|
Design-Build: Delivery Method Still Growing
in Popularity
Corporations and governments in
the Southeast are increasingly turning to design-build.
By Debra Wood
The design-build delivery method continues to grow in both
public and private construction projects in the Southeast.
"We're quoting more and more of this kind of work,"
said Kevin Burton, project director for CH2M Hill Lockwood
Greene of Spartanburg, S.C. "It's easier for [owners]
to manage if there's a single point of responsibility."
Richard A. Belle, vice president of public affairs and information
for the Design-Build Institute of America, said studies show
design-build is on the rise, with owners of 38 percent or
more of new nonresidential projects opting for the delivery
method. He projects it will hit 50 percent within the next
decade.
"Particularly when there is no wiggle room in the budget
or schedule, design-build becomes a more attractive vehicle,"
Belle said.
Private Projects
CH2M HILL Lockwood Greene began construction in April on
a $125 million, 700,000-sq.-ft. design-build gypsum wallboard
manufacturing plant in Georgetown, S.C., for American Gypsum
Co. of Dallas. The plant is going up adjacent to Santee Cooper's
Winyah Generating Station and will use synthetic gypsum created
by the power plant's scrubbing process.
In addition to constructing the building, CH2M HILL Lockwood
Greene is providing engineering and procurement of equipment
based on the owner's specifications. The project's completion
is scheduled for late 2007.
"Everyone wants to postpone [construction] as long as
they can because the market is changing so quickly,"
Burton said. "Design-build allows them flexibility and
pushes the responsibility down to firms like ours that do
this regularly and are comfortable taking on a little risk
to manage a job."
In St. Petersburg, Fla., The Austin Co. of Cleveland began
designing a production and warehouse facility two years ago
for Cox Target Media of Largo, Fla. The $50 million, 500,000-sq.-ft.,
steel-frame and tilt-up concrete facility broke ground last
year and is expected to be complete in January.
The relatively long design time for a design-build project
was needed to give the owner time to select automation and
other equipment.
"There is so much evolution and development going on
with technology that goes into a manufacturing plant,"
said Michael G. Pierce, senior vice president of sales and
marketing for The Austin Co. With design-build, "a lot
of the decisions are made while the building is under way.
They're squeezing the latest technology against the earliest
delivery of equipment."
Austin has divided the job into four sections. As it completes
construction in a quadrant, it turns it over to Cox to install
the equipment. The building boasts sustainable design features,
such as a flywheel-driven backup battery, enhanced natural
light and use of recycled materials.
Cardinal Health of Dublin, Ohio, took a different approach
to building its distribution center, allowing The Conlon Co.
of Marietta, Ga., to design and build a 330,000-sq.-ft., $15
million warehouse before all of the equipment was secured.
Conlon continues to modify designs to accommodate the equipment.
The steel frame and tilt-up distribution center will finish
in October.
"[Industrial facilities] are fairly easy to do design-build,"
said Scott Austin, vice president of Conlon. "If I had
a shell warehouse design-build, I would eat that up."
Quicker delivery drives many of the design-build projects,
including the Bass Pro Shop and distribution center in Macon,
Ga. This spring, Choate Construction Co. of Atlanta completed
construction of the 450,000-sq.-ft. distribution center within
13 months.
Macon Bibb County Industrial Authority owns and developed
the building, and Kathy Bowden, executive director of the
authority, said speed was the determining factor in using
design-build.
In Florida, the NFL's Tampa Bay Buccaneers opted for design-build
delivery for their new $35 million corporate headquarters
and training facility. Hunt Construction Group of Tampa, in
a joint venture with Sierra Commercial Construction of Laurel,
Md., began the project in August 2005.
Mark McCaskey, project director for Hunt, said the job should
wrap up in September.
The job consists of a two-story, 115,000-sq.-ft. office building
and a one-story, 22,000-sq.-ft. training facility, maintenance
building, guard shack and three practice fields.
The team selected design-build "to allow a quick start,
fast track through construction and having a single responsible
entity," McCaskey said.
Public Work
Speed can also sway governments to select design-build. Such
was the case for the city of Savannah, Ga., in its development
of a new four-level, 1,100-car, underground parking facility
and restoration of one of the city's historic squares atop
the parking structure.
The city tore down an existing parking structure and secured
subterranean rights for that site, which W.B. Barnard Co.
of Atlanta will develop into a hotel and office complex. The
post-tensioned concrete parking structure, with a 2.5-ace
footprint, will serve as a foundation for those private buildings.
