|
Powering Up
Growing Energy Demand Fuels Two
Major Savannah Construction Projects
By Bea Quirk
Savannah isn't just home to historic buildings and old-fashioned
Southern gentility anymore. The area is also home to two of
the Southeast's larger power projects.
Chicago Bridge & Iron Co. of Sewickley, Pa., is constructing
a $100 million storage tank and import facility as part of
Southern LNG's plant expansion of its Elba Island LNG terminal
in the Savannah River. Including the construction of dock
facilities, the total price tag is $150 million. Southern
LNG is operated by El Paso Corp. of Houston, an owner of several
gas pipelines around the country.
And about 20 mi. north of Savannah, near the town of Rincon,
Southern Power of Atlanta is designing and building a $99
million combined-cycle power generating plant that will go
online in June. It will be called Plant McIntosh and will
be jointly owned by Savannah Electric and Georgia Power. Southern
Power, Savannah Electric and Georgia Power are owned by Georgia-based
Southern Company Energy Solutions.
The power-generating plant features two combustion turbines
that use natural gas to generate electricity, as well as a
steam turbine powered by the heat exhaust.
Dale Lloyd, general manager of new generation, environmental
and retrofit projects for Southern Power, said the company
has brought 14 such plants online since 1999. Seven of them
- including Plant McIntosh - are virtually identical.
"We may make adjustments and refine designs for individual
weather and soil conditions, but it's basically the same design,
construction and equipment and the same vendors," Lloyd
added. "That produces construction efficiencies and lets
us build on lessons learned."
He said that, for example, the team has learned to schedule
and sequence activities to prevent on-site congestion and
backup. That means several tasks don't all need one crane
at the same time. Also, Southern Power has learned it is better
to weld some equipment on the ground before it is placed in
the facility rather than welding it from scaffolding after
it has been installed.
Coordinating labor for the project is another demanding aspect.
Lloyd said there can be up to several hundred workers onsite
at the same time. Southern Power acts as the construction
manager and uses a labor broker to provide the workforce.
Lloyd said the focus is on using local labor "to hold
costs down and support the community." But sometimes
that is not enough. With a project such as this, there is
a need for skilled workers who can build such a facility and
for workers with technical skills who deal with engineered
components and computer-based control systems.
Construction began on Plant McIntosh in March 2003. The new
plant will produce 1,240 MW; Savannah Electric will use 200
MW of that total and Georgia Power the rest.
LNG Storage Tank
The growing demand for power is also why Southern LNG is
almost doubling the capacity of its import facility in the
Savannah River. When the new facility is completed in April
2006, it will be able to process an additional 540 million
cu. ft. a day, up from the current 675 million.
Interfacing with the current operations isn't easy. "It's
a very busy import facility, and we are working right on top
of it," said Dan Tennison, principal project manager
for Southern LNG.
To foster communications and good working relationships,
Tennison said the team meets weekly with members of the plant
operating staff and gives them 30-60 days notice about future
activities "We benefit from their perspective, and they
give us valuable input," Tennison added. "We each
know what to expect so there are no surprises."
The storage tank is a major focus of the project, but, according
to CB&I Project Manager Kevin Landfried, it only represents
about 30 percent of the budget. "It's basically a big
heavily insulated cooler of stainless steel," he said.
"Most of our time and energy is spent on the processing
area."
In the processing area, liquid natural gas is unloaded from
tankers, then vaporized into a gas and shipped by pipeline.
The tank has a capacity of 160,000 cu. meters, with a diameter
of 260 ft. and the tip of the roof rising 160 ft. The outer
shell was built first, followed by the roof, which was actually
constructed at the bottom of the tank and then pressurized
using four fans to air raise it to the top of the structure.
That was accomplished in late October.
Construction began in June 2003, and there's an average of
120 workers on site. Another 150 workers are building the
new docking facilities, which are being built into the island
to minimize congestion on the river. This will require dredging.
Tennison said that the two projects are separate, but coordination
is required between the two.
Natural gas is abundant in other places around the globe,
such as Indonesia, Nigeria and Algeria. The gas is turned
into a liquid in these places, then shipped via tankers to
import facilities, where it is turned back into a gas.
The natural gas industry is an international one, and Landfried
said that much of the equipment and materials for the project
come from abroad. That requires careful coordination, and
once they are delivered, they must be tested and installed.
The construction team must also work closely with several
regulatory agencies, such as the U.S. Coast Guard, the U.S.
Army Corps of Engineers, the Federal Energy Regulatory Commission
and the U.S. Department of Transportation. National security
issues are an area of concern.
"This kind of project is heavily regulated for the health
and safety of the public, and it takes time," Tennison
said.
There are currently only four import facilities in the U.S.,
and CB&I is expanding three of them. Additional facilities
are in various stages of planning.
|