|
Clean Water: Cleaning Up in Atlanta
Atlanta-area Entities are Undertaking
Multiple, Major Sewer and Water Projects.
By Debra Wood
Faced with aging pipes, rapid population growth and, in the
case of the city of Atlanta, a consent decree, the Atlanta
region has embarked on a massive water infrastructure upgrade.
"Decades of not maintaining the system is an issue not
only in Atlanta but in other cities and counties all around
the United States," said Rob Hunter, commissioner of
Atlanta's Department of Watershed Management. "We, as
a nation, are at a point where our systems are failing because
we have not invested in them."
In 1995, the Environmental Protection Agency, the Georgia
Environmental Protection Division, the advocacy group Upper
Chattahoochee Riverkeeper and a citizen brought suit against
the city of Atlanta for multiple water-quality violations.
The city settled the lawsuits with a $3.2 billion upgrade
plan.
The city has funded the work through bond issues, raising
customers' water and sewer rates by 45 percent, a one-cent
sales tax and a commercial paper program with a $1.2 billion
line of credit.
"We are now doing things to change the infrastructure
for Atlanta for the next 100 years," Hunter said.
The first consent decree, which was issued in 1998, directed
the city to develop and implement a plan to stop combined
sewer overflows from polluting the Chattahoochee River by
November 2007. One year later, the parties agreed to amend
the document to eliminate violations from sanitary sewer overflows
by 2014.
While undertaking the court-ordered improvements, the city
decided to also invest in its drinking water system. Between
Christmas 2005 and New Years Day, Atlanta experienced 13 major
waterline breaks, and so it will replace drinking water lines
and mains in those areas where it replaces or divides sewer
lines.
The city will conduct a full evaluation and necessary rehabilitation
of the sewer system. Divided into six groups, the Sewer System
Evaluation Survey will inspect and repair 2,200 mi. of sanitary
sewers during a 12-year period. The process involves digital
closed-circuit television images, pipe lining and bursting,
and open-cut rehabilitation, completed as separate contracts.
Hunter said the survey was about 40 percent complete at the
end of January, with the two groups most in need of repair
evaluated.
Companies that performed the SSES group one included Atlanta
Infrastructure Managers, a joint venture between Atlanta Utility
Constructors of Decatur, Ga., Metals & Materials Engineers
of Suwanee, Ga., and Q-Solutions of Tucker, Ga.; Weston Solutions
of West Chester, Pa.; Compliance EnviroSystems of Atlanta;
and Camken Consulting of Atlanta. All of the same companies
are working on SSES group two, except for Weston Solutions.
The city expected to release contracts for the third and
fourth groups early in 2006.
The survey becomes the basis for a detailed rehabilitation
plan. Contractors can watch the television footage before
bidding and will know the condition of the pipes and work
required. The city was preparing to release the first rehabilitation
contract early in 2006.
Atlanta's Projects
Atlanta's sewer system includes separate sanitary sewers
in 85 percent of its territory and a 19-sq.-mi. area with
combined sanitary and stormwater pipes. The consent decree
requires separation of the combination lines in the Greensferry
and McDaniel CSO Basins and the Stockade sub-basin, to bring
the total separated area to 90 percent.
Ruby-Collins/Reynolds/EPR, a joint venture, is performing
the separation at Greensferry and Stockade. The partners include
Ruby Collins of Smyrna, Ga.; Reynolds Inc. of Orleans, Ind.,
and EPR Environmental Pipeline Rehabilitation of Hoboken,
Ga. Rockdale Pipeline of Conyers, Ga., and Integrated Municipal
Services Corp. of Decatur, Ga., received the contract for
the McDaniel separation.
The decree also requires construction of a deep-rock tunnel
storage and treatment system that will capture overflow from
the sanitary and combined sewers above and enable it to flow
by gravity to treatment facilities. The plan calls for reduction
of the number of overflows from more than 60 per year to an
average of four annually, with those overflows screened, disinfected
and dechlorinated before discharge.
The first tunnel project, the Nancy Creek Tunnel in northern
Atlanta, aimed to relieve sewage backup into peoples' homes
and yards. The city awarded that $150 million job to Nancy
Creek Constructors, a joint venture of Obayashi Corp. of San
Francisco and CJB Contracting of Atlanta.
Laser-guided tunnel-boring machines started at two different
points and crews worked around the clock to complete the $150
million, 16-ft. finished diameter, 8.5-mi.-long tunnel to
the R.M. Clayton Water Reclamation Center in December.