"The private part of the partnership was anxious to
get things moving and [design-build] was a faster way to move
forward," said Bob Scanlon, project manager for the city.
"We're 40 ft. in the ground and less than two years from
when the developer first came to us with a concept."
Batson-Cook Co. of Atlanta began construction before drawings
were complete. During excavation of the site, which is about
1.5 blocks from the Savannah River, crews hit water at 22
ft. and began dewatering.
The company contracted with Riato of Japan to install a secant
wall around the entire site. The wall reaches down 95 ft.
to a clay layer and eliminates almost all of the water seepage.
It will stay in place and become part of the garage's waterproofing
system.
"We anticipate having to run dewatering as long as the
garage is there, but the inflow is expected to be fairly low
volume," Scanlon said.
Hensel Phelps Construction Co. of Orlando began construction
in May on the 280,000-sq.-ft., 10-building Graceville Prison,
in Graceville, Fla. The GEO Group of Boca Raton, Fla., will
operate the $68 million, 1,500-bed facility for the Florida
Department of Management Services.
The project consists of three two-story housing buildings
with precast cells erected in place and several pre-engineered
metal buildings.
Mike Odom, project manager for Hensel Phelps, said design-build
helped save time, and the project should complete next September.
In Tallahassee, when Florida State University moved up plans
to build DeGraff Hall, the school opted for design-build with
a team with dormitory experience and off-the-shelf drawings
that could be tailored to the project's needs.
"The schedule was so tight when we advertised for this
project, the only way teams were going to be able to make
the schedule was to come in with a design on the shelf,"
said Lisa Durham, senior project manager for FSU.
Culpepper Construction of Tallahassee began demolition of
an existing dormitory in August 2005 and began construction
on the 157,000-sq.-ft., two-building, five-story, 706-bed
dormitories with documents only 75 percent modified for the
site. The project must wrap up in time for the 2007 fall term.
Speed of construction also factored into the North Carolina
Department of Transportation's decision to widen 2.1 mi. of
Interstate 40 near Asheville. Taylor and Murphy Construction
Co. of Asheville received the $42.9 million contract to add
an outside auxiliary lane and an inside lane in each direction.
The project includes several bridges, noise walls and utility
work.
"The efficiencies of the design-build process result
in a shortened project delivery time, which will enable the
department to meet the needs of this region much sooner,"
said NCDOT spokeswoman Lisa Crist Crawley. "The project
was also a good candidate for design-build because it is fairly
complex, and having one contractor oversee the entire process
significantly simplifies the management of all the project's
aspects."
In Lauderhill, Fla., the simplicity of working with one entity
convinced Broward County Parks and Recreation Division to
select the design-build delivery method for its new $35 million,
110-acre Central Broward Regional Park.
Seawood Builders of Deerfield Beach and H.J. Russell &
Co. of Atlanta received the contract in 2005 to design and
build a 5,000-seat, 20,000-sq.-ft. field house with a 560-ft.-diameter
multipurpose field for soccer, cricket and football, nature
trails and a jogging path on the former AT&T ship-to-shore
antenna farm. The park should open at the end of 2007.
"[Design-build] is one of the simpler ways to address
a construction project, because you're hiring a team, rather
that two individual companies," said Bob Harbin, director
of Parks and Recreation. "It's worked best for us."
Architectural firm VOA Associates of Orlando, which designs
for U.S. military clients, is serving as the design partner
on two projects being built by Sauer of Jacksonville, Fla.
At Fort Bragg, N.C., the team is renovating Kennedy Hall
for the U.S. Army Corps of Engineers. The $10 million job
includes demolishing the existing building to the shell and
reconfiguring the interior spaces for general-purpose administrative
and high-technology classroom space. The team received the
contract in June 2005, with completion scheduled for March.
The team also is building the Space and Naval Warfare Electronic
Integration and Support Facility at the Naval Weapons Station
in Charleston, S.C. It began work on the $10.6 million, 55,000-sq.-ft.
laboratory and office space in September 2005 and expects
to complete the job in April.
Ted Fery, a principal with VOA, said he anticipates that
the military will continue using design-build. "Design-build
is gaining strength," he said. "The steam has not
run out."
USEFUL SOURCES:
Ellis Square
http://www.theellisproject.com
|