|
CDC's New HQ
$115 Million Building Will Be CDC's
New Campus Headquarters
By Scott Judy
Two years of preconstruction communication between contractor,
designer and owner is paying off on the complicated, $115
million new headquarters building for the Centers for Disease
Control and Prevention in Atlanta.
The project is ahead of schedule, despite complexities such
as a nonlinear building and adherence to LEED standards.
"Because there was such a gracious preconstruction phase,
the design team had the opportunity to (provide) very good
documents," said Jason Hodges, senior project for Skanska
USA Building, Atlanta. "We're not constantly waiting
on answers to questions. We've been able to flow seamlessly
from foundations to structure to skin to interior build-out."
Skanska won a national preconstruction services solicitation
in September 2001 and worked on design until September 2003
with project architect Thompson Ventulett Stainback &
Associates of Atlanta. In August 2003, CDC awarded Skanska
an $82 million construction-management contract. Notice to
proceed was given on Jan. 5, 2004, with substantial completion
set for August - a 20-month timeframe, compared to the 24-month
preconstruction period.
Micah Rosen, project manager for TVS, said the lengthy preconstruction
ultimately allowed the firm to customize final documents in
accordance with the contractor's planned approach.
"We evaluated just about everything," Rosen said.
"So we kind of tailored the documents to how they were
going to build the building. You don't usually get that opportunity
on a fast-track project."
David Shoffner, construction manager for CDC, said there
also has been direct involvement from the owner.
"The big key to keeping this project on schedule is
the communication and coordination between the government,
Skanska and TVS," he said. "We're extremely open.
We haven't postured at all."
Going Up
From the beginning, there were problems - but plans were
already in place to address them. For instance, the area is
renowned for its inconsistent underground, and the team knew
that the initial borings might not have revealed the entire
picture.
"One of the things you anticipate in DeKalb County is
that once you get in the ground, you're going to find something
different from what a dozen borings can show you," Rosen
said. "It's like stalagmites down there. We knew as soon
as Skanska started digging that we'd be going back to the
structural engineer and making a few changes."
The team's existing contingency plan for just this scenario
enabled it to work around the issue and keep ahead of schedule.
The project used a combination of drilled piers, caissons
and spread footers.
Once out of the ground, the reinforced concrete, 12-story
building started going up on a roughly nine-day-per-floor
cycle. A curve along both sides of the building complicated
this work somewhat, though, Hodges said.
"The uniqueness of the curve didn't allow us to fly
it, so we had to conventionally frame it," he said. "We
broke up the building into three pours, and almost every third
day we were pouring concrete." Each floor measured about
26,000 sq. ft., with pours divided approximately equally.
TVS used masonry and precast for the building's lower exterior,
and a curtain wall system above that.
"We were looking for a progressive image for CDC, but
counterbalanced with permanence and groundedness that you'd
expect from a federal government project," Rosen said.
"So we basically came out of the ground with masonry
and precast concrete. The solid materials really form an anchor.
And then we go to a curtain wall system."
The project topped out Oct. 29.
Radial Design
TVS used the curving radius design to fit the 364,400-sq.-ft.
office building into the site's curved boundary line.
"Drawing was interesting," Rosen said. "It
wasn't some arbitrary thing. A curved building maximizes their
ability to use a limited site."
The curvy design impacted the contractors, too.
"It made for a challenge as far as layout," Hodges
said. "We had to train a lot of the subcontractors on
how to use advanced instrumentation to be able to take advantage
of computer-aided software and being able to lay out curtain
walls and everything on skews and radiuses."
Here, too, the heavy preconstruction input benefited the
contractors.
"That (curving) affords a lot of opportunities for dynamics
in the curtain walls," Hodges said. "That input
at the early stages created a lot fewer headaches once we
got out in the field." As a result, curtain-wall sub
JAMCO of Atlanta has been able to stay ahead of its planned
pace.
"JAMCO adapted to the curvature very well, and they're
ahead of schedule drying in the building," he added.
CDC's Shoffner said numerous other subcontractors on the
job were consulted during the preconstruction phase and provided
good ideas on how to build the project. For example, mechanical
sub McKenney's of Atlanta suggested that it custom fabricate
the pipe at its own shop, instead of using more standard components
and an excessive amount of joints to facilitate the curves.
The end result was both faster installation and higher quality.
"That's something they did to keep meeting the schedules,
but it also gave better durability because now we're not stressing
joints," Shoffner said.
Inside
The CDC's expectations and requirements for this office building
were different from a commercial owner's. The facility couldn't
be lavish, but it needed to be built to last an expected 50-
to 75-year lifespan.
"We had to pay special attention to what was specified
in terms of its durability and life-cycle costs," Rosen
said. "We knew we better not create anything that's too
delicate."
For instance, the architect made judicious use of interior
glass and other durable materials.
At the same time, the team is aiming for LEED certification,
so issues such as indoor air quality, health quality and use
of local materials had to be considered.
Rosen said the LEED standard didn't require too many items
that the firm hasn't been using already.
"It did not seem like a huge step for us," he said.
"We're using an energy-recover unit on the roof, but
we've been using those for years."
The exterior curtain-wall system was designed to allow daylight
to flow into the building without overheating employee workspaces.
Daylighting is another popular LEED feature.
"That is really going to help with the daylighting -
getting that natural light into the inner core of the building,"
Shoffner said. "Halfway into the building, it's still
going to get natural light in there."
For Hodges, this was his first LEED effort, and he said it
was a learning process.
"The biggest thing was getting our arms around the amount
of documentation involved," he added. "But our big
focus has been on acquiring the local and regional materials,
so there's been a lot of coordination between us and the subs
for products to be harvested, manufactured and brought in
from the local market."
Another focus has been on reducing construction waste, another
LEED standard. To date, both Skanska and CDC estimate that
80 percent of material leaving the site has been recycled.
There's plenty left to do, of course. The project was about
55 percent completed in January. But the owner is definitely
happy so far.
"From the government's standpoint, this is an excellent
project," Shoffner said. "We've got a great rapport
with the whole team and a good understanding of how things
are going. The expectations are that we're going to proceed
on just like we are and at the end we're going to turn around
and say, 'That was a darned good project. Let's do it again.'"
|