|
MUSC's Hospital Replacement
Hospital Built to Withstand Hurricanes,
Earthquake, Floods
By Scott Judy
The construction and design team for the Medical University
of South Carolina's $190 million Hospital Replacement project
in Charleston had the task of building a facility that could
overcome hurricanes, earthquakes, floods and terrible soil
conditions.
And the hospital is one of the few, if only, major health-care
projects in the country to meet both the 2000 International
Building Code's significantly enhanced seismic requirements
for Charleston - now on a par with the U.S. West Coast - as
well as its hurricane/windload criteria.
"We had to consider so many different things,"
said Tom Doyle, partner with structural engineer Korda/Nemeth
Engineering of Columbus, Ohio, and the project's lead engineer.
"About the only thing we didn't have to consider was
drifting snow."
Additionally, lead architect NBBJ of New York had another
hurdle to overcome - getting approval for an overtly modern
building from Charleston's conservative and historic-focused
Board of Architectural Review.
All of those challenges have been overtaken in an expedited
fashion, however, and less than 18 months into construction,
the team is an estimated nine months ahead of the contract
completion schedule and expects to have the building's exterior
completed by August.
"We're extraordinarily pleased with the innovation and
drive of our construction team," said Chris Malanuk,
director of strategic planning for MUSC Medical Center and
project director.
The Project
Construction of the MUSC project, referred to as the Center
for Advanced Medicine, is funded by a $401 million mortgage
loan from the U.S. Department of Housing and Urban Development
- the second-largest commitment ever made under the Federal
Housing Administration's Section 242 Hospital Mortgage Insurance
program. The loan is expected to save the hospital approximately
$110 million over the life of the mortgage, according to FHA.
The current project is merely the first phase of a 20-year
master-planned rebuilding of MUSC's Charleston campus, which
originally opened in 1955. (The hospital was founded in 1823
and became part of the state's higher education system in
1913.)
The first phase includes the development of a four-story
diagnostic and treatment building, seven-story patient tower
and a garden atrium that connects the two structures. The
641,000-sq.-ft., 156-bed facility will provide cardiovascular
and digestive services.
The project also includes a $38 million central energy plant
that will supply utilities for all future phases. The plant
became operational in June.
A 1,500-car, eight-story parking garage has yet to start
construction.
"We set out to develop this property and design it in
a way that we can take all of the existing inpatient and outpatient
capacity and migrate them to a separate campus," Malanuk
said.
BGKS, a joint venture of Birmingham, Ala.-based Brasfield
& Gorrie, and M.B. Kahn Construction and Southern Management
Group, both of Columbia, S.C., won the competition to serve
as construction manager-at-risk and has a $154 million GMP
contract. Brasfield & Gorrie is focused on the hospital
structure, while M.B. Kahn is leading construction of the
energy plant and new incoming infrastructure.
The Design
The MUSC project has demanded much from its architects and
engineers. First, due to capacity issues at its existing facility,
the owner needed design to be completed as quickly as possible.
While an optimum occupancy percentage is between 80 and 85
percent, "We've been running at 95-plus percent for some
time," Malanuk said. Also, due to significant population
growth in the region, even without any increased market share,
MUSC expects it will need 150 additional beds within the next
several years.
Design work began in January 2003, and designers were able
to finalize schematics and a complete program by that April.
"They cranked it out," Malanuk said. "We were
having user-group discussions concurrently with shaping the
building. So every day we would come up with program changes.
It was just an amazing, incredibly dynamic process."
Also dynamic would be the building's architectural design.
Timothy Johnson, partner with NBBJ in New York, was onsite
frequently for the project's first year and moved to Charleston
for the schematic and program design crunch time.
"He really tried to get a feel for the community and
he hit it off well with the city," said Hal S. Currey,
project adviser with MUSC. "We wanted it first to be
something that would work, and also something that the community
could accept."
Johnson added: "We had quite a schedule in front of
us." Moreover, to address the concerns of community leaders,
who were focused on Charleston's rich historic flavor, "There
would have been no other way to do it, frankly, because we
lived the project. Living down there was part of it."
And while the MUSC design is definitely modern, Johnson said
it is built upon what he calls the "genetics of Charleston."
For instance, he said, much of Charleston's cultural feel
comes from its historic homes, which are often narrow and
vertical. They often incorporated a garden between adjoining
homes to allow ocean breezes to naturally cool the area.
Johnson's design takes that concept to a much larger scale.
