|
North Carolina's Knightdale Bypass
14-mi. bypass to relieve congestion
along U.S. Highway 64 into Raleigh
by Carter Langston
An aggressively scheduled 30-month highway construction project
is taking shape around Raleigh, N.C., although it's running
a little late.
Due to unusually wet weather, the $170 million Knightdale
Bypass is expected to be substantially complete by spring,
rather than the earlier Dec. 31 target. There are two major
contracts - North Carolina Constructors' $131 million design-build
contract, and a $40 million effort being overseen by Vecellio
& Grogan.
"The weather was the most critical variable through
the end of the year," said Steve Leonard, resident engineer
with the North Carolina Department of Transportation in Raleigh.
The congested U.S. Highway 64 is the main corridor connecting
Raleigh to the eastern part of North Carolina. Once complete,
the Knightdale Bypass will connect U.S. 64 East with Interstate
440.
Since work on the 14-mi., six-lane bypass started in July
2002, there have been ice storms, eight hurricanes, unusually
heavy rain, cement shortages and bridge building hurdles in
regulated wetlands. All caused delays.
In November 2002, a severe ice storm froze the region and
delayed work for days. Weather has been a constant test since.
Temporary erosion control devices and access roads were frequently
washed out, destroyed or clogged. And the region's red clay
soil holds water for days after heavy rains.
"We lost six weeks to eight named storms," said
Paul Newman, project manager with North Carolina Constructors.
"We need unusually and unseasonably dry weather to achieve
our substantial completion target."
Substantial completion means that traffic may course the
new artery, but construction may not be fully complete until
June.
NCC, a 60/40 joint venture between HBG Flatiron and Lane,
is responsible for 9.6 mi. with a $131 million design-build
contract. The company responded to delays by increasing work
schedules from six to seven days on priority operations.
"NCC capitalizes on the strengths of the two companies,"
Newman said. "Flatiron took the lead in bridge building
and Lane leads the concrete paving."
Longmont, Colo.-based Flatiron erected 23 bridges at 15 sites,
including six precast bridges that feature a drilled shaft
into riverbeds below. Construction in the highly regulated
wetlands required temporary work structures to position cranes
and other equipment without harm to the banks below.
Newman said the bridges are 99 percent complete. Remaining
work includes finishing the expansion joints and paving the
approach.
The most demanding bridge sites were Bridge 2 and Bridge
4. The length of Bridge 4, which spans 1,500 ft. over Mango
Creek and the Neus River, made it the most difficult. Newman
said that Bridge 2, which actually comprises two structures,
was complicated because both structures were erected almost
simultaneously over Crabtree Creek.
At the Bridge 2 site, there's the mainline bridge on the
bypass and a crosscutting overpass.
"We drilled the shafts for the overpass at the same
time that we drilled the shafts for the mainline bridge,"
Newman added. "The different elevations made this the
second most complicated bridge construction."
Joint venture partner Lane, headquartered in Meriden, Conn.,
was hampered by a cement shortage during 2004 and has been
about a month behind schedule. The mainline is comprised of
290-mm-thick concrete pavement resting on a 75 mm permeable
asphalt drainage layer on a 25 mm asphalt surface. Those layers
top a 200-mm-thick lime- or cement-treated subbase.
Mangum Construction is completing the asphalt work along
the shoulders.
The final mile that ties the new bypass with existing traffic
along U.S. 64 East has been prepared, but not paved. That's
the last phase and work is expected to conclude in time for
the spring substantial completion date.
NCC employed 15 subcontractors. The largest was Glover Construction
of Pleasant Hill, N.C., which excavated about 2.85 million
cu. meters of dirt and rock.
Knightdale Bypass is the first project for NCC.
"We make a good team," Newman said of the joint
venture. "NCC is currently bidding on another highway
construction project near Lexington."
Recent legislation allows NCDOT to let up to 25 design-build
projects each year. In 2005, the department expects to issue
about seven or eight design-build contracts.
The Knightdale job is Leanard's first experience with design-build,
and he said it has been "a good personal experience for
me. [NCC] is a good design-build contractor, organized and
good at coordinating work."
While NCC won the fast-tracked mainline contract, Vecillio
& Grogan took the $40 million interchange and flyover
section, connecting the final 2 mi. of the mainline to I-440
and New Hope Road.
This section, also expected to be substantially complete
within the first quarter of this year, consists of concrete
and structural steel.
As work along the mainline winds down, another contractor,
Barnhill Construction, is working in tandem on a tie-in ramp
for a future project connecting the bypass with Highway 540.
The coordinated effort will ensure that traffic along the
Knightdale Bypass is not impeded as work continues on the
Highway 540 outer loop through 2006.
|