|
Everglades Restoration: What's Going On?
Florida has begun a massive restoration
program to preserve the Everglades, the River of Grass.
By Debra Wood
After a slow start, some Florida-funded projects on the $7.8
billion Comprehensive Everglades Restoration Program have
begun. The work aims to restore a more natural water flow
through the River of Grass.
"We've seen significant changes to the detriment of
the natural existing environment in South Florida as a result
of water-control features built during the past 60 years,"
said Dennis Duke, U.S. Army Corps of Engineers program manger
for South Florida Restoration. Secondly, South Florida is
experiencing a water shortage. "We're wasting 1.7 billion
gallons a day, on average, to the ocean. That used to flow
through the Everglades. We want to capture that water and
retain it for the natural and human environment."
Congress approved the Comprehensive Everglades Restoration
Program, or CERP, as part of the Water Resources Development
Act of 2000, which was signed into law by President Bill Clinton.
The Corps of Engineers and the South Florida Water Management
District share responsibility for reviving habitat for endangered
and threatened animals and for providing water and flood control
to the area.
New reservoirs will capture water now discharged through
the Caloosahatchee and St. Lucie rivers. That stored water
can be used to supplement drinking water supplies.
"We're trying to mimic in an engineered system what
Mother Nature used to do naturally," said Jeff Kivett,
project director for SFWMD consultant Jacobs Montgomery Joint
Venture, a partnership between Jacobs Engineering Group of
Pasadena, Calif., and MWH of Broomfield, Colo.
CERP cannot simply turn the Everglades back to what it was
historically because that would result in flooding of homes
or agricultural land. Hence, engineers designed systems to
replicate water flow while preventing adverse effects.
But the massive CERP has been slow to get off the ground,
and the $175 million in planning, modeling and review work
the Corps has done has been behind the scenes.
Duke the original schedule called for Congress to pass subsequent
water resources acts every two years, but federal priorities
have since changed.
"We should have had certain projects under construction
by this point, but until Congress authorizes the projects
and provides the construction funds, we cannot do that,"
he added.
The Corps now projects construction costs will increase to
$10.5 billion, with 60 percent of that due to inflation.
Meanwhile, the State of Florida established its own Acceler8
Program in 2004 to speed up design and construction of its
projects. Bond financing will fund $1.5 billion in design
and construction work on eight key projects, expected to wrap
up in 2010, rather than the initially projected 2020.
"They tried to pick projects that would give the largest
lift to the environment," Kivett said. "Most of
the projects in the Acceler8 program are independent of each
other. They're in distinct parts of the different regions."
Reservoirs
Barnard Construction Co. of Bozeman, Mont., constructed two
aboveground test cells in 2005 for the Everglades Agricultural
Area Reservoir. It is building two test cells at the C-43
Caloosahatchee River-West Storage Reservoir and expects to
receive the contract to start construction this year on two
test cells for the C-44 St. Lucie Canal Reservoir.
"They're using different embankment designs conducive
for the geology of that specific area, and once they fill
up, they'll look at seepage rates," said Jeff Higgins,
vice president of Barnard. "It's validating the design
engineers' assumptions and making sure they're heading in
the right direction."
The full, $275 million Everglades Agricultural Area Reservoir,
scheduled to start this year, remains in design, pending evaluation
of the test cell results. The reservoir will capture freshwater
releases from Lake Okeechobee and runoff from agricultural
areas into a 190,000-acre-ft. aboveground reservoir. The project
includes two pump stations. At the end of January, SFWMD was
reviewing bids for the construction-manager-at-risk contract.
The $340 million, 10,800-acre C-43 Caloosahatchee River West
Storage Reservoir, scheduled to begin construction in June
2007, will collect and store stormwater runoff and water released
from Lake Okeechobee in a 12- to 24-ft.-deep reservoir that
will protect salinity in the Caloosahatchee Estuary and provide
water to nearby farms and homes.
The project includes 15 million cu. yds. of excavation, placing
710,000 cu. yds. of soil cement, building a pump station with
two pumps and constructing 12 weirs, gated box culverts and
gated spillways.
C-44, the St. Lucie Canal Reservoir, is estimated to cost
$273 million and is scheduled to begin construction in October.
It will protect the St. Lucie Estuary and Indian River Lagoon
from stormwater runoff by collecting and treating it in a
3,000-acre, 12- to 14-ft.-deep aboveground reservoir that
will hold 36,000 acre ft. to 42,000 acre ft. of water.