"We've had three large storm events since [the Nancy
Creek Tunnel] went active, and we have had zero overflows
in the basin," Hunter said.
Last July, Atlanta CSO Constructors, a joint venture of Obayashi
and Massana Construction of Marietta, Ga., began work on the
$286 million West Area Combined Sewer Overflow Storage Tunnel,
a 8.5-mi.-long, 24-ft. finished diameter tunnel, ranging from
125 ft. to 300 ft. below ground, which will collect and carry
combined sanitary and stormwater overflow to the R.M. Clayton
plant.
The West Area team also will use two tunnel-boring machines
to plow through the solid granite. Although work got off to
a slow start, Hunter anticipates the project will finish before
the Nov. 7, 2007, court deadline.
Atlantic Skanska of Atlanta is building a $47 million, 85-million-gallons-per-day
combined sewer overflow plant that will process material from
the West Area Tunnel. It also is scheduled for completion
at the end of 2007.
Gunther-Nash of St. Louis received a $28 million contract
to build a 10-million-gallon, underground storage facility
at the Custer Avenue Combined Sewer Overflow Storage and Dechlorination
facility, which will increase capacity to 44 million gallons.
The work, scheduled for completion in 2007, will require
a 30-ft.-diameter, 120-ft.-deep, vertical construction access
shaft to reach the area, then excavation of solid rock, using
drill and blasting methods.
Also, the city hired Western Summit Constructors of Norcross,
Ga., to complete a $26 million upgrade at the Intrenchment
Creek Combined Sewer Overflow Plant, which handles flow from
the Custer Avenue facility.
Atlanta also plans to start a stormwater utility to deal
with maintenance of stormwater culverts, retention ponds and
other facilities. Currently, if a retention pond fills with
sediment, the city cannot clean it out because fees are restricted
to water and sewer, with no provision for stormwater.
The city is developing options for the new services, which
will add about $4 in fees to an average homeowner's monthly
water bill. Then it will conduct public meetings to learn
what residents want to support.
Other Area Projects
While unaffected by Atlanta's consent decrees, surrounding
communities also are investing in sewer upgrades.
Crowder Construction Co. of Apex, N.C., began work in August
on a $55 million expansion to increase capacity from 6 mgd
to 10 million mgd at Clayton County's Northeast Water Reclamation
Facility.
Crews will install a new solid handling system, switching
the plant from dewatering on a belt filter press to a centrifuge
that extracts more water, decreasing hauling and disposal
fees, said Jim Poff, Clayton Water Reclamation Department
manager.
The project, expected to finish in 2008, includes upgrading
the manually operated facility to an electronic Supervisory
Control and Data Acquisition System.
"The advantage is it's easier to operate and maintain
the facility in compliance with a much more strict permit,"
Poff said. "Going from 6 to 10 MGD, we were not able
to get any additional waste load into the receiving [area].
Our permit limits almost cuts in half what we had to meet."
Cobb County also has a reclamation expansion project under
way. Atlantic Skanska began expanding capacity at the Northwest
Water Reclamation Facility from 8 mgd to 12 mgd in 2004. The
$22 million project will wrap up at the end of 2007.
At Cobb County's R.L. Sutton Water Reclamation Facility,
Archer-Western Contractors of Atlanta is expanding the plant's
solid-waste handling capacity and enhancing incineration and
dewatering facilities. Crews will install a fluidized bed
incinerator, which according to Cobb County engineers will
make the plant more cost effective. This project also began
in 2004 and is scheduled to finish in 2007.
Max Foote Construction of Birmingham, Ala., is building a
new $16 million, 20-MGD Level Creek Pump Station, with a 2.5-million-gallon
emergency wet well, for Gwinnett County. It replaces an existing
5.9 mgd pump station and will transfer raw sewage to the F.
Wayne Hill Water Resources Center for treatment.
The project includes excavation of 100,000 cu. yds. of soil
and rock, placement of 9,000 cu. yds. of concrete and 1,000
tons of steel reinforcement. Construction began in September
and is anticipated to finish in June 2007.
"This is being done to prevent overflow into the Chattahoochee
River," said Rich Schoeck, chief engineer, Gwinnett County
Department of Public Utilities. "We're just keeping up
with demand in the area."
Useful sources:
Clean Water Atlanta
http://www.cleanwateratlanta.org/
Upper Chattahoochee Riverkeeper
http://www.ucriverkeeper.org
|