S. R. 429, Western Beltway, Part C -
Section 655, Orlando
Project Team
Owner: Orlando-Orange County
Expressway Authority
General Contractor: Granite
Construction Co., Tampa
CEI: GAI Consultants-Southeast
This project completes the interchange between State Road
429, the Florida Turnpike and State Road 50 in Ocoee, west
of Orlando. The owner for this project was the Orlando-Orange
County Expressway Authority (OOCEA).
The project included the construction of six new steel bridges
and five new concrete bridges, cast-in-place retaining walls,
numerous earth retaining walls and two concrete box culverts.
Work also included the construction of 10 ponds, the delivery
and placement of over 3 million cu. yds. of fill, the installation
of 40,000 ft. of storm drain pipe and over 220,000 sq. yds.
of paving. One of the steel bridges was a curved structure,
over 60 ft. in the air and almost 2,000 ft. long.
Granite Construction Co. also constructed Section 600 of the
Western Beltway, which included the first part of the interchange
between SR 429 and the Florida Turnpike. The majority of personnel
for Granite, GAI Consultants - Southeast (the construction
engineering and inspection firm) and the expressway authority,
worked on both projects. This resulted in an experienced team
of personnel with established relationships working together
to build the project.
The biggest challenge on this $42 million project involved
the crossing of a 130-ft.-deep muck hole. The hardest part
of dealing with this location was that the cone-shaped hole
was partially outside the right-of-way and opened onto an
existing pond. The challenge was to install a stable work
platform on top of the extremely soft muck without impacting
the adjacent pond or losing equipment into the hole. Once
the work platform was in place, wick drains and monitoring
devices were installed. Embankment was placed at a very slow
rate, with the placing of the next lift dependent on satisfactory
readings from the monitoring equipment. By working carefully
together, the project team was able to complete this work,
without impacting the project schedule.
Another area of innovation on the project involved the erection
of steel girders over existing Ramp G. This erection required
the use of three cranes in combination, while minimizing impacts
to traffic and while working 60 ft. in the air.
Careful planning and close cooperation between all parties
avoided numerous potential problems, Granite officials stated.
More than 800 truckloads of fill per day were delivered to
the project over a 12-month period without major incidents.
Four bridges had to be constructed across the Florida Turnpike.
Much of the work for these bridges had to be performed at
night to minimize impacts to traffic. One of the main phone
cables to Miami is located in the median of the Turnpike,
and had to be avoided during pile driving and drainage construction.
In summing up their project entry, Granite officials stated,
"This project has been a safe project with one of the
lowest accident-incidence rates within Granite. The whole
project team partnered together to make this a successful
project."
|