University of Florida Exotic Aquatic
Quarantine Facility
Project Team
Owner: University of Florida
Planning & Construction, Gainesville
Location: Fort Pierce, Fla.
Cost: $3.3 million
Contractor: Elkins Constructors,
Jacksonville
Architect: KBJ Architects, Jacksonville
Located in Fort Pierce, this University of Florida facility
is utilized by researchers to study the potential use of biological
control organisms such as insects, mites and nematodes to
combat the growing number of exotic, invasive plants and arthropods
that have been identified throughout the state.
The goal of the researchers is to ensure that these organisms
that may be used to help control the spread of the invasive
species will not feed on unintended plants or other living
matter. For that reason, the entire facility had to be constructed
so that every room could be completely airtight and climate-controlled.
The exterior of the two-story, 19,710-sq.-ft. building is
fairly traditional, featuring a block-and-brick structure
with an aluminum standing-seam roof. Inside, the facility
is more complex, featuring 13 separate mechanical systems
for each area of the building. Laboratory spaces comprise
roughly 12,380 sq. ft., and the facility also has six greenhouses
and office areas.
The entire building had to be tightly sealed, and each room
quarantined from the next. For this purpose, the project team
used zero-tolerance caulking and other airtight construction
methods. This method of caulking required that all sheetrock
be cut to fit tightly around all spaces, then slathered with
flexible caulk to prevent air from passing from room to room.
Drywall was sealed at ducts and conduit, and ceilings and
floors were preserved with a protective sealant. Electrical
conduit going from room to room was sealed with a special
conduit system, and the heating and cooling system was self-contained
for each quarantined area.
To ensure the quality of each sealed space, the Elkins team
would caulk a room and then test it individually, instead
of testing the entire building at once. This was critical,
because finding out at the end of the project that a room
was not sealed correctly would be too late. To certify that
rooms were successfully sealed, federal inspectors would verify
the quality of each quarantined room with air-pressure testing.
According to Elkins Constructors' project entry information,
the intricate and complex nature of the project resulted in
its cost being roughly three times that of a more standard
building of a similar size.
|