Esplanade Grande
Project Team
Owner: Royal Palm Holdings
Location: West Palm Beach
Cost: $24.7 million
Contractor: Suffolk Construction Co., West Palm Beach
Architect: Sieger Suarez Architectural Partnership,
Miami
The Esplanade Grande is a 16-story high-rise condominium
located near the Meyer Amphitheater and Intracoastal Waterway
in downtown West Palm Beach. The 329,000-sq.-ft. building
consists of 62 condominiums, ranging from 1,200 to 7,000 sq.
ft., and four levels of parking for 123 vehicles.
The main entrance consists of a two-story-high lobby along
with 6,700 sq. ft. of retail space. Other features include
a cast-stone entry area, elegant lobby finishes, fourth-floor
spa, roof-top swimming pool and roof observation deck.
Preconstruction activities began with the demolition of several
one- and two-story buildings. This required great care because
an operating Fidelity Federal Bank building was located approximately
6 in. from the jobsite.
The building was supported by a 5-ft.-thick concrete mat
slab. Basement-level parking began 15 ft. below street level.
Dewatering was a major issue because the project was as much
as 10 ft. below the water table.
An interesting hurdle involved the city of West Palm Beach's
requirement that no ductwork or drywall be installed on a
floor until it was proven to be dry during rainstorms. Typical
high-rise construction schedules don't allow for installation
of the roofing and exterior stucco and windows prior to installation
of ductwork and drywall.
To accommodate this, Suffolk prepared a detailed temporary
waterproof plan. Measures included sealing every pipe and
duct floor opening and installing temporary waterproofing
over the elevator shafts. Instead of starting stucco work
from the roof and working down, Suffolk had its contractors
start at the 11th floor on stucco base coat only.
This allowed the contractors to begin ductwork and drywall
on the lower floors while the building shell construction
proceeded on the upper floors. This plan enabled the team
to maintain schedule while satisfying the city's concerns
about water intrusion.
Another challenge was the rooftop deck, which involved the
phased construction of the structural concrete deck, pool
walls, planter and 15-ft.-high perimeter walls.
|