"We started with a more horizontal (space), which created
the garden and the drop-off, then also the more vertical mass,
which were the beds, which was relevant to a housing paradigm
that was part of the fabric of Charleston," he said.
"We took that same sort of model of the streetscape of
old Charleston with vertically proportioned buildings and
gardens
and we blew that up a little bit. We were pulling
these genetic elements from the past and reimplementing them
in a contemporary way."
A signature contemporary element is the glass curtain wall,
which adorns the south side of the seven-story patient tower's
exterior and continues down into the atrium section that connects
the two buildings.
"That (curtain wall) was sort of abhorred by some of
the more traditionally minded folks" who wanted brick,
Johnson said. "They had a very different image of the
building in mind. But as we talked through the type of glass
we were using, which was transparent and not reflective like
a building in Miami might be, we convinced them that material
was going to feel much less heavy and much less daunting in
the skyline of the city."
MUSC was supportive of NBBJ throughout, Currey said.
"The design was incredibly important," he added.
"It's the gateway to our campus, and it had to look good."
The building's exterior also incorporates metal panels, precast
concrete panels, punch-out windows and other materials.
The challenge for engineer Doyle was at least three-fold:
overcome the soil conditions; design for a seismic event;
and design for a hurricane-induced windload of more than 200
mph. (The project site was a part of the Ashley River a century
ago. Also, almost all of the soil in the Charleston area is
constantly settling over time.)
To engineer for both criteria, Doyle said the designers first
had to figure out which standard would be foremost for each
area of the building. For example, for the seven-story, curtain-walled
patient tower, the hurricane/windload standard was the dominant
requirement.
"Whenever you're dealing with seismic requirements,
columns generally get bigger and the connections get a lot
stronger," Doyle added. "In a seismic zone, any
connection that has to do with the seismic restraint of the
building generally has to be designed for the full strength
of the members into that joint. So the connections get a lot
more stout."
The poor soil conditions actually magnified the seismic issues
that had to be overcome, he added.
Moreover, because the area's soil would continue to settle
after construction, the foundation and bottom floor had to
be designed and built as a self-supported deck instead of
a mat slab. The overall project includes approximately 1,800
concrete piles driven to about 105 ft. deep. Every pile cap
is tied together via a 1-in. thick structural slab.
To address the flooding issue, the building's first floor
was designed as a parking structure, with the rest of the
building starting 10 ft. above that. The lowest level features
watertight mechanical rooms that can be sealed off so the
building can allow floodwater through. Built-in pumps would
then pump out any floodwater once the waters start to recede.
Accelerated Plan
About the time of the notice to proceed date, BGKS approached
MUSC with a plan to dramatically accelerate the construction
schedule. If approved, it would shave about nine to 10 months
off the schedule - a potentially financially rewarding scenario
for the owner, mostly because of the capitalized interest
it can accrue.
The plan essentially involves dividing each building into
numerous smaller segments and thus enabling BGKS to minimize
its subcontractor crews.
Ultimately, all parties signed on, and on Feb. 14, 2005,
the first piling was driven in the southwest corner. By April,
pile caps and foundation structure was being formed, even
as pilings were still being driven on other parts of the project.
By June, the first corner of the building received its first
piece of steel - even as crews were still driving piles. By
July, the first elevated deck was poured.
"Everybody really had to agree on it," said Dan
Mortimer, senior superintendent for BGKS. "When you have
a venture this large, with this many entities involved, you've
got to have everybody working together or it's messy."
A potential for a "messy" disruption to the schedule
rested with the exterior skin, which incorporates five different
elements and includes the curtain-wall system. To overcome
that, both BGKS and NBBJ assigned managers to focus specifically
on the building's skin.
"You've got so many different components and different
start and termination points," Mortimer said. "Everything
is about tolerances - for glass, for panels. Dimensional control
is critical." BGKS also hired Williams & Associates
as an exterior skin consultant.
Even with all the focused attention, the schedule sometimes
"has to take a back seat to getting it right," Mortimer
said. "The two goals are: it doesn't leak, and it looks
good. Schedule's important, but if you don't meet the 'look
good' or 'doesn't leak' criteria, everything else doesn't
really matter."
There still is plenty of work to do, but the team likes its
chances of finishing ahead of schedule.
"The risk with the soil is behind us," Mortimer
said. "The structure is behind us. The major things we
still have out there on the horizon would be medical equipment,
and we've made great strides towards getting all of that information
in. Weather still could be an issue. But right now we are
cautiously optimistic."
|