|
More "Home" for Holmes
Owner Expectations Drove $130 Million
Project to a New Standard
By Scott Judy
For several years, hospitals in the Southeast have utilized
cues from the hospitality industry to design and build facilities
that are warmer and friendlier places that provide a more
healing environment.
Of course, it's also big business, and updated facilities
are seen as an investment in a hospital's future financial
health.
In Melbourne, Fla., officials with Holmes Regional Medical
Center pushed their design and construction team to go beyond
even the latest trends on its $130 million addition of a heart
hospital and emergency/trauma center. The facility has been
operational since November, with final completion scheduled
for March.
"They certainly wanted us to propose things that were
unique or aren't normally seen in a patient room, in a nursing
setting," says Gary Cox, vice president and project manager
for HKS Inc. of Orlando, the project architect.
Tom Mills, vice president for facilities and planning at
Holmes Regional, says the goal was definitely one of patient
comfort.
"The expectations were that it be less intimidating
to the patient and have the experience be as pleasant as possible,"
he says. "Within reason, we tried to bring in more residential
and less institutional feel the best we could."
One example was the inclusion of 27 private holding beds for
catheterization preparation and recovery. Whereas in the past
these accommodations have usually been ward-type settings
of cubicles and curtains, and little privacy, these areas
at Holmes will be small private rooms with walls and a closing
French door, television sets - and even a ceiling painted
with a scenic touch to help ease the minds of the patients
about to undergo this procedure.
"It's a big move trying to satisfy patients and their
families when they go in for something like a catheterization,
which is a high-stress situation a lot of times," Cox
says. "We were able to provide private rooms for all
of those folks and achieve something special in terms of the
finishes."
Mills said the inclusion of these cath prep and recovery
rooms happened because the hospital's clinicians and physicians
pushed for them.
Additionally, the original full-size mock-up of a patient
room that HKS delivered to the owner for review prior to construction
"wasn't at the level where they wanted it to be,"
Cox says.
While this resulted in major changes, Mills appreciated this
step in the process. "We knew exactly like it would be,"
he says. "That helped a lot in making our decisions."
Patient rooms now feature custom cabinetry that can hide
away much of the installed equipment, a full-size sleeper
couch, plasma televisions with pay-per-view capability, computers
with wireless Internet connections, high-end bathroom countertops,
Italian marble tile finishes and works of art. Wireless systems
enable patient care physiological monitoring and tracking
of the nurses.
The Project
Bovis Lend Lease of Orlando started work in mid-2004 with
foundation work and received the final building permit in
November of that year.
The contractor held a $92 million construction management
contract for the 402,000-sq-ft project, which entailed construction
of an eight-story heart hospital with 108 new, all-private
patient-room beds and a 43,000-sq-ft emergency/trauma center
with 58 treatment beds.
The heart hospital includes four cardiovascular and two general
operating rooms; a 14-bed cardiovascular intensive care unit;
seven cardiac catheterization labs with 27 holding beds; three
floors of patient rooms; an additional floor shelled in for
36 future patient beds; and a rooftop helistop. (Bovis had
been involved with preconstruction since 2002, when the original
vision for the project was much different: a medical office
building with parking garages and connector bridges. Market
demand for cardiac services forced the project's evolution.)
Karen Voit, senior project manager for Bovis, says the construction
manager set a roughly two-year goal for the project-one year
to erect the structure and another to complete the interior
and exterior finishes. Luckily, that schedule had some extra
time built into it, says Mike Cockman, senior superintendent
for Bovis.
"We probably would have beaten that schedule by quite
a bit had nothing changed," Cockman says. "But we
were able to absorb all of the (design) changes and still
maintain the original date." He adds that Bovis received
approximately 32 sets of new drawings, revisions and other
items after the start of construction that impacted the schedule.
The contractor also absorbed the close calls of two hurricanes
in 2005, both of which required the lowering of the project's
tower crane and had a significant impact to the job's progress,
Cockman adds.
"It seems like we were either cleaning up after a storm
or getting ready for the next one for about two months,"
he says.
The ability to withstand a hurricane would extend to the
project's design and construction. Partly because Holmes is
the highest-rated trauma center between West Palm Beach and
Daytona Beach, the owner required enhanced hurricane criteria
for all exterior envelope materials and systems, including
the doors, windows, louvers and precast materials. The project
was designed and built to remain structurally sound against
wind gusts of up to 160 mph.
One method Bovis utilized to get the structure up as quickly
as possible was the use of two separate crews to simultaneously
erect the precast concrete panels on two opposite sides of
the building. Voit says the contractor tried to gain as much
time as possible during the first year, so it could have more
flexibility during the second.
It would need it. In addition to the design changes to the
patient rooms and related oversight of these upgraded finishes,
Bovis also had to accommodate the installation of new equipment.
Like other health-care providers, Holmes wanted to ensure
it had the latest and best equipment available, so it held
off on purchases until as late as possible.
While Voit says the pushed-back installation of equipment
caused some level of "struggle" and "frustration"
because of the need to put some construction on hold to accommodate
this, Cox with HKS says it was well worth it.
"A lot of hospitals will sell themselves short in terms
of being on the cutting edge of technology," he says.
"This hospital has been far ahead on technology and has
been able to incorporate that into the hospital design-not
without pain."
Just as a new hospital is big business for the health-care
providers, a quality end-product is good business for contractors.
In the case of Holmes, Mills says the hospital based much
of its original selection of Bovis and HKS on the individual
personnel committed to the project.
"I can't imagine going through a big project like this
without those people," Mills says. "We have other
big projects on our agenda, and we're trying to keep the same
team in place to continue to work with us."
|