|
FICE Presents Engineering Excellence Awards
Association presented annual awards
at July convention in Palm Beach
The Florida Institute of Consulting Engineers recently presented
the winners of its 2006 Engineering Excellence awards competition.
The winning projects and entrants were recognized at the group's
annual convention, held this July at the Breakers Hotel in
Palm Beach.
The FICE competition awarded 12 Grand Awards and three honor
awards. Grand Awards are eligible to be considered in the
American Council of Engineering Companies' national Engineering
Excellence competition.
Water and environmental projects were prevalent among FICE's
12 Grand Award winners. Descriptions of the dozen top award
winners follows.
St. Lucie County Baling and Recycling
Facility
The Vero Beach office of CDM served as the environmental
engineering consultant for St. Lucie County's efforts to design
and construct a landfill gas-to-energy project. This venture
used the gas produced by the landfill to provide energy to
a neighboring citrus processing facility. The landfill gas
currently accounts for between 25 and 35 percent of the processing
facility's energy requirements, and is expected to reach 50
percent as the landfill expands.
City of Boca Raton, 40 MGD Membrane
Softening Process Addition, Glades Road Water Treatment Plant
The city of Boca Raton hired CDM of West Palm Beach to provide
engineering design and construction management for a 40 mgd
membrane-softening process addition to its existing lime-softening
process at the Glades Road Water Treatment Plant. Commissioned
in 2005, the plant is currently the largest membrane softening
facility in the world.
The objective of the project was to comply with the new,
stringent disinfection by-product regulations and to improve
the color of the treated water. According to FICE, the project
resulted in several advancements in membrane-softening technology.
The facility is the first large plant now to operate successfully
with no chemical pretreatment, saving nearly $1 million annually
in operating costs. The treatment plant also utilizes a new
generation of low-fouling membranes specifically developed
for the project, which require less cleaning and lower power
costs.
West Palm Beach Wetlands-Based Water
Reclamation and Aquifer Recharge System
In 2005, the city of West Palm Beach completed construction
of the CDM-designed wetlands-based water reclamation project,
which consists of a 10 MGD advanced wastewater treatment facility.
The project's three goals included: (1) treat secondary wastewater
so as to produce a high quality for discharge to wetlands
for restoration and aquifer recharge at the wetland reuse
site; (2) allow flow conveyance from the wetland reuse site
to the wellfield for aquifer recharge; and (3) pumping of
wellfield production wells with discharge to augment the city's
drinking water supply. Multiple levels of treatment and a
two-year residence time for the water in the entire system,
from secondary wastewater to drinking water, ensures that
this first-of-its-kind sustainable indirect potable reuse
system protects the health, safety and welfare of the public.
Samuel Butts Youth Archaeological Park
and Recreational Trail
The Nova Road Canal watershed area in the city of Daytona
Beach experienced chronic flooding that posed a health and
safety risk and hindered economic development. The city and
CDM of Maitland designed a multi-use stormwater facility to
alleviate flooding, provide recreational activities and improve
the image of the local neighborhood. The project involved
the construction of two stormwater ponds, an improved outfall
structure, and park amenities such as an exercise trail, elevated
boardwalk and learning center. During design, an archaeological
site was found at the larger pond site. A decision was made
to incorporate the archaeological site into the multi-use
facility and use it as a cornerstone of the learning center.
Ship Access Study, Port of Miami-Dade
CH2M Hill of Cape Canaveral was retained by the Port of Miami-Dade
to assess the impacts of a container ship transiting to and
from the container berths adjacent to Fisherman's Channel.
The engineering study first focused on executing a series
of navigation simulations replicating the Port of Miami-Dade,
both with and without the proposed widening and deepening
improvements. This evaluation validated the need for and configuration
of the proposed improvements. The study also allowed ship-to-pier
line arrangements to be optimized for safe mooring of vessels
and definition of pier improvements.
Royal Park Bridge
The bridge owner, the Florida Department of Transportation,
hired a consultant team led by E.C. Driver and Associates
of Tampa to perform the PD&E study and prepare preliminary
and final designs.
Early in the study phase, it was discovered that the existing
bridge's timber pile foundations had seriously deteriorated.
As a result, the bridge was closed to traffic and an emergency
was declared. Traffic was moved to a temporary bridge. The
state directed the design team to accelerate the project -
without deviating from the key objectives or circumventing
the public involvement process. Innovative program management,
unique structural designs and an extensive public involvement
program were implemented to achieve the project's objectives
in record time. Applying a unique set of multiple construction
contracts and fast-tracking planning with design, four years
were cut off the overall project schedule.
LYNX Central Station
The LYNX Central Station project provided a facility for
intermodal connections for regional transit and transportation
systems in the Central Florida area, replaced an aging bus
terminal facility in downtown Orlando and also incorporated
an office tower to serve as headquarters for the Central Florida
Regional Transportation Authority, or LYNX.
Earth Tech Consulting of Orlando was the program manager/construction
manager for the project. The firm performed preliminary site
analysis, developed potential concepts and led the effort
to prepare and obtain approval of the NEPA-required environmental
documentation.
Magnetic Ion Exchange System, Village
of Palm Springs
The Village of Palm Springs needed alternatives to ensure
that its two lime-softening water treatment plants would meet
the revised federal rules for disinfection byproducts without
additional modifications to the treatment process. Eckler
Engineering of Coral Springs recommended the municipality
incorporate a magnetic ion exchange pretreatment system into
the two water treatment plants. These two magnetic ion exchange
water treatment systems were the first to be constructed and
become operational in the United States.
Sunpass Challenge
Kimley-Horn and Associates of West Palm Beach provided work
on the "SunPass Challenge," an initiative of Gov.
Jeb Bush that called for an overhaul of the Florida's Turnpike
Enterprise's entire electronic toll collection system. The
idea was to increase SunPass transponder use and help reduce
delays at toll plazas, while improving traffic operations
and safety. Kimley-Horn and three other consultants (URS Corp.,
Parsons Transportation Group and Volkert & Associates)
provided operational improvements at 45 toll plazas throughout
Central and South Florida. This required the simultaneous
design and construction of 66 new dedicated SunPass lanes
within an accelerated 22-month schedule.
St. George Island Bridge
Parsons Brinckerhoff Construction Services provided construction
engineering and inspection services on the St. George Island
Bridge project -one of the Florida Department of Transportation's
first and largest design/build efforts ever undertaken at
the time of bid.
The project consisted of a new 4.1-mi. bridge structure across
Apalachicola Bay to St. George Island. This bridge crosses
one of North America's most environmentally sensitive bays.
Hundreds of oyster harvesters were concerned about the possible
effects it would have on the bay and their livelihood.
S.R. 408 Widening
The Orlando-Orange County Expressway Authority tasked PBS&J
or Orlando as its general engineering consultant to develop
concepts through a context-sensitive design to not only relieve
congestion, but to do it in a manner that would be received
positively by the community.
Public meetings were held during the design phase to collect
input and feedback from the S.R. 408 users, community and
local government. Key elements of the context-sensitive design
included an aesthetic package with planter walls, soundwalls,
bridge pylons, a gateway bridge feature and a community park.
Florida's ETDM Process
URS Corp. of Tampa worked in collaboration with the Florida
Department of Transportation and Federal Highway Administration
to develop a new process for planning and developing transportation
projects. The purpose of this initiative was to improve the
speed and efficiency of the environmental review process required
by the National Environmental Protection Act.
|