|
Airport Construction: No Delay Expected
for Southeast
Throughout the Southeast, airports
are undertaking construction projects to upgrade busy facilities.
By Debra Wood
Spurred by rebounding air travel, Southeast airports have
launched multiple projects to handle increasing numbers of
passengers and to upgrade baggage systems, as passenger volume
is expected to nearly double in the next 10 years.
"The Federal Aviation Association has predicted a billion
passengers annually by 2015," said Eryn Travis, spokesperson
for the American Association of Airport Executives in Alexandria,
Va. "To meet that demand, the aviation system has to
add capacity, and that's an important issue for the aviation
community, adding runways, taxiways."
North Carolina
Piedmont Triad International Airport in Greensboro, N.C.,
has undertaken multiple projects, totaling between $175 million
and $200 million, to accommodate a new FedEx Mid-Atlantic
hub, said Mickie Elmore, director of development for the airport.
The work includes grading the 175-acre FedEx parcel, building
a 9,000-ft.-long runway and 1-mi.-long connecting taxiway
and relocating a major thoroughfare, said Elmore, who expects
the project will be complete by 2009.
Vecellio & Grogan of Greensboro, N.C., has moved about
4 million cu. yds. of dirt to level the FedEx parcel, Elmore
said. The airport authority expects FedEx to begin construction
this fall.
Vecillio & Grogan has also holds the contract to move
a 2-mi. section of Bryan Boulevard. That job was scheduled
for completion in October.
D.H. Griffin Cos. and EME, both of Greensboro, are demolishing
old warehouse and office buildings to prepare the area for
final grading. Phase three, scheduled to go to bid in 2007,
will include paving and lighting the runway.
Elmore expected W.C. English Construction Co. Inc. of Lynchburg,
Va., to complete phase one of the taxiway, constructing a
bridge over an interior roadway, by the end of the year. Meanwhile,
Blythe Construction Inc. of Charlotte, N.C., has begun working
on phase two of the taxiway-site clearing and building a tunnel
under the taxiway.
Archer Western Contractors of Atlanta received a $257.6 million
contract from the Raleigh-Durham International Airport Authority
to update and expand Terminal C.
Work began in April, with steel scheduled to rise in the
fall. Scheduled for completion in 2010, Terminal C will become
the airport's main terminal and include an expanded federal
inspection facility to process more international passengers.
The project will more than double the size of the terminal
from 330,000 sq. ft. to 890,000 sq. ft.
Shelco of Charlotte began building a $34 million, five-level,
3,000-car parking garage at Charlotte-Douglas International
Airport in January, said Galen Heying, vice president of project
management for Shelco.
The 1-million-sq.-ft., cast-in-place, post-tensioned concrete
facility will consume 35,000 cu. yds. of concrete, he added.
It is set to open in April.
Florida
Work continues on Miami International Airport's North and
South terminals.
"We've made a lot of progress on the South Terminal,"
said John Cosper, deputy director of capital improvements
for Miami-Dade County Aviation Department. "We added
$105 million in scope to the South Terminal project."
That brings the total construction cost to about $800 million.
Incorporating the new fiber-optic communication, security
and facilities system improvements has pushed the completion
date back to February, Cosper said.
The construction manager at risk, a joint venture between
Parsons Corp. of Pasadena, Calif., and Odebrecht Construction
Inc. of Coral Gables, Fla., has turned some of the space over
for airlines to begin build-out of their sections, Cosper
said.
In 2005, after taking over construction responsibility for
the North Terminal from American Airlines, the Miami-Dade
Aviation Department awarded Parsons-Odebrecht a $542 million,
four-year managing-general-contractor contract for that 3.4-million-sq.-ft.
terminal.
But there have been some difficulties.
"We've had significant issues with our budget due to
high bids," Cosper said. "In some cases, we have
been successful in negotiating them down, but in others cases,
we are rebidding."
