|
Florida Beach Restoration
Work to Restore Beaches Hurt by
Past Storms, Prevent Further Erosion
by E. Michael Powers
Beaches on both the Gulf and Atlantic coasts of Florida were
ravaged by hurricanes Charley, Frances, Jeanne and "Ivan
the Terrible" in 2004.
And now, faced with the possibility of another strong hurricane
season, federal, state and local governments alike are scrambling
to restore the state's beaches before they are washed away
completely.
The U.S. Army Corps of Engineers owns 15 beach reclamation
projects in Florida. The projects were created and funded
on an emergency basis in an effort to repair the beaches before
the 2005 hurricane season, which runs from June 1 until November.
"The fact that Congress provided the emergency funds
proves the importance of the beaches," said Jerry Scarborough,
chief of coastal and navigation branch and project management
in the Corps of Engineers Jacksonville district. "It
is crucial to have beaches in place to prevent damage from
hurricanes."
The Project Implementation Reports and National Environmental
Protection Act process have been completed for all of the
Jacksonville district emergency beach restoration projects,
Scarborough said. With the exception of the Panama City project,
all of the beaches are being restored to their full nourishment
levels rather than simply pre-2004 hurricane season levels.
"It just made sense to bring the beaches back to full
levels as long as we were doing the work," Scarborough
said. The money to bring the beaches to their spring 2004
levels will be entirely federal. The cost of any additional
work needed to reach full nourishment will be split between
local sponsors and federal funds, he added.
The reasons behind beach restoration vary based on funding
sources. Federally funded projects managed by the Army Corps
of Engineers are under way for the sole purpose of reducing
future storm damage, Scarborough said. Wider beaches significantly
reduce hurricane damage, as shown by a University of Florida
study which found that beaches widened by 100 ft. could reduce
storm damage by 51 percent in a 25-year storm and by 39 percent
in a 50-year storm.
"The renourished beaches have higher berm elevations,
which act as levees, absorbing the energy of the storm,"
said Steve Chatry, vice president of administration in the
dredging division of Weeks Marine of Covington, La. Weeks
Marine and Great Lakes Dredge and Dock Co. of Oak Brook, Ill.,
have been the two primary contractors for the Corps-owned
projects.
Locally sponsored beach reclamation projects, on the other
hand, are primarily about the protection of tourism-based
economies, said Erik Olsen, president of Olsen Associates
of Jacksonville, a contractor on many local efforts.
"Florida is a primarily tourism-based economy, and the
state and local governments know that they must protect the
beaches as a public asset," Olsen said. The beaches draw
millions of tourists and billions of their dollars, and the
state realizes that the beaches are essentially a high-return
investment, he added.
Weeks Marine is currently working locally funded projects
at Pensacola Beach and Hideaway Beach. The company is pumping
2.3 million cu. yds. of sand onto a 5-mi. stretch of Pensacola
Beach using a hopper dredge at a cost of roughly $10 million,
Chatry said.
For its $2.5 million job at Hideaway Beach, Weeks is using
a cutter dredge to pump approximately 250,000 cu. yds. of
sand onto the beach, at the request of Collier County, the
project owner.
The erosion of these beaches is not simply the product of
hurricanes. The development of coastal waterways and building
on beachfront property are the primary culprits, Olsen said.
Without a long-term fix available, the Corps will continue
to employ the temporary solution of dredging sand and pumping
it back onto the beach. Projects at Martin County and Del
Ray in Palm Beach have been completed at a cost of $8 million
and $4 million, respectively.
A $4 million job is in the process of wrapping up at Ft.
Pierce Beach. The $3 million Broward County Segment III project
was scheduled to wrap up recently.
Other Corps projects under way include a $16 million, 1 million
cu.-yd. effort at Venice Beach and two jobs worth $29 million
in Brevard County.
Other projects are in their preliminary phases - the $13
million effort at the beaches of St. Johns County and a $9
million contract for Duval County. Both projects should conclude
this fall.
Projects in the process of being bid include an estimated
$22 million job in Pinellas County, a $5 million contract
for the beach of Manatee County and a $16 million job in Lee
County-Captiva.
Two other projects are in a holding pattern. Broward County
Segment II, valued at approximately $4 million for the transfer
of 300,000 cu. yds. of sand, cannot go forward until the $4
million Segment III is completed. This 500,000-cu.-yd. rejuvenation
of Ocean Ridge, Palm Beach, will be the last on the Jacksonville
division's docket due to sea turtle nesting.
The restoration of the Panama City Beach, currently under
way, has proven to be the oddball of the 15 Florida Corps-owned
projects. The task fell under the purview of the Mobile, Ala.,
district of the Corps, which has employed creative environmental
management practices to hasten the start of work.
"We are working the NEPA process concurrent with the
project and are combining our work with NEPA work from past
projects," said Howard Ladner, a biologist with the Corps
Mobile district. The district was able to get a work permit
by piggybacking it onto a NEPA permit already obtained by
the Tourist Development Council.
The creativity and efficiency of the Mobile district was
adopted by the U.S. Fish and Wildlife Service, which prioritized
the Panama City assessment and modified the biological opinion
from a 1998 permit to speed the process along, Ladner said.
The $25 million project will renourish 16.5 mi. of beach
with 4 million cu. yds. of sand by the end of August. The
beach will not be taken to its full level because there is
not enough of the proper sand available, said Terry Jangula,
site manager in the Panama City site office of the Corps of
Engineers.
The sand color must match because of environmental concerns.
The color affects the sand temperature, which in turn affects
the sexual differentiation of sea turtle eggs buried in the
sand, Ladner explained. Acquiring enough sand of the correct
color is proving difficult because they are drawing from sites
that were identified and used for projects in the 1990s, Jugula
said.
Areas of the beach will be taken above pre-2004 levels. However,
certain areas will remain unreplenished until November because
of nesting shore birds.
|