|
The Georgia Aquarium
Intense Project is Pushing Contractors
to Their Limits
By Scott Judy
Bernie Marcus's extraordinary gift to the people of Atlanta,
the city where he co-founded his Home Depot business empire,
is coming alive near Centennial Park.
With an overall value of more than $200 million, the Georgia
Aquarium is certainly a generous and visionary gift. Touted
as one of the largest aquariums in the world, it will reportedly
feature more than 55,000 animals from approximately 500 species
and an estimated 5 million gallons of fresh and saltwater.
Approximately 25 percent of the state-of-the-art facility's
450,000-sq.-ft. of space will be able to be used for educational
purposes, and officials are expecting to teach 70,000 students
per year about the underwater world. It will also feature
a 17,000-sq.-ft. ballroom that can accommodate up to 2,000
people for an event. Promotional material states that officials
are expecting two million visitors within the first year.
This gift will unveil itself in the latter part of this year,
or perhaps early 2006, as originally scheduled. For now, though,
for the hundreds of men and women building it, this underwater
fantasyland remains strictly a mountainous undertaking, the
size and degree of which they may never experience again.
"This is the most intense project - for everybody within
our company - that we've ever been involved in," said
Eric Young, division manager for general contractor Brasfield
& Gorrie of Kennesaw, Ga. "It's probably the most
complex (aquarium) structure we've seen anywhere. With all
of the aquariums (we've visited), I've never seen anything
like it."
Dwayne Strickland, general superintendent for Brasfield &
Gorrie, said the facility will contain the largest closed-loop
aquarium piping system in the world. "As we understand,
there's nothing in the United States that compares to this,"
he added.
Unmatched Scope?
Strickland may be right. As a comparison, the John G. Shedd
Aquarium in Chicago features about 4.5 million gallons between
its original aquarium and a newer Oceanarium facility completed
in 1991. More to the point, the 3-million-gallon, 170,000-sq.-ft.
Shedd Oceanarium took roughly 3.5 years from groundbreaking
until completion.
In short, the Georgia Aquarium will have an extra 2 million
gallons of water, more than 2.5 times the space and will be
built one year faster.
Additionally, the project's 100,000 yds. of concrete - for
both the aquarium and parking deck - is roughly double the
amount the Brasfield & Gorrie used to build the Georgia
Dome. More than 150 subcontractors and suppliers are working
the job. Budget negotiations between the contractor and owner's
agent required five consecutive weeks of day-long meetings
to finalize project costs.
And yet, for Brasfield & Gorrie, pursuing this project
came down to a couple of guys who wanted to take a chance.
"We weren't even going to chase this job, that's the
funny thing," Young said. Every other division manager
had passed on pursuing this sketchily detailed project when
Young got a call from his boss one night while Young was coaching
pee-wee football.
"He said, 'If you want to chase it, we'll chase it.
If you don't want to chase it, we'll pass,'" Young recounted.
"I said let's chase it."
But at the time, "We didn't even know what it was,"
Young said. "It wasn't released. It was only supposed
to be $100 million. And they were just giving us these little
boxes on a piece of paper."
The contractor's field staff was hesitant, too, Young said,
but then Strickland stepped up.
"Dwayne really wanted to do it," Young added. "He
said, 'I won't put my career on hold as a general superintendent,
but I'll do this one personally, while I'm overseeing other
projects.'"
As promised, Strickland not only oversees the aquarium project
but about eight others, too.
The story of the schedule is a similar tale. Strickland,
Young and Michael Freberg headed up Brasfield & Gorrie's
preconstruction efforts and developed a 30-month overall project
schedule based on "a few napkin sketches," Young
said.
The original is still hanging on a project manager's office
wall, but a more thorough, 37-page version has since been
created that contains details on roughly 2,300 activities.
(Another version exceeds 80 pages.) Young said the two documents
are "almost identical."
"We're off on a few things here and there," he
said. "We actually started a few things earlier than
we thought we could."
The Project
Brasfield & Gorrie is working as a general contractor,
self-performing all of the forming, placing and finishing
of the 100,000 yds. of concrete and formwork for both the
aquarium and parking deck. Heery International of Atlanta
is working alongside as program manager. Thompson, Ventulett,
Stainback & Associates of Atlanta is the project architect.
The contractor broke ground with grading work on May 29,
2003. The value of the firm's contract with the Georgia Aquarium
was later increased with the addition of the parking deck.
"We actually started planning for (the parking deck)
as we were coming out of the ground (with the aquarium),"
said Chris Britton, senior project manager for Brasfield &
Gorrie. "We did some special designing to be able to
build the parking deck without affecting the work taking place
(at the aquarium)."
That was necessary due to the site's already tight conditions.
Strickland explained: "We've got a 10-acre site. Counting
the parking deck, we've got eight acres under roof. The other
two acres are total hardscape. So at the end of the day we've
got no room."
Berkel & Co. installed approximately 2,500 auger-cast
piles for the aquarium structure, while Brasfield & Gorrie
built the pile caps and spread footers, then placed and finished
all vertical and horizontal concrete. The most intense concrete
work was in support of the aquarium tanks while forming the
acrylic openings inside the tanks.
"It was the most expensive concrete I've ever done,"
Young said. "It's literally two to three times more expensive
than normal concrete." Numerous admixtures, used to combat
saltwater intrusion, shrinkage cracks and other issues, added
to the material cost.
The contractor used Lafarge's Agilia brand of self-leveling
concrete to construct the intricate, nonlinear tank structures.
Walls measured between 30 and 36 in. thick and as much as
32 ft. high. Individual pours covered wall sections measuring
between 20 and 50 ft. wide.
Regardless of the wall's configuration, the Agilia concrete
would fully fill out the form, with no vibration necessary,
Young said. "When you broke the forms out, there wasn't
even a bughole," he added.
The process took considerable testing at Lafarge's plant
to ensure the product would perform up to its promise in the
field. While such a technology innovation helped, Strickland
shrugged it off. "We're still pouring concrete; we're
still doing formwork," he said. "It's the same basic
principles."
The contractor is already releasing certain areas to the
owner. This process began early this year and will continue
gradually through project completion.
Other Challenges
The life-support systems for this aquarium are similarly
sizable. Though McKenney's had never done anything quite like
this, Brasfield & Gorrie chose the Atlanta-based subcontractor
based on its past relationship with the firm.
The systems are unique. Despite their huge capacity, the
contractors reported that the aquarium's life-support systems
will actually only waste about 1,000 gallons per year - or
less than three gallons per day.
"All of the water is completely recirculated,"
Britton said. "They'll use more water flushing the toilets
in a month than the actual aquarium life-support systems."
While the concrete and piping systems are major hurdles,
Young said the biggest obstacles left may be in punching the
job out.
"We're actually starting to punch stuff now," he
said. "But that could kill us. If we don't get it punched
out before we open, the quality won't be where it needs to
be."
Since last summer, the team has been working second and third
shifts, and most subs are putting in an average of about 56
hours per week.
Still, despite the team's progress to date, the schedule
will remain a daunting task. "It's all we can do,"
Young said. "On some (activities) we're ahead and some
we're behind. We've got to stay on top of everything."
|