|
Quick Fix for Florida
Bridge Damaged by Hurricane Ivan
The westbound bridge of Interstate 10 near Pensacola, Fla.,
which was knocked out by Hurricane Ivan, opened for traffic
Oct. 5, seven days ahead of schedule. Kiewit subsidiary Gilbert
Southern, Atlanta, and its joint-venture partner, marine contractor
Massman Construction Co., Kansas City, Mo., completed the
work in 17 days under a $24.4-million contract signed with
the Florida Department of Transportation just two days after
the storm hit.
The team had until Dec. 16 to complete work on the more heavily
damaged eastbound bridge. To complete westbound work, the
companies built seven new substructure bents, each with four
160-ft.-tall, 36-in.-dia. pipe piles, said Scott Cassels,
Kiewit senior vice president. The bents were capped with structural
steel girders.
A Manitowoc 4600 ringer crane was used to move 11 of the
220-ton deck slabs from the eastbound portion of the bridge
to the new decking on the west side. Twenty slabs on the west
side were moved back into normal alignment. Work on the eastbound
bridge will include new bents and a temporary structural steel
bridge. Source: Engineering News-Record.
Big Repair Costs Loom in
Tampa
Evaluation of 35 of 224 foundations for an uncompleted elevated
Tampa highway has revealed that most rest on unstable ground
and will require reinforcing.
PCL Civil Constructors, a division of Edmonton, Canada-based
PCL Enterprises, had been ahead of schedule on the reversible-lanes
Lee Roy Selmon Crosstown Expressway project linking downtown
Tampa and Interstate 75 near Brandon. Completion was to be
in 2005 and is now slated for 2006.
Problems began April 13 when a pier sank 11 ft. The Tampa-Hillsborough
Expressway Authority hired Orlando-based Ardaman & Associates
to perform an independent forensic analysis. On July 6, another
pier settled 1.3 in. Work halted and Ardaman's role expanded
to include all 224 foundations.
Ardaman reported on Sept. 7 that the foundation under the
first pier sank into undetected soft materials. Review of
the remaining foundations is still in progress and should
be finished by early February.
Remedial action may include construction of "sister
shaft" reinforcements and grout injections to strengthen
soils. If most of the foundations need work, repair costs
could reach $70 million. Spokesperson Perry Dawn Brown said
the authority expected general-engineering consultant URS
to cover the costs. San Francisco-based URS has agreed to
pay for field tests and design of foundation repairs but not
yet for actual repair costs.
Until a settlement is reached, the authority is looking at
ways to cover the costs without relying on taxes, tolls or
the state Department of Transportation. Brown said the authority
will ask to restructure its $100-million loan from FDOT and
may sell bonds in 2005.
PCL continues to cast girders in its yard and do earthwork,
said Jerry Harder, district vice president. "We have
casting until the end of the year," he said. Still, PCL
has had to lay off about 40 employees. Source:
Engineering News-Record.
Florida Contract Activity
Declines in September
The overall value of contracts for future construction in
Florida dipped significantly in September, McGraw-Hill Construction
reported. Perhaps impacted by a series of major hurricanes
that hit the state, even the soaring residential category
declined, as the most recently monthly figures for Florida
contract activity tallied 16 percent below last September's.
In September, the value of residential contracts decreased
by 8 percent compared to September 2003. The most recent month's
report indicated an estimated $2.9 billion for this sector,
down from the roughly $3.2 billion of a year ago. Nonbuilding
construction was also a major contributor to the overall downturn,
decreasing 63 percent from last year to total just under $332.3
million, compared to the year-ago figure of $892.4 million.
Nonresidential was the only market to show a positive pace,
increasing 4 percent to total roughly $798.1 million, compared
to last year's $769.4 million.
Even so, for the first nine months of 2004, overall activity
in Florida has increased by 15 percent, from the $37.6 billion
total reported in this period in 2003 to 2004's $43.3 billion
total. To date, however, residential remains the only positive
sector, up 26 percent so far in 2004, with roughly $30.6 billion
in activity reported. With its 4 percent increase in September,
nonresidential is now even with 2003, with an estimated $8
billion in contracts reported to date. The nonbuilding sector,
after turning positive for the year in August, is now 9 percent
behind 2003's pace, with a roughly $4.7 billion total.
Eby May Sell Florida, Texas Operations
Martin K. Eby Construction Co., a contractor that was founded
during the depths of the Great Depression and became one of
the most respected open-shop employers in the industry, is
struggling under the triple blow of contract cost overruns
and lost surety and bank credit. The Wichita, Kan.-based company
said it is currently exploring sales of its Florida and Texas
operations to try to cut expenses and boost its balance sheet.
