|
Growing Underground
City of Cape Coral Undergoing $458
Million Utilities Expansion Program
By Scott Judy
As the building boom in Southwest Florida continues at a
breakneck pace, the demands on the area's communities to keep
their underground infrastructure systems up-to-speed are becoming
increasingly intense.
The city of Cape Coral's approach is an especially ambitious
one. The city is currently undertaking a seven-year, roughly
$458 million initiative to expand its utility distribution
system and also construct new facilities. Broomfield, Colo.-based
water and wastewater specialist MWH Constructors is engineering
and overseeing the city's efforts through a program manager-at-risk
contract.
The contract commenced in September 2004 and will run for
an estimated seven years. This latest contract succeeds a
previous five-year utility extension program, under which
MWH delivered more than 400 mi. of installed piping and 100
mi. of new roads.
Overall, the effort is aimed at meeting the city's water
infrastructure needs through the projected build-out of the
community, expected roughly 10 years from now.
"The growth in our area has exceeded all expectations,"
said Chuck Pavlos, director of public works for Cape Coral.
He said actual growth has far surpassed the figures generated
by numerous, yearly growth projections.
"We had growth projections in our master plan, then
we updated those with newer data, and then we hired a consultant
who updated those growth projections, and we busted all of
those," he said. "Nobody expected the growth that
we're seeing."
Pavlos added that the city is regularly experiencing new
monthly records for single-family home permits, with approximately
8,000 generated in 2004.
"They're eating up (our) capacity every day," he
said.
UEP
The project is broken up in roughly halves between an expansion
of the city's distribution system, referred to as the Utilities
Extension Program, as well as the Facilities Expansion Program.
The UEP extends Cape Coral's collection and distribution
lines to areas currently served by groundwater wells and septic
tanks. This includes the extension of roughly 100 mi. of new
utility piping per year.
"We're extending water, irrigation (reuse water), gravity
sewer, associated pump stations and force mains," said
Larry Laws, program manager for MWH. A small amount of storm
drain improvement is also included. Reconstruction of the
disturbed roads is also included in MWH's contract.
The company is utilizing a prequalified group of five underground
utility contractors to handle the UEP work, which is divided
up into five segments. Each individual segment is further
broken down into a number of subcontract areas, which are
then competitively bid to the group of prequalified firms.
These firms include: Denco Construction, Forsberg Construction,
Guymann Construction of Florida, Southwest Utility Systems
and Westra Construction.
"For instance, the Southeast 1 project is broken up
into six different subcontract areas," Laws said. "There
are six subcontracts in play under that one project."
The $47.8 million Southeast 1 contract, the first of the
five projects, began construction in spring 2005 and continues
for roughly a year. The remaining four utility extension areas
will follow sequentially. Once Southeast 1 is completed, the
next segment up is Southwest 4, which will then be followed
by Southwest 5, Southwest 6 and Southwest 7, in that order.
Laws added that each of the five contracts will "get
a little bigger" as the group moves forward through the
program.
"It's MWH's responsibility to coordinate the different
contractors, to make sure they don't have the roads torn up
at the same time and that sort of thing, and that the work
is properly planned and sequenced," Laws said. "We
typically break it up into gravity sewer collection areas/pump
station areas, so a contractor has total responsibility for
a particular service/pump station area."
FEP
Meanwhile, the Facilities Expansion Program, or FEP, includes
the approximate doubling of capacity at two existing water-reclamation
facilities, the addition of approximately 4 MGD of capacity
at the existing reverse-osmosis water plant, construction
of a new wastewater plant and also a new 12 MGD reverse-osmosis
water plant that is expandable to 36 MGD.
Contractors currently at work on FEP projects include: Parkson
Corp. of Fort Lauderdale; Cardinal Contractors, Sarasota;
Cogburn Electrical of Jacksonville; Boyd Irrigation of Bokeelia,
Fla.; Raymond Inc. of Marietta, Ga.; and Mitchell & Stark
of Naples.
Unlike the UEP, where the construction teams will progress
from one contract to the next in sequential order, the FEP
will feature multiple contracts being built simultaneously.
"There will be a lot overlapping work, going on in different
geographic locations," Laws said. He added that the expansions
of the two existing treatment plants will occur simultaneously,
as well as the construction of a new plant in the northern
portion of town.
Installation of interconnecting pipelines that tie those
plants together is also included in the FEP, as is the drilling
of about 20 water production wells to approximately double
the city's number.
PM-At-Risk
Cape Coral's decision to use the alternative-delivery method
of program manager-at-risk stems from the city's past history
of bad results. An infrastructure program undertaken during
the 1990s, utilizing the traditional design-bid-build method,
resulted mostly in bad feelings.
"We ended up with a bunch of lawsuits at the end of
that," Pavlos said. "You had the city, the contractor,
the designer, the construction manager, everybody pointing
fingers at everybody else."
Before moving forward with the current program, Pavlos said
city officials asked themselves questions such as, "How
do we control the construction better?" and "How
do we not tear up the whole city and have it torn up for nine
months?" (In the previous effort, residents experienced
this unacceptable situation.)
This time around, the city wanted to limit its risk of lawsuits,
establish a single point of responsibility and also address
issues of quality.
Pavlos said the program manager-at-risk approach "takes
the best parts of design-build and construction manager-at-risk
and creates a hybrid. It gives us a lot of flexibility, certainty
and control."
The city sees an advantage to having MWH manage both the
UEP and FEP.
"Giving them both programs forces them to coordinate
it so we don't get too far in front on the distribution and
collection expansion where the plants can't handle it,"
Pavlos said.
With the extreme amount of other construction going on in
Southwest Florida, as well as in other areas, a major challenge
facing MWH will be attracting competitive bids from contractors
and subcontractors.
"We can always use more qualified contractors to keep
the competitive juices flowing," Laws said. "The
bidding environment is very tough right now. There's so many
other things going on."
Useful Source:
http://www.capecoralutilityexpansion.com/
|