|
Ashley-Phosphate Road Widening
"No excuses" clause enforced on $50 million South
Carolina highway expansion
by Scott Judy
The South Carolina Department of Transportation made extensive
use of incentive/disincentive pay and a "no-excuses"
clause on its $50.6 million Ashley-Phosphate Road Widening
project in the Charleston area.
Apparently, these tools were put to good use. With the contractor
in the final stages and just months away from the original
completion date, SCDOT officials are describing the work performed
to date as "an A-plus job."
Part of the department's heralded "27-in-7" roadbuilding
program - named for its goal of constructing 27 years of projects
in just seven - the contract is aimed at relieving significant
congestion and related safety problems in the Charleston area.
Ashley Phosphate Road serves as a connector road between
Dorchester Road (South Carolina Highway 642), Interstate 26
and Rivers Avenue (U.S. Highway 52). It also serves commuters
traveling to and from Summerville, Ladson, North Charleston
and Charleston, connecting them to such area destinations
as the Northwoods Mall, downtown and the Charleston Air Force
Base.
The road also serves commercial and industrial development
that lines the project corridor.
Leland Colvin, program manager for SCDOT, said the most recent
average daily traffic count for Ashley-Phosphate was 64,800,
with a rate of 77,700 vehicles anticipated within 20 years.
Traffic on Interstate 26, for which Ashley-Phosphate is a
major interchange, was reported as 115,000 and is expected
to escalate to 182,000 by 2025.
Timeline
Banks Construction Co. of Charleston Heights, S.C., a firm
that specializes in asphalt paving, won the general contract
in August 2002. Work started two months later with substantial
completion set for this summer.
In between those milestones, there have been numerous others
tied to incentive/disincentive pay under the project's "no-excuses"
bonus provisions. First, the contractor team had 60 days from
the time it received its Notice to Proceed to complete construction
of Northside Drive. For every day this part of the contract
was completed ahead of that 60-day schedule, Banks Construction
would receive $6,500 per day in incentive payments.
The contractor had 45 days from the start date to construct
substructures for the South Ashley Phosphate Road and U.S.
Highway 52 Bridge, and a $20,000-per-day incentive to finish
ahead of schedule.
Another section involving both bridge work and widening allowed
563 days and provided a potential $12,500-per-day incentive/disincentive.
Widening yet another stretch of Ashley-Phosphate allowed a
623-day schedule and offered a potential bonus of $6,500 per
day. Widening of the final section and total project completion
was scheduled for 1,017 days, with a $10,000-per-day early
completion incentive.
Colvin said Banks Construction earned incentive pay on all
of the milestone sections.
Project Details
Colvin described the contract as "actually two projects
in one." The first part was to widen approximately 4
mi. of Ashley-Phosphate from Dorchester Road to Rivers Avenue.
The second was building the major interchange with I-26.
The interchange portion consists of replacing and widening
two interstate overpasses, constructing an on/off ramp for
I-26 East and adding "collector-distributor" lanes
serving Ashley Phosphate and U.S. 52 for I-26 West.
The contract also called for replacing the U.S. 52 overpass
with a new three-lane bridge and replacing the existing five-lane
Ashley Phosphate overpass with a 10-lane structure.
The remainder consists of widening Ashley Phosphate Road.
This widening effort was "pretty simple" because
the existing road was already five lanes wide - two lanes
in each direction with a median lane, Colvin said. In short,
there was plenty of room to add two lanes and accommodate
associated traffic shifts.
"We just reduced the lane size and went out and widened
half of the road, shifted traffic back and then went back
and widened the other half," he added. "With five
lanes, that's not too difficult."
Banks started work at the I-26 interchange area, located
at the eastern end of the project. Colvin said the team had
to hustle through this section as quickly as possible. This
section featured a $20,000-per-day incentive/disincentive.
The interchange area required significant soil stabilization,
a situation that normally might have been addressed with a
surcharge of soil material left on the area for an extended
period of time. Due to the area's traffic volumes, the group
simply couldn't wait that long.
"We put some heavy incentive/disincentive on that end
of the project to where we could get the contractor in and
out," Colvin said.
DOT and project designer Earth Tech Inc. of Raleigh, N.C.,
opted for a variety of ground modification techniques, including
vibratory concrete columns and vibratory stone columns.
"We had 16,236 lin. ft. of vibratory concrete columns
and 20,000 lin. ft. of vibratory stone columns," Colvin
said. Installation of these substructures provided the necessary
support for the new overpass structure.
The proximity of the interchange work to a popular shopping
center actually caused unanticipated changes.
"We're close to the Northwoods Mall, and what we did
not account for in our traffic-control plan was pedestrians
as we phased the bridge," Colvin said. "We had to
tweak the design to include a pedestrian path during the construction
phasing on the bridge there at I-26."
Partnering and Progress
As this project nears completion, Colvin said everything
has gone well. He praised the partnering initiative undertaken
by the project team, which was led by Banks Construction and
also the project's construction engineering and inspection
firm, Davis & Floyd.
"The biggest thing was just the partnership," Colvin
said. "We got together with the city, the county, fire
department, police department, all of the utilities and our
contractors and had periodic partnering sessions. So it's
gone very well."
Project Team:
Owner: South Carolina Department
of Transportation
General Contractor: Banks
Construction Co., Charleston Heights, S.C.
Designer: Earth Tech Inc.,
Raleigh, N.C.
Construction Engineering and Inspection:
Davis & Floyd
Useful Sources:
http://www.dot.state.sc.us/Projects/Ashley/default.shtml
|