|
FDOT Privatization: Trouble in Paradise?
Dealing With Problems, Agency Pushes
Accountability
By Scott Judy
One day after a major rainstorm in January 2004, construction
crews discovered evidence of cracking on some of the piers
of the nearly completed $60 million Memorial Causeway Bridge
in Clearwater, Fla.
Further investigation revealed deep cracks penetrating more
than halfway through four piers that exposed reinforcing steel.
Replacement of the piers will cost $10 million and add a year
to construction.
A few months later, the ground underneath a pier along the
elevated portion of the Lee Roy Selmon Crosstown Expressway
gave way, plunging the support about 12 ft. into the ground.
Workers were on top of a supported deck, but luckily, no one
was seriously injured.
While a sinkhole was first thought to be the culprit, it
was actually insufficient engineering. Repairs and other necessary
retrofits could cost $100 million.
PCL Civil Constructors of Tampa was the contractor on both
projects, and, according to FDOT, is "believed to be
of no blame" on the Lee Roy Selmon Crosstown Expressway
project. However, added FDOT, PCL's role in the problems with
the Memorial Causeway Bridge project is still "unclear."
Even so, errors and faulty assumptions by the private engineering
firms were cited both times.
In Florida's world of increasingly privatized design - a
world in which contractors often are more intimately involved
- engineers are perhaps finding out the downside of what has
been a lucrative trend for them. In other words, design errors
of such magnitude won't result simply in change orders and
increased costs to the owner. The engineers - or contractors
- are increasingly on the hook.
In case it wasn't clear before, William Nickas, state structures
design engineer for FDOT, told Southeast Construction: "The
Department of Transportation doesn't imply nor represent that
you are shifting the engineering responsibilities to us just
because we accept an engineer's work. It's the sole responsibility
of the engineering (firm)."
Take the case of URS Corp., the engineer of record on the
Crosstown Expressway project. With the blame pointed at URS,
the expressway authority has been pushing for an extensive
retrofitting of constructed piers - even those that haven't
failed - and for the engineering company to pay the full bill
for repairs.
Speaking about a proposed solution to the project that his
firm does not agree with, Tom Logan, URS vice president, recently
told Engineering News-Record, "We don't agree with the
decision, but we respect it. Our clients get what they want.
And if that's what they want to do, we'll help them implement
it." Mediation has been scheduled for June.
Logan's comments are indicative of the potential for future
work in Florida and the importance of staying in FDOT's good
graces. Currently, FDOT is awarding between $500 million and
$700 million in consulting contracts annually.
Ananth Prasad, director of FDOT's office of construction,
said as a result of such problems, the department will be
closely reviewing the capabilities of the engineering firms
it does business with.
"We need to look more carefully at (firms) we're qualifying
to do various work," he said.
During the recent annual FDOT/Florida Transportation Builders
Association conference, held in March in Orlando, department
officials repeatedly reminded attendees, especially engineers,
of their responsibilities. In turn, engineers occasionally
grumbled about the shift in accountability.
The Shift
At this year's conference, the emphasis on accountability
was clear. In the opening session, FDOT Assistant Secretary
Kevin Thibault thanked industry attendees for their efforts
over the past year - such as helping with the recovery from
the four hurricanes - but quickly returned to the accountability
theme.
"We're asking you to be accountable for the efforts
and responsibilities we've given to you," he said. But
he added that doesn't mean FDOT isn't willing to hear some
feedback.
"We truly believe in the spirit of trying to learn the
good, the bad and the ugly," he said. "We want you
to help us make sure we're identifying those areas where we've
done some good things, and identify where we need to do some
improvement."
Jim Lynch, vice president of LBFH of Palm City and chair
of the Florida Institute of Consulting Engineers' Subcommittee
on Construction, took Thibault up on his offer when he addressed
the opening crowd.
"The department is a very good client, and we're all
lucky to work for them," he said. "However, that
doesn't mean that we agree with everything the department
says. We are talking about some serious issues that are critical
to our industry."
He added that one of the serious issues is responsibility,
and when it comes to contractor-based quality control, for
example, some firms don't always provide accurate information
- and are not held accountable.
Under the current system, the engineering firm is held responsible
for the accuracy of the contractor-gathered data. "Our
position is if it's a contract requirement for the contractor,
then they need to do it," Lynch said. "They need
to be responsible for the accuracy and timeliness of it.
"Everybody needs to be responsible for their contract
obligations. It's not cost effective to the state of Florida
to pay a CEI, a contractor or even a third-party consultant
if they're not going to be responsible for that duty. We'd
like to see the department hold all of the various people
responsible for their contract obligations."
