|
Finishing Up the Fifth Runway
$61.8 Million Concrete-Paving Contract is Final Piece of
$1.3 Billion Effort
Lane Construction Co. will have roughly one year to place
approximately 450,000 sq. yds. of concrete for the much-anticipated
new Fifth Runway at Hartsfield-Jackson Atlanta International
Airport.
By Scott Judy
"The icing on the cake." That's what Dwight Pullen,
director of the Runway 10-28 project at Hartsfield-Jackson
Atlanta International Airport, calls Lane Construction Co.'s
$61.8 million concrete paving contract that will finally realize
the airport's long-awaited, 9000-ft.-long Fifth Runway.
Pullen's comment is as much a statement about the extreme
efforts the airport has had to undertake to simply get to
this point - including a $360 million excavation contract
and a $160 million bridge structure contract that extends
over Interstate 285 and forms the end of the new 10/28 runway
- as much as it is a commentary on how he and the rest of
the team sees the final piece of this $1.3 billion runway
puzzle finally coming together.
"We're all pretty excited about it," said Kathy
Masters, senior project manager with the City of Atlanta Department
of Aviation. "It's kind of hard to believe we're there
already."
The Federal Aviation Administration is scheduled to commission
the new runway in May.
Straightforward, Not Simple
Lane's start to the job has been positive to date and is
a main reason for the team's widespread optimism. And while
Pullen and others may regard this latest contract as the least
complicated of all the runway-related projects, no $61.8 million
contract is ever simple.
The contractor's notice to proceed date was March 2, 2005,
and it has roughly 13 months to place the approximately 221,300
cu. yds. of 20-in-thick pavement for the 150-ft.-wide runway.
If Lane doesn't complete its work by that date, it faces liquidated
damages of $20,000 per day. There are no incentives for early
completion.
Jim Ward, paving superintendent for Lane, said the contractor
plans to meet this schedule by placing an average of 3,000
cu. yds. of concrete per day of paving, and hopes to be able
to construct as much as 4,000 cu. yds. in a single day.
And while the Department of Aviation was pleased by Lane's
start, wet weather has proven to be a concern.
"The weather's been a little bit of a hinderance,"
Pullen said. "If we can get through the weather, we think
it's going to be a good contract."
Ward added that the biggest challenge the contractor faces
is the "adverse weather."
Lane was using a CMI paver set at a 25-ft. width and a CMI
placer/spreader supplying the concrete to the front of the
paver. Dowel baskets are being used as the runway pavement's
reinforcing. The pavement will sit atop a 9-in. layer of soil
cement and a 24-in. subbase under that. The concrete mix is
being delivered via dump trucks from an on-site batch plant.
It is being designed to achieve a 650-psi flexural strength
within 28 days, Ward said.
The Department of Aviation is experimenting somewhat with
the inclusion of a lithium nitrate additive to the otherwise
standard concrete mix design in an effort to improve long-term
pavement performance. The lithium nitrate additive is intended
to reduce or eliminate alkali/silica reactivity (ASR) problems,
which can eventually lead to cracking of the pavement.
Quintin Watkins, project manager with the Department of Aviation,
explained that the problem is fairly common to some airports
that utilize deicing chemicals. The deicing chemicals can
react with silica contained in the aggregate to create a byproduct
that can cause cracking. The addition of the lithium nitrate
obstructs this chemical reaction from occurring, and essentially
changes it so that the byproduct is a benign gel that does
not cause cracking.
"We're still trying to pinpoint the source of our problem,"
added Masters. "Our granite aggregate is very difficult
to test for silica, and that has been an issue.
"We're kind of sticking our necks out on the runway"
with the use of the lithium nitrate, Masters added.
Though the Department of Aviation has recently experimented
with the lithium nitrate on a taxiway project it completed
last year, the results won't be known for awhile.
"We'll know in four or five years if it's working,"
Masters said, explaining that a runway the department replaced
six years ago recently started showing microscopic signs of
ASR.
Actually, lithium nitrate has been used for numerous years.
Masters indicated that there is roughly 25 years of performance
data on the concrete admixture. She added that it hasn't been
used very extensively until recently due to its high costs.
Lately the price has decreased significantly, so that it is
now cost-effective to consider.
"My understanding is the price point is coming down
and it's a lot more affordable," Masters said.
The runway is being built to the same measurements as the
airport's other landing runway, which Masters said is where
the facility has mostly experienced flight delays. Though
it will likely mostly be used as a landing runway - takeoff
runways are longer - the flight control staff will be able
to utilize it as it deems necessary.
Contractor Performance
Of course, another reason the aviation team is pleased with
Lane stems from the contractor's bid.
Pullen said the department's pre-bid estimate for the project
was around $70 million. The owner was pleased when the low
bid came in at $61.8 million, about 5-10 percent lower than
the other competitors.
"They had a very competitive bid, which brings back
huge savings to the airport, the city and the project,"
said Pullen. "But I think what enabled us to have a good,
low bid is we had a good contractor, and a good set of documents,
with a lot of upfront planning. So we should expect low bids."
He added that any potential paver had to be pre-qualified
by the department prior to the bid process.
Though the project was still in its earlier stages, the owner
was feeling positive about the contractor's performance.
"It's still early, but they've worked well with us on
issues that have come up," Masters aid. "Currently
we're on schedule and on budget, so I think that speaks for
itself."
As for the pending finality of this entire fifth runway effort,
Masters said, "Time flies when you're scrambling around
constructing. I think we're going to end up with a very good
product."
|