C-2 Wharves Renovations/Upgrades, Mayport
Naval Station, Jacksonville
Project Team
Owner: U.S. Navy
Contractor: Military Construction
Corp. (Mil-Con), Jacksonville
The purpose of this project was to upgrade the existing infrastructure
of the Mayport Naval Station aircraft carrier pier to accommodate
nuclear- as well as conventional-powered aircraft carriers.
This included upgrading and/or replacing electric, water,
sewer, oily waste and steam laterals.
The unique aspect of this project was the method used to furnish
two 600-amp, 26.4-kV electrical circuits to the pier. Using
horizontal directional drilling technology, the construction
team drilled under the turning basin, through which three
6-in. pipes were installed. The electrical circuits were installed
in two of the three pipes, leaving one as a spare for future
use.
The directional drilling measured 2,200 ft. in length, with
an ultimate depth of 125 ft. The use of HDD shortened the
overall distance the electrical circuits had to traverse from
their point of origination at the municipal power source to
the carrier pier. Carrying the electrical circuits under water
helped reduce costs for the Navy as compared to the alternative
of an overland, duct-bank, manhole system.
An additional challenge came from the fact that the turning
basin was located at an active Naval station, with numerous
ships moving in and out on a continual basis.
The second greatest challenge was the accelerated time schedule
for the project. All construction work needed to be completed
during deployment of the USS Kennedy. The project award date
was Sept. 13, 2001, and scheduled deployment was for the following
March. The contractor used those six months for planning and
design, though design work would continue throughout the construction
phase of this design-build project.
The day the USS Kennedy deployed, work commenced. The originally
scheduled completion date was September 2002. However, the
owner accelerated that date to August 2002. Military Construction
Corp. (Mil-Con) officials considered the project's schedule
to be "extremely aggressive," considering that utility
laterals on the pier, such as potable water, sanitary sewer,
oily waste and steam needed to be replaced.
This involved removing the paving and massive amounts of materials,
as well as the old systems to make way for the new. That,
combined with the resurfacing of approximately 12,000 sq.
yds. of paving, had to be accomplished prior to the Kennedy's
return.
Mil-Con's Mark Thompson credited the close working relationships
between the owner and the rest of the construction team for
the project's successful completion.
"Due to our past experience with Art Mosely, the Navy's
construction representative, we had developed an extremely
high level of trust," said Thompson. "We could go
to him with any problems and he would work with us to reach
a solution." Thompson also cited the efforts of Lt. Jorge
Cuadros, regional officer in charge of construction, as well
as Brian Price, the Navy's project manager.
|