Essentially, engineering firms appear to be feeling that
an inappropriate level of risk is being shifted to them.
Doug Cox, also representing FICE and the moderator of the
conference's "Design-Build Update," suggested the
risk-shifting conversation is still ongoing, but said: "We
want to shift the risk back to DOT. Of course, DOT is shifting
the risk back to us."
The Projects
As it turned out, a factor common to both projects was cutting-edge
design - or, more precisely, design work that was pushed to
the edge.
On the Memorial Causeway Bridge, PCL initiated a design change
after winning a design-bid-build contract. Its changes were
made under a value-engineer-change procedure, a process similar
to design-build, and included the use of a different type
of pier/superstructure connection than was originally proposed.
During construction, the deck became unbalanced and created
excessive compression on one side of the pier columns and
tension on the other. This caused the cracking.
FDOT's Nickas said if more attention had been paid to the
project's engineering, the problems would not have occurred.
"The fundamental design is not (in question),"
he added. "If it was erected with due care and had some
additional engineering to bring attention to these hot spots,
then (the engineer) would have designed past it with external
falsework or changes to his balance calculations so he wouldn't
have impacted those columns."
On the elevated Lee Roy Selmon project, single piers - referred
to as nonredundant piers - support the new highway that is
being erected in the median of an existing expressway. URS
is being blamed for overlooking engineering standards for
these supports, essentially not providing a sufficient safety
margin for area soil conditions.
After construction was halted due to the event, consulting
engineer Ardaman & Associates of Orlando was brought in
to review engineering and make recommendations for completing
the project.
Ardaman's recommendations included retrofitting most of the
already constructed piers. URS has recommended further testing
to determine exactly which piers should be retrofitted. FDOT
has sided with Ardaman's conclusions.
(Interestingly, FDOT admitted that its officials warned the
expressway authority and its consultant engineers four times
prior to construction that the piers were overloaded - but
went ahead and made a $100 million loan that enabled the project
to begin without requiring design changes.)
Striving to learn - and educate - from these mishaps, FDOT
is re-emphasizing the tried-and-true over cutting-edge innovation.
"We want to focus on traditional solutions," Nickas
told Southeast Construction. "Innovative doesn't mean
you're running the concrete stresses up higher or breaking
the codes. Innovative should mean taking our normal engineering
solutions and how you package it and how you approach the
project.
"The exotic stretch of interwebs and longer spans and
instability during construction is just not attractive. You've
got (issues of) workers' safety, stability during erection
- and ultimately you're going to have the performance issue."
Jerry Harder, president of PCL Civil Constructors, the contractor
on both of the Memorial Causeway and Crosstown Expressway
jobs, agreed that a return to basics would be welcome.
"They (engineers) need to follow sound engineering practices,"
he said. "You just can't stray from that."
Changes
FDOT's Prasad said the department will be implementing new
standards to ensure errors of this magnitude don't recur,
such as changing how it qualifies consultants and revising
the requirements for consultants that perform complex bridge
work, geotechnical work and inspections on complex projects.
The agency hopes to have these new rules in place by fall.
"We are trying to establish more controls so that the
firms that get the work are going to do the work," he
said.
In the ultimate privatized process, design-build, FDOT will
be mandating third-party peer review of designs, instituting
new requirements and specs for shafts and otherwise shoring
up its controls.
"We're trying to strengthen our requirements, have (procedures
such as) independent peer reviews, load calculations, service
limit checks, so we can assure ourselves that what we're getting
is what we want," Prasad said. "We're not trying
to stifle innovation per se, but we're trying to make sure
that the (design) passes through all of these time-established
checks, so at the end it's truly established that it has the
factor of safety for long-term performance."
Safety factors will be increased, too, so that engineers
will need to go beyond simply meeting design minimums.
"There are minimums, and then there are judgments,"
Prasad said. "Engineering includes a lot of judgment.
You can hit all of the minimums, but then when you're actually
building something, you can't afford any slip-ups. So we're
establishing minimums that can take into factor construction
tolerances.
After all, Prasad continued, "Construction is not a
perfect science. You're going to have some imperfections.
But we need to make sure that the design allows for some of
those."
Again, for Prasad and the rest of DOT, it all comes down
to that buzzword, accountability.
"You have responsibility, and with responsibility comes
accountability," he said. "That doesn't mean we're
perfect. Contractors aren't perfect. Employees of the department
aren't perfect. What we hope is folks are learning from their
mistakes, trying to improve themselves. If they're not, then
we need to ask the fundamental question: Why are we doing
business with them?"
|