Cosper cited escalating material prices and labor shortages
due to South Florida's booming construction industry as factors
in pushing costs up.
Miami-Dade Aviation has rephased the work and will likely
cut out portions of the project, such as architectural structural
changes, to bring the cost closer to budget, said Cosper,
adding that it would not eliminate the four major components:
49 gates, a baggage-handling system, a people mover on the
roof and a federal inspection services facility.
Next year, the airport will close the North Terminal's Concourse
A, which will pull the project out of the aircraft-operating
area, easing security requirements, Cosper said. He added
that the closing should save two years and as much as $200
million.
The new goal for completion of the North Terminal stands
at 2012.
Miami-Dade Aviation began negotiations in August with Parsons-Odebrecht
and Sumitomo/Mitsubishi to design, build, operate and maintain
for 20 years a people mover from the airport to the 1.2-million-sq.-ft.
Miami Intermodal Center.
Earth Tech of Long Beach, Calif. is providing program management
services for the MIC for the Florida Department of Transportation,
said MIC spokesperson Ric Katz.
Turner Construction Co. of Miami performed foundation work
for the $221 million Rental Car Center, the first building
to be constructed, Katz added. FDOT planned to select a contractor
in late September to build the facility and for construction
to begin in January, with completion in 2010, he said.
The next phase of the MIC, a central station, is still under
development, Katz added.
Neighboring Broward County also has launched a major airport
expansion plan. The airport has experienced a tremendous influx
of cruise passengers and South American passengers, said Barry
Lagerstedt, director of planning and development for the Broward
County Aviation Department.
Lagerstedt expects to take a $2.5 billion master plan to
the board of county commissioners in September.
Meanwhile, several construction projects are under way.
Broward County expected a $10 million tollbooth relocation
project by a joint venture between James A. Cummings of Fort
Lauderdale, and Centex Construction, Plantation, would wrap
up in October. It was undertaken to prepare for future pedestrian
bridges, said airport spokesperson Gregory Meyer.
Triple R Paving of Davie received a $25 million contract
in May to extend an existing taxiway and upgrade drainage
and infrastructure on the airport's west side. Completion
is scheduled for early 2008.
Skanska USA Building of Dania Beach is constructing a $20.5
million inline baggage system at terminals 2 and 3. The project
began in A pril and will finish in January 2007.
At terminal 4, Skanska is upgrading ticket counters, expanding
the customs and federal inspection services areas, and installing
a new baggage screening system. The $30 million job will wrap
up in December 2007.
Up the coast in Palm Beach County, James A. Cummings of Fort
Lauderdale began constructing a $61 million, seven-story,
precast concrete parking garage with about 3,500 spaces, said
John Church, vice president of Cummings.
The project includes building pedestrian bridges to an adjacent
parking structure and the terminal, he added. Church expects
to finish the 1.3 million-sq.-ft. project by the end of 2007.
Across the state at Pensacola Regional Airport, Phoenix Construction
Services of Lynn Haven, Fla., is tearing out and replacing
a 6,853-ft.-long runway, said Ted Schoppe, senior project
manager. The company started the phased job in April and will
complete it next May, he said.
Crews will complete about half of the runway and then have
45 nights to work on the sections abutting an active intersecting
runway, Schoppe added. That work will begin after the last
flight leaves and crews must have the area open and safe before
the first morning flight, he added.
The project also includes pipe jacking reinforced concrete
storm-drainage pipes under the active runway, using a tunneling
machine that cuts through the dirt, pushes the pipe and maintains
a constant pressure, Schoppe said. There are two 130-ft. runs
of 54-in. pipe, one 177-ft. run of 84-in. pipe and one 125-ft.
run of 72-in. pipe, he said.
Useful sources:
Raleigh-Durham International Airport
http://www.rdu.com/
Hartsfield-Jackson Atlanta International Airport
http://www.atlanta-airport.com/default.asp?url=http://www.atlanta-airport.com/fifth/ceela2.htm
|