|
CATS: Coming Down the Line
First Phase of Charlotte's Light-Rail
System Heading for Fall Completion
By Bea Quirk
Considerable excitement has justifiably surrounded Charlotte's
development of a comprehensive, $4 billion light-rail system.
The city's planning efforts vaulted the project ahead of
those in other cities for the critical federal funding necessary
to build such capital-intensive systems. (For more information
see “All Aboard - Light Rail Comes to Charlotte” and “Mass Transit: All Aboard?” in the May
2006 issue of Southeast Construction.)
However, as the $400 million-plus first phase has turned
the corner into its last leg, some of the excitement has given
way to negativity.
Controversy broke out this fall over construction of the
light-rail line - called Lynx - when the Charlotte Area Transit
System announced in September that the probable final cost
of the 9.6-mi-long line - the first of several proposed -
would reach $462.7 million, an 8.4% increase over the previous
announced budget of $426.8 million. When completed in about
2035, the system is expected to cost more than $4 billion.
CATS and the City of Charlotte contend that it was design
errors by California-based Parsons Transportation Group that
played a key role in the latest cost overruns, although they
acknowledge dramatic increases in the cost of concrete, steel
and labor also contributed. Tension between the two date back
to 2004, and CATS took Parsons off construction management
in early 2005. Parsons received $38 million for its work as
the designer of record and some initial construction management.
According to CATS public relations manager Jean Leier, Parsons
submitted bid documents that were incomplete and required
expensive change orders and field fixes; delivered poor plans
with errors and omissions; and failed to coordinate design
between contracts and packages.
CATS chief executive Ron Tober offered to resign over the
latest cost overruns, but Charlotte City Manager Pam Syfert
refused to accept it.
With the threat of a lawsuit pending, officials from Parsons
and the city are otherwise staying mum. But in an Oct. 11
letter to Parsons, city attorney Mac McCarly wrote, "We
are in the process of cataloging specific errors and omissions
to comply with the notice provisions of the contract. That
list is not yet complete, but when it is, we will send it
to Parsons immediately."
Less than two weeks later, Parsons responded in a prepared
statement that read, in part: "It is clear to us that
Parsons is wrongly being blamed for problems and costs resulting
from decisions made by CATS in the face of tight budget constraints,
an aggressive schedule and extraordinary economic conditions
that drove up costs on all large public work projects."
It appears the war of words is at an end for now. "We
have shared our concerns with Parsons, and in the months ahead,
the various lawyers of both organizations will be talking
to each other," Tober said in January. "But we want
to wait until the project is done to see where we are and
to understand fully the scope of the issues and concerns."
Tober adds that the recent cost increase "isn't bad
in comparison to other projects, including highways."
He says the new cost figure has an 80% probability of being
met successfully, as required by the federal government, but
he is hopeful the final figure will actually be less. "We
are making scope adjustments and doing value-added engineering,"
he says.
To meet the shortfalls, CATS is issuing more long-term debt
than initially planned, plus there is a $16 million contingency
fund, which Tober says, "We'll be careful about using."
Construction of the light-rail line is funded by a ½%
countywide sales tax approved by voters in 1998. In addition
to those funds, CATS received $200 million from the federal
government and $107 million from the state.
While the final ramifications of the cost overruns are yet
to be seen, CATS is moving forward to complete the South Corridor
Line for a November opening after starting work in early 2005.
The line connects the center city with Interstate 485 and
runs parallel to a Norfolk Southern Rail line right-of-way
along a major thoroughfare.
At the end of 2006, about 25% of the track had been laid.
Signal houses and power substations had been installed. The
$30 million vehicle maintenance facility opened in January,
soon after the first 10 of 16 cars had been delivered and
the start of test runs. Canopies began going up at some of
the 15 stations as well.
Among the contractors are Charlotte-based Crowder Construction,
which is building a parking garage at the I-485 terminus;
Charlotte-based Edifice, which constructed the vehicle maintenance
facility; and Archer Western Contractors, part of the Chicago-based
Walsh Group, which handled road beds, bridges and stations.
Archer Western has two contracts: $106.8 million for the roadbed
facilities and trackwork and $44.1 million for building 15
stations plus park-and-ride lots. The Edifice contract was
r $30 million.
Although the completion date is several months away, Tober
says he has already begun thinking about lessons learned in
preparation for building the next lines. One of the biggest
hurdles was negotiations with Norfolk Southern, whose track
runs just 40 ft away from the light rail line for about 3
mi. Contentious issues included the sale of land, spatial
separations, operating rights, liability insurance and the
use of flagmen.
But the greatest change Tober sees for the future construction
is what he calls "using an alternative project-delivery
system." For the South Corridor, CATS went with a design-bid-build
system, but in the future, he says a construction manager-at-risk
will be hired early in the process.
"You'll have one entity in charge of everything, and
that will mean better design coordination," he adds.
"The lack of coordination among design packages was the
biggest issue we faced, and it cost us significant money."
In late 2006, the Metropolitan Transit Commission, the governing
board of CATS, voted to begin efforts to pursue two additional
lines - an extension of the South Corridor line from downtown
to the University of North Carolina at Charlotte and a commuter
rail line serving the northern towns of Mecklenburg County.
Although government funding was uncertain at the end of 2006,
CATS officials are hoping to begin some initial work by midyear.
Positive Developments
Meanwhile, as the light-rail line progresses through this
late-stage controversy, privately developed projects are rising
adjacent to the track.
Tina Votaw, CATS transit-oriented-development specialist,
estimated the value of new development going along the line
at between $500 million and $1 billion.
That estimate may be conservative. In the South End alone,
according to Charlotte Center City Partners, there is approximately
$712 million of construction projects either proposed or under
way. That includes 10 residential projects and more than 300,000
sq ft of retail.
"There is tremendous interest in the light rail corridor,
particularly among developers who have witnessed or participated
in the success of real estate ventures along transit lines
in Washington, Denver, Portland, Dallas and other cities,"
observes Frank Warren, a Charlotte-based real estate consultant.
"There is a growing share of the market that will pay
a premium for urban amenities and convenience, and it's not
just young professionals. Developers are capitalizing on two
fundamental societal shifts - people placing higher value
on time - reducing the commute - and the environment - saving
the remaining resources."
The South End is an area-and a special tax district-just
outside the center city. Its redevelopment from an abandoned
industrial district to a neighborhood of businesses, residences
and entertainment facilities began several years ago. It is
where most of the new development along the line is occurring.
For example, Abbott Street Professional Townhomes-16 live/work
units-will be completed this spring. The project is part of
a larger development, Camden Square, which is being developed
by MECA Properties and built by the Sidbury Group, both of
Charlotte, with a price tag of more than $6 million.
Also, construction begins early this summer on what Charlotte-based
Crescent Resources simply calls C, a mixed-use village at
East Bland Street and South Boulevard that will have 420 residential
units, 25,000 sq ft of retail and 10,500 sq ft of office.
To encourage development along the line, the City of Charlotte
introduced in 2005 a new zoning classification called transit-oriented
development. Votaw says the city is receiving two or three
applications a month for this kind of rezoning, which allows
higher density, relief on parking requirements and stricter
streetscape requirements along the line.
|