to structurally
retrofit an eight-level parking deck the company had built
in 1991. Four concrete shear towers, each estimated to be
the size of a parking space, were designed and built to stiffen
the existing precast deck. Each of these shear towers sat
on 16 minipiles, which were drilled into the basement level
of the deck to bedrock below.
Vibration studies were conducted to monitor the impact of
traffic movement at the finished patient floor. The four shear
towers were designed to carry the majority of the patient
floor load so that vibrations from the cars below would not
migrate through to the Women's Center addition above.
The North Wing addition added 20,000 sq. ft. of patient floor
at level seven, over an existing two-story children's hospital.
The four floors of space in between were created as interstitial
space. Additionally, the footprint of the building was expanded
to add 7,000 sq. ft. to the original existing levels. All
structural bracing and framing in the interstitial space,
as well as the new floor, took place while the hospital was
fully operational. More than 800 tons of structural steel
were erected in this area.
Due to a lack of space at grade level, the tower crane had
to be positioned inside one of the newly constructed shear
towers in the parking deck. Also, a motorized scaffolding
system was employed to install the skin on the exterior of
the project. Use of this motorized system allowed the work
of several trades to occur simultaneously on several levels
of the building.
Extensive mockups were done of every type of room for owner
and architect approval. Long lead items such as flooring were
installed in an alternate area for early approval and durability
testing.
|