|
Big Pour Kick Starts Ave Maria Project
Suffolk/Kraft Work on 3,000 Cu.-Yd.
Mat Pour
By Scott Judy
In a secluded section of Collier County, Fla., an army of
contractors, laborers and ready-mixed concrete trucks came
together on Saturday, May 13, for one of the biggest concrete
mat pours ever conducted in southwest Florida. The event was
in support of the new Oratory at Ave Maria University, the
nearly $140 million project that the joint venture of West
Palm Beach-based Suffolk Construction Co. and Kraft Construction
Co. of Naples, Fla., is building.
Created by former Domino's Pizza founder and owner Tom Monaghan,
Ave Maria is reported to be the first Catholic university
to be founded in the United States in more than 40 years.
In addition to the university, Suffolk/Kraft's contract calls
for the construction of a 1,100-seat church known as the Oratory
that will serve as a focal point of the development's new
town center. The university is being built first, and the
new town of Ave Maria will be developed around it.
For the big pour, concrete - supplied to the project by Rinker
Materials - started flowing as early as 2:30 a.m., said Mike
Beaumier, vice president-West Coast, for Suffolk Construction.
"We had a whole logistic plan laid out as to how we
were going to move trucks back and forth, temporary lighting
and numerous ways to get the concrete pumps lined up,"
he said. "We had four concrete pumps on-site, and God
only knows how many people."
By the end of the day, the 3-ft.-thick mat for the 23,600-sq.-ft.,
100-ft.-tall Oratory had required approximately 3,120 cu.
yds. of the 5,000-psi concrete specified for the project.
Beaumier said the remote nature of the site was one of the
bigger issues to overcome in the planning process. To solve
the problem, Rinker had to establish a concrete plant on site.
Two off-site plants, located in Fort Myers and Naples, also
fed the project.
"The challenge was that the concrete was so far away,"
said Mike Fenton, project manager with Suffolk. "Two
of the three plants were out of the way and they had to make
sure they had the right amount of retarder added" to
keep the mix from setting up too early.
Roughly 75 Rinker trucks supplied the ready-mixed concrete
to the site throughout the duration of the roughly 8.5-hour-long
pour.
"They tried to get 200 yards an hour from the onsite
plant, and we tried to get 100 (each) from the two outside
plants," Beaumier explained. "That was the plan
to try to supply 400 yards an hour."
Interestingly, the 3-ft.-thick mat will function more as
ballast than as support.
"On top of the mat, we'll place 4 ft. of fill and then
we pour our slab on grade, and then the fill and the concrete
acts as a ballast.," Fenton said. "It's really a
ballast so the building won't blow over."
"When we build a large building, we (usually) put it
on piles," Beaumier said. "The fact that we are
building such a large structure that is not on piles makes
it a unique operation for most of South Florida. It is so
different from what most people do in this area."
In the end, said Fenton, "Everything went as planned.
Both the supplier and the concrete finisher did a great job.
By 11 o'clock, we had all the concrete in the hole and no
major issues."
|