|
Time to Change
By Ted Garrison
The author suggests some radical changes in the way contractors
work.
When I talk to people in construction, there seems to be
a general agreement that the industry is worse off today than
it was 10 or 15 years ago, except in the areas of technology
and safety. Clearly, profit margins are down; quality is down
(buyers say this); and confrontation and stress are up. However,
when I ask whose fault is it, I get a lot of finger pointing.
Here I try to rattle the cage, saying, "It's your fault!"
Fault is not the correct term, but until you accept accountability
there is little chance for improvement. Blaming others for
our problems will not solve them. If we want to fix our problems
we must take responsibility for them. While progress may be
slow, every step forward helps.
Radical change is needed - tinkering at the edges will no
longer work. I suggest four changes:
- Increase the worker's wages substantially.
- Increase subcontractor's profit margins.
- Increase the GC's profit margins.
- Lower costs to the buyers of construction services.
Under the old business model, those four suggestions would
be contradictory - but that's why change is needed. The Construction
Industry Institute has calculated that the average worker
nationwide works at about 40 percent efficiency. They also
determined that 20 percent of the lost efficiency is due to
waiting for materials or supplies and 20 percent is due to
inefficiencies in the processes used to perform the work.
If management does its job these two problems could be eliminated.
Eliminating these problems would double productivity from
40 percent to 80 percent. The average construction project's
cost breakdown is approximately 40 percent for materials,
40 percent for labor and 20 percent overhead and profit. Therefore,
if labor productivity is doubled, it would cut labor costs
in half or save about 20 percent of total project costs that
could be divided up.
Since the national average for GC's is about 2 percent annual
net profit, let's increase their fee by 2 percent. This falls
to the bottom line since no costs were added. The national
average for subcontractors is more varied, depending on type
of sub and other variables, but let's increase each subcontractor's
fee by 3 percent. This increase would at the very least represent
a significant increase in net profits for subcontractors.
Giving the workers a 50 percent pay increase would consume
half of the 20 percent savings. This increase should be split
between wage increases and profit sharing allocation, but
that is a topic for another day. For now it's sufficient to
state that wages must increase if the industry is going to
attract more and better craft workers. The fact is there are
critical shortages of labor today and it is only going to
get worse unless something drastic is done.
At this point, we have consumed three quarters of the 20
percent savings. The rest goes back to the owner - a 5 percent
savings. This is a significant savings and it has been achieved
not by beating on people or contractors and increasing stress
and confrontation, but instead by working together.
Wishful thinking? Yes and no. Yes, because I realize no one
can accomplish this alone. No, because it can be done if everyone
works together. The above example is just one of many ways
the owner, GC, design team, subs and workers can work together
to deliver greater value.
Every stakeholder must focus on the project as a whole, instead
of just focusing on themselves. When this is done, waste can
be removed and the benefits shared among all the stakeholders.
Edwards Deming, a noted business consultant, has been preaching
since the 1950s that "sub optimization" does not
work. In fact, he says that it actually increases costs.
In construction, sub optimization is the process where one
stakeholder's costs are reduced without regard to the impact
on other stakeholders. An example would be lowering the design
fee to save on design costs. However, this usually results
in major problems in the field that cost more than the design
savings. This approach is penny wise and dollar foolish.
The GC's fee and the designer's fee represent about 10 percent
of total construction costs. Construction costs represent
about 10 percent of total lifetime cost of a building. Therefore,
the GC's fee and designer's fee represent about 1 percent
of the total lifetime cost of a project. The moral of the
story is it is more important to find the right team and work
together on the 99 percent instead of focusing on the GC's
and designer's 1 percent.
In the next three issues I will explore how to work together
through partnering.
Ted Garrison, president of Garrison
Associates, is a consultant, author and speaker who works
with businesses in the construction industry. He can be reached
by email at Growing@TedGarrison.com.
|