Eby executives say the company has unpaid claims of about
$25 million on two recently completed public projects in Florida
and Texas. When the St. Paul Cos., the contractor's key surety,
merged with Travelers Property Casualty Corp. earlier this
year, everything changed. At a July 28 meeting with Eby, the
surety declined to issue any more payment or performance bonds.
"We have bid work where no bond is needed but of course
that limits our cash flow and ability to maintain normal operations,"
said Jim Grier, the company's chairman.
The loss of surety credit constituted a significant financial
event triggering suspension of the company's line of credit
by its key lender, Wichita-based Intrust Bank. Some of Eby's
co-sureties have been providing the company with working capital,
said Grier.
Rich Bean, Eby's president and chief operating officer, termed
the triple misfortune of cost overruns and lost surety and
bank credit a "kind of perfect storm."
Texas and Florida were not new markets to the contractor.
Grier said the company's claims on both bad projects in those
states are based on several causes including differing site
conditions. One of the jobs is a $36-million contract to build
a bridge over a coastal waterway in Jacksonville, Fla., for
the Jacksonville Transportation Authority. Eby has filed a
lawsuit over part of its claim in U.S. district court in Jacksonville.
The other project involves work on a light-rail transit line
for the Dallas Area Rapid Transit agency. Neither agency could
be reached for comment.
Bean, the Eby family and Grier, who is related to the Eby
family by marriage, are owners of the company stock. They
plan to continue operations in Kansas and build up business
again after settling claims and repaying sureties. The company
had 2003 revenue of about $171 million. Source:
Engineering News-Record. By Richard Korman
16-Screen Megaplex Planned for Boynton
Beach Mall
Simon Property Group, a real-estate investment trust based
in Indianapolis, and Muvico Theaters of Fort Lauderdale recently
announced plans for a 16-screen megaplex theater at Simon's
Boynton Beach Mall in Boynton Beach.
The 16-screen complex is estimated to have a total seating
capacity of approximately 3,800 seats.
Construction Starts on Paul J. Hagerty
High School
Construction began in October on a new 2,500-student Paul
J. Hagerty High School in Oviedo. The new school is an expansion
of Chiles Middle School that was designed by SchenkelShultz
Architecture of Orlando to be the future anchor of the new
high school.
The expansion more than doubles the school's size from the
original size to 352,000 sq. ft., and includes two new two-story
classroom buildings, media center, performing arts center
with auditorium, 1,700-seat gymnasium, 3,000-seat football
stadium and other amenities.
The project is scheduled to be complete by the 2006-2007
school year.
MGE Architects to Design West Kendall Baptist
Hospital
MGE Architects of Coral Gables has been retained by Baptist
Health South to design West Kendall Baptist Hospital in Miami.
The 80-bed, acute-care hospital will include a central energy
plant and a medical office building. The project is expected
to be completed in 2008.
Broward Co. Retains Designer for Family
Court Facility
Broward County recently retained a joint venture of Atlanta-based
Heery International, Spillis Candella and Partners of Coral
Gables and Cartaya and Associates of Fort Lauderdale to handle
both master planning and design services for the Broward County
Family Court project.
The facility will include 10 courtrooms, 28 hearing rooms
and 15 judge suites. In addition, space will be provided for
the sheriff and holding areas, administrative support space
and clerk functions.
Developer Breaks Ground on The Landmark
HomeDevco Development Corp. recently broke ground on The
Landmark at the Gardens, its luxury high-rise condominium
project in Palm Beach Gardens. The Landmark development follows
HomeDevco's Downtown at the Gardens project, a 350,000-sq.-ft.
retail complex already under construction.
The towers will feature 166 residences ranging in size from
1,870 sq. ft. to more than 5,000 sq. ft.
Clancy & Theys to Build LaColonnade
Condo in Satellite Beach
Clancy & Theys Construction Co., with offices in Orlando,
has been selected to build the LaColonnade condominium project
in Satellite Beach in Brevard County. The post-tensioned concrete
structure project totals roughly 120,000 sq. ft. The project
includes installation of underground stormwater retention
tanks and erection of a two-story parking garage with storage
below the building.
The two six-story buildings incorporate 20 residences with
angled ocean views. Construction on LaColonnade began in August
with a projected completion date of October 2005.
Also, the company recently completed construction on the
relocation and refurbishment of three passenger boarding bridges
for Spirit Airlines at the Orlando International Airport.
The project was completed in October.
|