C-44 includes 6,000 acres of 4-ft.-deep Stormwater Treatment
Areas with emergent vegetation, canals and water-control structures.
Crews will remove an existing pump station and construct a
new 1,100-cu.-ft.-per-second, diesel/electrical pump station
with three or four pumps and expand an existing canal.
Other Acceler8 projects
The Everglades Agricultural Area Stormwater Treatment Area
Expansion will add 4,500 acres of marsh to a 40,000-acre wetland
already built by the state. Water from agricultural areas
flows through the marshes. The plant life absorbs phosphorus
from fertilizers and filters the water before it reaches the
Everglades.
Gulf Group of Panama City, Fla., has begun working in Stormwater
Treatment Area Expansion Compartment B, Area 2, Cell 4. It
features 10 mi. of levees, requiring 800,000 cu. yds. of fill;
11 mi. of canal, requiring 1 million cu. yds. of excavation;
construction of gated precast inflow and outflow culverts;
and conversion of a seepage pump station to a gated structure.
Stormwater Treatment Area Expansion Compartment C will begin
in July and cost $78 million. Harry Pepper & Associates
of Jacksonville received the contract for Area 6, Section
2, which includes 6.9 mi. of perimeter levees and 6.9 mi.
of borrow canals, 4.5 mi. of backfill farm canals, 10 gated
control structures, 6.75 mi. of power line extensions and
two access bridges.
In compartment C, Area 5, Flow-way 3, crews from Interlaken
of Manalapan, Fla., will build 10 mi. of perimeter and internal
levees, six control gated structures, 5.5 mi. of power line
extensions and recreational facilities.
Harry Pepper has begun work on phase 1, the Prairie canal
on the Picayune Strand (Southern Golden Gate Estates) Restoration
to create a natural flow of water to Ten Thousand Islands
National Wildlife Refuge, provide flood protection and improve
water quality. Crews will remove 227 mi. of road and build
three diesel-powered pump stations sized for a 100-year storm
event. They also will build spreader canals, canal plugs and
levee protection. Phase two of the $125 million project will
begin in August.
"It's going to create habitat for the Florida panthers
and various other endangered species," Kivett said.
Five Water Preserve Areas will buffer natural and developed
areas and divert runoff into storage areas. The $16 million
3A/3B levee seepage management area will begin construction
in July. The work includes ecosystem restoration, wetlands
enhancement, modification of existing canals, raising a maintenance
access road by 1 ft. and adding bridges to access an electric
company substation and a mobile home community.
The district expects construction to begin on the $15 million
ACME Basin B this spring and finish by year-end. The project
includes 1 million cu. yds. of cut and 512,433 cu. yds. of
fill, construction of a 4-ft. levee, seepage canals, two pump
stations and four culverts.
Site 1 Impoundment, a $47 million project set to begin in
October, features a seepage management system, pump station,
three gated culverts and canal and levee improvements.
The $69 million C-11 impoundment involves 1,850 acres, a
three-bay ogee-gated spillway, pump station, gated and ungated
culverts, two fixed weir structures and seepage canals, embankments
and windbreaks. Work will begin in August and includes 1 million
cu. yards of excavation and placement of 750,000 cu. yds.
of material for levees.
C-9 Impoundment, a $47 million project to store 6,600 acre
ft. of water, will begin in July and includes construction
of spillways, culverts, weirs and canals.
The $14 million Biscayne Bay Coastal Wetlands project will
restore water quality and distribution of fresh water into
the bay, increase coastal wetlands and enhance marine habitat.
That work will begin in August 2007.
The $40 million C-111 Spreader Canal, set to begin construction
in November 2007, will eliminate harmful freshwater discharges
into Florida Bay and revitalize wetlands in the Southern Glades
and Model Lands.
SFWMD is dividing the projects into multiple contracts and
will award them to prequalified contactors. Most major projects
remain up for grabs, with prequalification continuing throughout
the process.
"A significant amount of bidding will come out the end
of this year through next year," Kivett said. "The
district is really interested in small business development
and local communities, so we will strategically and economically
break these into packages."
Useful sources:
South Florida Water Management District, Acceler8
http://www.evergladesnow.org
Comprehensive Everglades Restoration Plan
http://www.evergladesplan.org/
|