|
Rosen's Shingle Creek Resort Rises
By Debra Wood
The 1,495-room Rosen Shingle Creek resort and convention
center in Orlando opened in September, five months ahead of
schedule to coincide with owner Harris Rosen's birthday.
"The time frame was the most challenging piece of the
construction," said Bruce Holmes, executive vice president
of general contractor WELBRO Building Corp. of Maitland. "It's
a large building to build in that period of time, and we built
it during periods of rapid material cost increases and a labor
workforce that is thin, based on the amount of construction
going on in Central Florida."
The 230-acre resort includes a 1.1 million-sq.-ft., 14-story
hotel tower, with rooms of about 440-sq.-ft. each and six
wings off the main trunk; a 640,000-sq.-ft. convention center,
with a 95,000-sq.-ft. column-free ballroom; a full-service
13,000-sq.-ft. spa and health club; and an 18-hole golf course
that wraps around the hotel. An octagonal atrium and rotunda
connects the hotel with the convention center. The resort
is Rosen Hotels & Resorts of Orlando's seventh Central
Florida lodging facility.
Helman Hurley Charvat Peacock/Architects of Orlando created
an Old Florida theme for the property located near Shingle
Creek. A headwater of the Florida Everglades, the creek earned
its moniker due to early settlers using the waterway to ship
cypress for use as roofing material. The area near the creek
will stay in its natural state, with walking paths through
the vegetation for guests. A glass facade in the lobby overlooks
the golf course and pools.
After benchmarking best facilities from across the country,
Rosen Hotels incorporated spacious prefunction spaces, registration
areas, kitchen facilities capable of quickly serving large
groups and the open ballroom.
"The column-free ballroom, from an operation standpoint,
is a tremendous feat," said Mark Davidson, senior project
coordinator for HHCP. "Everyone who comes in, whether
hosting a show or thinking about booking a show, is very happy
they don't have to work around columns."
WELBRO broke ground on the poured-in-place concrete-frame
hotel tower and the tilt-wall and structural-steel convention
center in November 2004, said Holmes. The resort sits on a
large spread-footing foundation. The hotel tower has heavy-gauge
structural-stud framing. Both buildings are clad with EIFS.
The project required 68,500 cu. yds. of concrete, 3,200 tons
of reinforcing steel, 650,000 lbs. of post-tension cable,
410,000 sq. ft. of tilt-wall panel and 4,800 tons of structural
steel.
Structural engineers from Mitzo Engineering of Maitland used
cambered steel trusses to create the open ballroom. Each truss
is 10-ft. in height and spans 200-ft. left to right.
"They are bowed up in the center," Davidson said.
"When they place the dead weight of the roof, which includes
the HVAC equipment and other machinery on the roof, the cambered
bow of the truss flattens out. In that way they are able to
make it longer and still support all of the weight it needs
to support."
The trusses sit atop 9.25-in. thick, 40-ft. high concrete
tilt walls, Davidson said. Most of the concrete sections are
20-ft. or less in width.
Full Speed Ahead
The contractor created two teams, one for the hotel tower
and one for the convention center, working simultaneously,
Davidson said.
"When we signed the work with the subs and vendors,
we got the principals of those firms to personally commit
to the project, knowing it would be fast-paced," said
Holmes, adding that crews worked weekends and extended hours.
In addition, Rosen Hotels stepped in to handle a tremendous
amount of the construction tasks with existing employees or
through Rosen-hired subcontractors, Davidson said.
"That freed up the contractor to put more manpower on
the larger disciplines of the building," Davidson said.
"It was a concerted effort on all parts to do it."
Rosen Hotels' employees or contractors completed the framing,
drywall, painting, trim and carpet and furniture installation.
Hotel employees were available to work all three shifts, said
Davidson. He added that Rosen crews utilized lifts, scaffolding
and other tools on site after the major subcontractors left
for the day.
"It kept his costs tremendously down," Davidson
said. "He built this facility for 60 percent of what
the facility would have cost for someone else who was doing
it through a contractor."
Even so, Garritt Toohey, vice president of Rosen Hotels,
pegged costs at more than $300 million. This is the first
property the company has built that required some short-term
financing, which was needed to speed up construction from
the original finish date in February 2007. The completion
date was moved up to create the birthday celebration.
Owner Involvement
Owner Harris Rosen's involvement began from the time he purchased
the land and donated 20 acres of it to the University of Central
Florida for the Rosen College of Hospitality Management. HHCP
crafted the master plan for the property.
"[Rosen] was extremely involved in the design of the
school and resort, down to every detail," said Michael
Chatham, senior vice president and director of design for
HHCP. "He questioned and challenged us on every decision.
He is a tough customer, and on the entire project, he wanted
to make sure we were getting the most from every dollar spent.
He did an incredible job."
That close involvement in design carried through to construction.
Rosen walked the site daily, monitoring progress and pushing
the project along.
|
Team Box:
Owner:
Rosen Hotels & Resorts, Orlando
General Contractor: WELBRO Building Corp., Maitland
Architect: Helman Hurley Charvat Peacock/Architects,
Orlando
Interior Design Public Areas & Convention Center:
Khristine Gregonis Associates, Longwood, Fla.
Interior Design Guest Rooms: W. B. Dodson Inc.,
Ormond Beach, Fla.
Civil Engineer: Davidson Design Group, Lenexa,
Kan.
Structural Engineer: Mitzo Engineering, Maitland
Mechanical, Electrical & Plumbing Engineer: KLG
Orlando, Casselberry, Fla.
Concrete: Rinker Materials Corp., Orlando
Concrete Framing: APEC, Palmetto, Ga.
Tilt-Wall: Empire Tilt-up Systems Inc., Deltona,
Fla.
Plumbing: Progressive Plumbing Inc., Clermont,
Fla.
Mechanical: Coastal Mechanical Services, Cocoa,
Fla.
Electrical: Tri-City Electric, Orlando
Drywall Framing & Finishing: Aetna Drywall
Contractors, Oakland Park, Fla.
|
"People shared their frustrations and concerns, and
we could nip them in the bud," said Rosen.
Rosen has compiled a book featuring photos of workers on
the diverse team that took the project from concept through
construction. Workers hailed from more than 40 countries.
Rosen plans to distribute the thousands of copies on order
to contractors to give potential clients and to resort guests.
Rosen also attended hundreds of meetings with suppliers and
subcontractors WELBRO had selected based on price or past
performance, Holmes said. Toohey added that the company was
able to get price reductions from firms that felt working
on the Rosen project would lead to other work.
"We try to start with a number and drive that number
lower as we work the process," he said.
Rosen involved himself in purchasing elevator equipment,
air conditioning, paint, electrical switchgear, fire alarms,
toilets, steel and light fixtures.
"It's a great experience for us," Rosen said. "When
we take over, that building is our responsibility. We have
to know the plumbing. We have to know about the electrical
system. We have to know about the air conditioning and heating.
We have to know how everything is installed."
Holmes met formally twice weekly with subcontractors and
kept close watch on progress.
The strategy seems to have worked. Holmes said WELBRO has
not faced any disputes with subcontractors. WELBRO also involved
the Orange County building and fire departments at the start
of construction and as the building neared completion to avoid
any surprises.
Rosen envisions corporations and associations will seek out
Shingle Creek as a place that can accommodate groups as large
as 1,500 to 2,000 in a single hotel, Toohey said. It's off
to a good start. The property secured 1 million advance room
reservations in August, had a conference booked within days
of opening and was busy from day one.
Useful Sources:
Rosen Shingle Creek
www.RosenShingleCreek.com
|