Tampa Preparatory School, Tampa
Project Team
Owner: Tampa Preparatory School,
Tampa.
Contractor: J.O. DeLotto &
Sons, Tampa.
A tight site and constraining project logistics were the rule of the
day on J.O. DeLotto & Sons' recent $18 million Tampa Preparatory School
project.
The project constituted an entirely new campus for Tampa Prep on an 11-acre
site in downtown Tampa. Phase one included site work, relocation of utilities,
and relocation of athletic fields and the field house. Phase two included
construction of a 125,000-sq.-ft., three-story classroom building, as
well as a 15,000-sq.-ft. athletic facility, and a 10,000-sq.-ft. "black
box" theater with a black granite façade. The upper-division
classroom facility included eight chemistry laboratories and facilities
for visual and performing arts. The new campus also featured an outdoor
swimming pool with a diving well.
In building the project's three main structures, the contractor faced
three issues:
- The need to build all three virtually simultaneously;
- The tight conditions of this urban site, which made project phasing
a challenge; and,
- The need to build the project in approximately 18 months - between
November 2000 and May 2002.
Originally, the contractor planned to complete the smaller black-box
theater facility prior to the other two buildings. However, because of
certain logistics, the contractor re-scheduled the project, which resulted
in the theater structure completing at roughly the same time as the other
two structures. The close proximity of the three buildings to each other
was a main factor in the contractor's decision to re-stage the project
this way.
J.O. Delotto & Sons acted as both construction manager and general
contractor on the project, self-performing some of the concrete work,
finish doors, hardware and finish trims. The project team utilized different
subcontractors for some of the same trades on the three different buildings,
which were actually managed as if they were three separate projects.
As one of the area's top private schools, the new Tampa Prep campus features
items perhaps not found at other educational facilities. Some of these
features include:
- A state-of-the-art gymnasium, with automated bleacher systems and
a built-in closed-circuit camera and television system.
- A central computer room features enough high-tech equipment that it
requires two dedicated air-conditioning units (one is for backup), weighing
approximately 7 tons total, to keep it at the appropriate temperature
and overall environment.
- A dance room with springboard wood flooring is located in the three-story
classroom building. Additionally, each classroom features a large color
television.
|