|
Growing Commitment in Health Care
University of Miami's School of
Medicine in Midst of $1 Billion Construction Plan
By Debra Wood
The University of Miami Leonard M. Miller School of Medicine's
aggressive $1 billion, 10-year construction plan has hit its
stride, with the Clinical Research Institute Building nearing
completion, foundation work under way on a wet lab facility
and a hospital in design.
"We have a growing need for clinical research space,"
said Ronald Bogue, assistant vice president of facilities
and support services for the Miller School. "Translational
research, that is taking experimental drugs to the marketplace
through clinical research and drug development companies,
is growing tremendously in the country and at our school of
medicine."
Perkins & Will of Miami and Atlanta designed the 900,000-sq.-ft.,
$90 million total cost clinical research project. It includes
a 15-story, 340,000-sq.-ft. tower, with 50-ft. free spans
and a sidesaddle core facing an 11-story parking garage for
more than 1,400 cars; and a two-story, 60,000-sq.-ft. wellness
center atop the parking facility.
"We felt it was important that the building be expressive
with a look of innovation and modernity," said Manuel
Cadrecha, design principal "It became an opportunity
for the university medical center to make a statement toward
its commitment to the city."
Construction manager Bovis Lend Lease of Miami broke ground
in April 2004, topped out in April 2005, was more than 85
percent complete in January and will finish in May.
The project sits on a concrete footer foundation with about
800 auger-cast piles. The tight site, bordered on two sides
by highways, required dewatering.
"With some of those deep footers, the water started
coming out like a geyser," said Luis Garcia-Huidobro,
project manager for Bovis.
The tower was constructed using a precast joist system with
cast-in-place concrete slabs on top of the joists. Crews poured
17,000 cu. yds. of concrete and used 4.7 million lbs. of reinforcing
steel for the structure.
A unitized curtain wall facade with tinted vision and opaque
spandrel glass, which gives an opalescent look, graces the
exterior. The building withstood Hurricane Wilma without losing
any glass.
Strong verticals take the eye toward the sky, with a crown
motif at the top of the building.
"The glass is colorful and expressive of Miami, and
it has a fresh look," Cadrecha said about the appearance
changes throughout the day. "When the sun's hitting,
it has a bright look, and at other times, it has a dramatic,
rich, light-bronze look. It has a chameleon effect."
Inside, four core floors will contain exam, observation and
group-session rooms. The balance of the floors will house
administrative and support services. Bovis will build the
shell but is not contracted to complete the interiors.
Perkins & Will designed the interior for flexibility
and maximum efficiency. It will contain a modular wall system
and a pressurized, raised-flooring system on levels three
through 15.
"We can rapidly adapt to clinicians' changes in regard
to grants," said Bogue, explaining that grants typically
run three to five years before the researcher moves on to
the next project. "It's going to reduce our cost for
those changes."
Air-conditioning and electrical connections can quickly be
modified. In addition, letting the cool air rise from the
floor represents a more sustainable design than pushing it
down from above, Cadrecha said.
"All you have to do is remove square planks that make
the raised floor, and you can reroute the electrical,"
Garcia-Huidobro said. "You won't see any wires. Everything
comes from the floor. And you don't destroy anything to move
it."
The precast/prestressed concrete parking garage is built
with columns, 62-ft. double Ts and spandrel panels. Allen
Witt, vice president and sales manager of Coreslab of Miami,
reported it was the tallest precast parking garage built by
the company in Florida.
"It's tall for precast," Garcia-Huidobro said.
"It was put together like a LEGO, welding pieces together
and vaulting."
The garage contains 1,728 pieces of precast and is designed
to handle hurricane wind speeds. The garage has four stair
towers, with precast walls and metal stairs, and three elevators.
The exterior was painted and is partially covered with ornamental
grilles.
The wellness center, sitting atop the garage, has a structural-steel
frame, with concrete-on-metal decking. Perkins & Will
chose structural steel to lighten the load carried by the
foundations, to have separate trades handle different sections
of the building and for flexibility with the mechanical and
electrical systems, said George Valcarcel, project manager
for Perkins & Will.
"We had to design the garage to handle the loads of
the wellness center structure, which were very large,"
Witt said. "The key thing that made it the most difficult
was blending the two [structural systems]. When you build
something that tall out of precast and then you start with
a different system, your tolerances have to be really tight
to align that thing. You can image keeping everything plumbed
at those heights."
Garcia-Huidobro added, "Probably the biggest challenge
was reaching so high to erect [the steel] on top of the precast
garage. We had to go all the way up and walk away from the
site. We couldn't do it going horizontal, a bit at a time,
because the pieces were too heavy for the tower crane to manage.
"So we had to go by sections all the way up and advance
toward the north. Every single section that went up had to
have the strength to be stable during construction."
Bovis laterally supported the structure during construction
with X cables, and some welds and precast members on the bottom.
A ninth-floor, structural-steel sky bridge connects the research
building with the wellness center.
Also under way at the Miller School is a $70 million, 200,000-sq.-ft.,
10-story, concrete wet laboratory for basic-science research.
It is being built by Moss of Miami and will contain two floors
for animal studies and eight floors with long sinks, gas and
other items needed for bench science experiments.
Crews were placing auger piles in January. Completion is
scheduled for summer 2007.
The University of Miami also plans to erect a $320 million
medical practice building and replacement hospital, being
designed by Perkins & Will. The university will bring
clinics now in a variety of locations to this central campus.
The plan calls for three or four floors for medical offices
and two bed towers, with operating suites and intensive care
units. Finally, the school plans to add two more on-campus
wet lab buildings.
Useful Sources:
University of Miami
http://www.miami.edu/ummedicine-magazine/fstory5.html
http://www.miami.edu/scrip/summer2005/story05.html
Team Box:
Owner: University of Miami,
Miami
Architect: Perkins &
Will, Miami and Atlanta
Structural Engineer: Donnell,
Duquesne & Albaisa, Miami
Mechanical, Electrical and Plumbing
Engineer: Tilden Lobnitz Cooper, Miami
Concrete: Turnkey Construction
Co. Inc. of Miami and Florida Lemark Corp., Miami
Precast: Coreslab Structures,
Medley, Fla., PCI
Structural Steel: Steel
Fabricators LLC, Fort Lauderdale
Curtain wall: Glassalum
International Corp., Miami
Electrical: Elcon Electric,
Miami
Mechanical and Plumbing:
A & M Mechanical Contractors, Miami
Fire Protection: Arfran
II Inc., Doral, Fla.
EMS/Controls: Cyrus Technologies
Inc., Fort Lauderdale
|