|
The Perkins Project
Contract Includes Major Addition
and Renovations to Duke University's Perkins Library
By Bea Quirk
Librarians don't like noise, but at Duke University in Durham,
N.C., the university librarians are not only tolerating some
loud noise - they're cooperating with the noisemakers.
That's because when all the banging, pounding and hammering
is over with, the William R. Perkins Library will have a 150,000-sq.-ft.
addition, a new atrium-pavilion and a renovated first floor
in its current facility.
The new addition, called the Bostock Building, will be connected
to the current library complex, which is made up of three
buildings, constructed in 1928, 1948 and 1968. Ground was
broken on the new structure in fall 2003, with a completion
date of this fall. Also currently under construction is the
Karl and Mary Ellen von der Heyden Pavilion, a two-story atrium/reading
room located off the main entry to the library.
Once those structures open, work will begin on phase two,
renovating the first floor of the Perkins building. That's
set to be completed in fall 2006. The cost for the three components
- jointly called the Perkins Project - is approximately $52
million. Bovis Lend Lease of Raleigh is serving as the construction
manager.
"Our biggest challenge is maintaining a study environment
during construction," said Ashley Jackson, Duke's project
manager for the Perkins Project. "Noise is the worst
thing, but there is also dust and fumes."
The library staff has worked closely with the construction
team to minimize disruption of library operations. For example,
demolition and excavation are scheduled during summer and
semester breaks. Construction is halted during finals. Library
users - primarily students - are kept informed of the construction
schedule and what areas are most likely to be impacted, both
on the Web and by postings in the library. Earplugs are also
made available.
"I've been amazed by how many have been used,"
Jackson said. "It's incredible."
Steps have also been made to protect the library's highly
valuable collection. The Bostock Builing will be attached
to the existing library by a 25-ft.-wide corridor on each
level, except the first. An interior wall was built against
the construction wall to maintain the integrity of the existing
structure, keep its heating and AC systems intact and keep
out animals. Some materials have also been moved.
The library's location - on The Quad, the symbolic heart
and soul of Duke - gives it great prestige, but it also creates
design and logistical challenges.
The design, developed by Boston-based Shepley Bulfinch Richardson
and Abbott, includes the new building, the atrium and renovating
the existing library complex - the latter of which will be
completed in phase two.
Given today's technology and how research is now conducted,
libraries have to be much more than simply a place to store
books. The design process on the Perkins Project included
input from students, faculty, staff, librarians and alumni
on their needs.
"The library is the centerpiece of intellectual activity
on campus, a place of scholarship and discovery where the
social aspect of learning is also important," said Geoff
Freeman, the Shepley Bulfinch principal in charge of the project.
Tradition is important at Duke, and because the library is
located on the Quad, it has to feature the same Gothic architecture
and Duke stone - limestone from the university's quarry -
as the rest of the buildings. The front of Bostock does indeed
feature that on the front side of the building facing the
Quad. But on the backend - which faces newer buildings - precast
and brick make up the exterior.
The connector between the two structures features the same
exterior materials, and from the outside, the structures look
like one contiguous building.
"You don't see a lot of stone buildings these days,
and there are only a limited number of subcontractors who
can do the work - it's a small workforce out there,"
said Barry Berger, project manager for Bovis Lend Lease. For
the entire project, Bovis is using about 25 subs with as many
as 175 workers onsite at any given time.
The site is small, too and is located among existing buildings,
all of which must maintain operations. In addition, three
other construction projects are going on concurrently, and
Berger said construction coordination had to extend to those
sites. He added that some deliveries were taken offsite and
that the stone was dressed and packaged before taken to campus.
Bovis has a longstanding relationship with Duke and has completed
about a dozen buildings for the university. "Duke is
a very special client for us," Berger said. "They
have special needs and requirements, and we are focused on
meeting them. By working on multiple projects, we have a better
understanding of them and how to address them."
But even with that long history, the Perkins Project stands
out. "It is a rare opportunity to build a building at
this location (on the Quad) and of this prestige," Berger
added. "It's a signature building, and we are honored
to be a part of it."
Project Team:
Owner: Duke University,
Durham, N.C.
Architect: Shepley Bulfinch
Richardson and Abbott, Boston
Construction Manager: Bovis
Lend Lease, Raleigh, N.C.
Useful Sources:
http://www.lib.duke.edu/perkproj/
|