|
A New Symbol for Law and Order
By Debra Wood
As part of a comprehensive plan to upgrade court facilities
to handle increasing caseloads, the General Services Administration
is building an $87.2 million annex to the George C. Young
U.S. Federal Courthouse & Federal Building in Orlando.
"The concept of the project was to create a new campus
environment for the U.S. courts in Orlando," said Bob
Egleston, project manager for Heery-HLM Design of Orlando,
one of the lead design firms. "Currently there are a
number of courts and court-related agencies located in leased
space in the downtown area. When you couple that with the
fact the courts are growing, there was a definite need for
a new courthouse."
Thirty-three courthouses are listed on the GSA's most recent
project plan. In October 2004, the Judicial Council, a Division
of the U.S. Courts, issued a two-year moratorium on courthouse
construction, ending plans for new facilities not already
under way. Security factors increased rental costs, according
to Gary Mote, spokesperson for GSA.
GSA selected a design concept developed by Heery-HLM and
Leers, Weinzapfel Associates of Boston, in 2000, after a design-excellence
selection process, during which independent, private-sector
architecture professionals evaluated various proposals. Mote
said that the design adheres to recommendations made in the
U.S. Courts Design Guide, developed by the federal judiciary
and an outside panel of experts.
Hensel Phelps Construction Co. of Orlando received the $77
million construction manager/general contractor contract for
the new six-story building, with a basement, and a 132-car
parking facility and began construction in March 2004, said
Richard Lewis, project manager for Hensel Phelps. It completed
the garage during the first year, he added. The 336,000-sq.-ft.
building is scheduled for completion in January. Once finished
and people in the existing courthouse move, Hensel Phelps
will complete a linked passage way between the two structures.
Three hurricanes that year set the job back about three weeks,
but Hensel Phelps made up the time.
Original plans called for the City of Orlando to take stormwater
off site, through pipe to a retention pond about two blocks
away. However, the city ran into hazardous material, delaying
the work for seven months.
"We had to detain the water on site until it was done,"
said Lewis, explaining that Hensel Phelps built a retention
pond on site. "We had to deal with that during erection
of the precast and skin. It didn't delay us, but there were
associated costs."
The pond consuming about a quarter of the parcel, and restricted
easy access to portions of the building. Hensel Phelps brought
in a larger crane to reach all of the elevations. The retention
pond also delayed hardscaping. Once the city completed its
work, Hensel Phelps filled in the onsite pond.
Design
The Orlando courthouse design balances security needs with
a desire to provide a community-friendly building. A two-acre
landscaped outdoor courtyard/park will connect the new building
with the Florida A&M University College of Law.
"We are trying to make [courthouses] get away from the
bunker mentality, with no windows, to something aesthetically
pleasing and functional," Mote said.
Architects sought and incorporated suggestions from judges
before designing the new facility and renovation of the existing
courthouse for use by other courts and federal agencies.
"Judges are always involved, and they play a major role
in the design of the building," Egleston said. "They
are, ultimately, in charge of how the courts and related agencies
function within the building. They want to make sure the building
functions correctly, that the public has good access to areas
they need, and that security for prisoner movement works well."
The judges also requested good lines of sight and acoustics
in the courtrooms, Egleston said. Heery-HLM completed computer
modeling and built a full-size, rough mock-up of a courtroom
out of plywood and invited judges and attorneys to visit it,
sit in various places and evaluate the different lines of
sight.
"We verify there is good line of sight for all the critical
functions," Egleston said. "When we're building
it, we've already worked those things out in a full-size [courtroom]
so, hopefully, there's no need to make major changes once
the building is built."
Most of the full-height walls in the courtroom areas received
sound insulation and extra drywall on both sides and were
sealed with caulk at the top and at all penetrations, Lewis
said.
"The designers worked very diligently to make sure no
other mechanical ductwork or piping was run over the courtrooms
to create any unnecessary noise," Lewis said. "It
moves those materials into other areas that become congested."
|
Team Box:
Owner:
General Services Administration, Washington, D.C., contracted
through the Atlanta office
Construction Manager/General Contractor: Hensel
Phelps Construction Co., Orlando
Architect of Record: Heery-HLM Design, Orlando
Lead Designer: Leers, Weinzapfel Associates,
Boston
Structural Engineer: Heery-HLM Design, Orlando
MEP Engineer: Heery-HLM Design, Orlando
Steel Supply and Erection: Allstate Steel Co.,
Jacksonville, Fla.
Concrete Formwork: Skyline Forming, Lakeland,
Fla.
Concrete Placement: Hensel Phelps Construction
Co., Orlando
Rebar installation: Liberty Steel Erectors, Orlando
Mechanical: Harper Mechanical Corp., Sanford
Sheet Metal: Lapin Sheet Metal Co., Orlando
Electrical: Bergelectric Corp., Orlando
Plumbing: Nash Plumbing & Contractors, Coleman,
Fla.
|
Construction
The reinforced, cast-in-place concrete building, with a structural-steel
roof, sits on about 174 displacement piles, Lewis said. Additional
structural elements and supports provide blast hardening for
the building. Large flower boxes in front also serve to keep
vehicles away from the building, Mote said. Neither Mote,
Lewis nor Heery-HLM could reveal other security features.
However, the building was designed to meet the strict security
criteria outlined in the Interagency Security Committee blast-protection
guidelines.
Floors three through six contain four courtrooms each. In
addition, on the third floor, there is a library, which could
be built out in the future for another courtroom, and a special
proceeding room on the third floor.
The courtrooms open onto a four-story lobby. As in historic
courthouses, with their high steps and stately columns, Mote
said the GSA hopes the public will embrace the lobby area
as a place to hold private functions, such as wedding receptions.
On the east side of the building, a 48-ft.-tall by 20-ft.-wide
laminated art-glass mural designed by artist Al Held and fabricated
by Architectural Glass Art of Louisville, Ky., provides a
visual feature in the atrium, after the public passes through
security.
"When the sun comes up, you're going to get some brilliant
light coming through that window. It's very cathedral-like,"
Egleston said.
The work was commissioned as part of the GSA's Art in Architecture
Program. GSA allocates .5 of 1 percent of the estimated construction
cost to one or more works of art for new or substantially
expanded buildings.
Held created five paintings the panel could choose from for
the stained-glass window, Egleston said. The artist donated
the other four paintings to create smaller art-glass punched
windows on the ground floor, he continued.
However, that left one window without art glass.
"[Held] agreed at no extra cost to provide a sixth painting
to fill in the last window," Egleston said. "Unfortunately,
during that process he met an untimely death. But the painting
was far enough along, that his studio could complete it. All
of the windows will have an Al Held stained-glass design."
The courthouse also includes a detention wing for arrangements,
special elevators for prisoners and holding cells for courtroom
appearances.
Architectural precast concrete and curtain wall cover the
exterior. A cast-in-place concrete tower clad with white precast
projects 30-ft. above the building, Lewis said. Four open
cut outs and a skylight provide natural light to the main
entry way below. Security guidelines require a reduced amount
of glass, so the skylight offers a safer way to create an
open, airy feeling.
All jurors and the public will enter through a security area
in that space. Heery-HLM included queuing space, so people
will not have to wait in the elements before passing through
the checkpoints.
About 280 workers toiled on the project at its peak.
Useful sources:
U.S. Courts Design Guide
http://www.gsa.gov/Portal/gsa/ep/contentView.do?P=PME&contentId=15102&contentType=GSA_DOCUMENT
|