|
Duke Power Spending Big In Emissions
Control Effort
A North Carolina utility is spending nearly $2 billion to
clean its emissions. A federally driven $450-million selective
catalytic reduction (SCR) project, the largest in the U.S.,
is now nearing completion and another $1.5-billion state-driven
sulfur dioxide reduction program is just ramping up.
Duke Power, Charlotte, has started engineering on a $1.5-billion
program designed to reduce nitrogen oxide emissions by 30
percent and sulfur dioxide emissions by 70 percent at its
seven North Carolina coal-fired powerplants. The effort was
driven by state clean air legislation passed last year that
also freezes rates for five years. The program will be amortized
through existing rates and costs recouped in a flexible manner
to keep earnings stable. "We'll be scrubbing 12 units
and likely do selective noncatalytic reductions (SNCRs) on
24 units," said Mary Katherine Green, Duke spokesperson.
Persistent smog, acid rain and air quality problems in the
western part of the state drove the cleanup. On hot, sunny
days NOx combines with organic chemicals in the air to form
ground-level ozone, a component of smog. Sulfur dioxide also
contributes to smog and acid rain. SCRs channel hot flue gasses
and injected anhydrous ammonia through ceramic honeycombed
bricks to convert more than 80 percent NOx into nitrogen and
water. SNCRs inject ammonia into the gas stream, converting
NOx to a lesser degree, or about 25 percent. Wet scrubbers
bubble flue gas through molten limestone to transform SO2
into gypsum and water. "We used SCRs where the largest
emissions were and where we could do the engineering,"
said Thomas C. Williams, Duke communications manager. "SNCRs
are more cost-effective on smaller and older units and scrubbers
will be used on all large plants."
Duke will perform SNCR engineering work in-house but Alstom
Power, Knoxville, Tenn., will provide the engineering, equipment
scoping and site testing for the scrubber work. Plants involved
include: the five-unit Allen station, unit number five at
the Cliffside station, the four units at the Marshall station
and the two units at Belews Creek station. Contracts totaling
about $300 million to $400 million will be let in the next
six months for the Marshall work. Work at all plants must
be completed by 2013.
Duke is wrapping up about $550 million in federally driven
SCR work at two plants. Unit five at Cliffside, a 760-Mw plant,
is finished and phase two at Belews Creek, a two-unit, 2,400-Mw
plant, is nearing a June 2004 completion. Belews Creek is
Duke's largest coal-burning plant, consuming up to 19 tons
of coal per day. To comply with federal clean air standards,
Duke is reducing NOx emissions by 80 percent there.
Charlotte-based Duke/Fluor Daniel heads the three-year engineer-procure-construct
deal at Belews. Because of a tight site, the SCRs had to be
built over existing boiler buildings and precipitators, resulting
in 300-ft-tall towers that were structurally integrated into
the plant. "The SCR creates a huge sail so we had to
drill and grout several hundred rock anchors about 30 ft to
40 ft deep in bedrock," said Harold L. Backman, Duke
project director. Over 7,000 tons of structural steel and
44,500 linear ft of piping were used on unit one. It has been
operating at full capacity since August.
The 29-year-old plant provides power to more than 2 million
homes in the Carolinas. It cost about $357 million to build.
Duke also is replacing boiler tubing and controls and completing
a precipitator refurbishment. Because of the project size
and location of the SCRs, a Manitowoc 21000 crane with a 420-ft
boom and jib was needed to lift equipment and ductwork fabricated
on the ground. The rig was last used in the cleanup at the
World Trade Center.
"This is the largest SCR project in the U.S. owing to
the electric output of the station and the tight site and
the capacity for four layers of catalysts," said Ray
Hollins, general manager of the joint venture. "We upsized
the four induced draft and four forced draft fans and motors
and added variable frequency drive to the ID fans to better
control speed." He notes they also replaced the air heaters
to increase boiler efficiency. That required significant interior
plant demolition and increased structural steel on the SCR
and building to support the heaters. The SCR currently uses
only two levels of catalysts but two more levels are available
for future management.
Duke/Fluor Daniel also completed the Cliffside work. In July
officials announced the venture would disband because of a
decline in powerplant construction. The transition could take
two years. Source: Engineering
News-Record. By William J. Angelo.
Court Approves J.A. Jones Sales to
Fluor and Turner
U.S. Bankruptcy Court in Charlotte has approved a $10-million
bid by Turner Corp., Dallas, to buy the assets of Tompkins
Builders, Washington, D.C. Tompkins is a unit of Charlotte-based
J.A. Jones Inc., which filed for Chapter 11 in September.
Fluor Corp.'s $4-million bid for the international division
of J.A. Jones Construction Co. was also approved. It has $135
million in estimated revenue in fiscal 2003.
Standard & Poor's, which, like Engineering News-Record
and Southeast Construction, is a unit of the McGraw-Hill Cos.,
said the purchase will have "no immediate impact"
on Fluor's outlook. Source: Engineering
News-Record.
Peterson Associates to Design Heart
and Vascular Center
Moses H. Cone Memorial Health Systems has announced plans
to upgrade their heart and vascular center in Greensboro,
N.C. Peterson Associates of Charlotte was selected as architect
for this estimated $26 million project, which involves a new
28-bed, 61,000-sq.-ft. cardiac care and transitional care
unit.
Construction could possibly start in February and be completed
by April 2005. Source: Engineering
News-Record.
|