Features
 Current Features
 Past Features





Features - February 2005

Hometown Renovation

LaGrange, Ga., project has added meaning for contractors

By Scott Judy

Paul Meadows remembers growing up in Troup County, Ga., and attending numerous parades that culminated in downtown LaGrange's Lafayette Square. Even though he lived outside of town, LaGrange was "part of home."

Today, Meadows works as a project executive for Batson-Cook Co., a major contractor headquartered in nearby West Point, Ga., also in Troup County, that ranks among Engineering News-Record's Top 400 Contractors nationally.

While Meadows doesn't live in Troup County anymore, it's in his and Batson-Cook's hometown county that he is working on what he considers a "once-in-a-lifetime project," one he views as a chance back to contribute to the community in which he grew up.

"We're very excited," he said. "It's one of the biggest projects I can imagine for LaGrange, and it's something that the people have been very excited about and talked about for years."

Likewise, Troup County was pleased to be able to hire a local contractor.

advertisement

"By going as local as much as possible, we feel we're helping our local economy," said County Manager Mike Cobb.

The project's location near Lafayette Square will be a boost to the downtown economy, Cobb added. "The center will meet the needs of the community for years to come," he added. "We're ready to get in it."

The Project

The project will consolidate numerous governmental functions and improve ease of use for area residents. It includes a new, 124,000-sq.-ft. courthouse building; a 138,000-sq.-ft., 335-space parking deck; and the renovation of a historic courthouse building. The project is being built as the result of a September 2001 passage of a local tax that also funds several enhancements to the county's recreational amenities.

The new courthouse includes county administration offices, various courtrooms, prisoner holding cells and other spaces. The renovated structure will accommodate juvenile court and other support offices. Completion is set for May.

Batson-Cook is serving as construction manager and also holds contracts covering concrete work and general trades. The contractor self-performed all concrete work on both the new courthouse structure and the parking deck.

The new building was constructed with a cast-in-place-concrete shell and an exterior featuring brick, architectural precast concrete and copper shingle siding along the roofline.

The new courthouse and parking deck rest on driven steel piles.

"That was quite an undertaking," Meadows added. "You get a lot of noise and vibrations, so we went to extensive lengths to monitor vibrations in the existing buildings downtown to make sure none of those were damaged," including the existing courthouse across the street.

Foundation contractor F & W Construction of Ozark, Ala., installed the roughly 300 piles required for the two structures. Meadows said vibration proved to be quite low, "well within the tolerances."

Batson-Cook crews oversaw the concrete work, utilizing a forming subcontractor and another firm to handle finishing. "Once we had the structure poured out on (the new courthouse), we moved over to the parking structure and started working," Meadows said.

Crews topped out the new building in July and then poured out the parking deck in October.

Batson-Cook divided all three phases of the project - new building, parking deck and existing courthouse - along trades, so that one firm would handle all related construction in all three parts of the project.

Interior finishes in the new building were "pretty basic," Meadows said, with higher-end ceiling and millwork detail included in the judges' chambers and courtrooms.

Outside, the goal was to design the new, up-to-date structure to fit in with the surrounding architecture.

"We wanted it to blend in," said Troup County's Cobb.

"They wanted something that was appropriate to the area," said Lamar Chambers, project architect with Urban Design Group of Atlanta. "They wanted something that had a certain stature, but something that was very cost-effective."

To that end, the architect chose materials common to the area, opting for a mostly brick exterior but with some precast concrete as well.

"We tried to mold the exterior skin of the building to have the right feel for that area," Chambers said.

The Renovation

Less typical was the renovation of the existing courthouse.

A three-story, 17,000-sq.-ft. structure built in the 1930s, the existing courthouse was out of date and lacked true handicapped accessibility. A beautiful courtroom on the third floor, which will serve as juvenile court, served as the main impetus for preserving the structure.

Batson-Cook and its crews started work on the existing building by first doing an asbestos abatement and then made it watertight with a new roof and new windows.

"It had leaked over the years, so one of the first things we did was put a new roof system on it," Meadows said. "They also had problems with water coming through some of the exterior walls. We actually started putting the roof on first, and then we started doing the exterior wall repairs."

Engineered Restorations of Lawrenceville, Ga., regrouted the joints of the exterior marble walls and also cleaned the entire exterior.

Meadows said easily the most difficult construction task was the elevator installation.

"We had to cut through a wall from the basement side into a crawl space," he added. "And no one really knew what was on that other side of the wall. Once we got in, we found the dirt was much higher than floor level.

"We had to hand excavate down probably 8 ft. just to get down to where the floor level would be, and then hand excavate again for the elevator pit. Then we had to structurally support each floor before we cut those holes for the elevator to travel from top to bottom."

Elevator installation took about three months.

To function as a modern facility, the building needed completely new communication, security and other systems.

"Today's buildings require a lot of communications electronics, a lot more security electronics, and we expect the security to be tighter and more automated than it was when it was built," Chambers said.

There was little space in which to install these systems, and they needed to be hidden.

"We tried to run those (systems) in those less-public areas," such as the offices, Chambers said.

Again, the main focus of preservation was the upper courtroom.

"It's a beautiful old courtroom, with lots of marble," Chambers said. "We tried very hard to keep that space like it was originally designed, but we still had to put in new air conditioning, fire protection, sprinkler systems, new lighting without intruding on that beautiful old space."

To help protect the space, designers called for several smaller HVAC units instead of a single larger unit. The smaller systems required smaller ductwork, which was necessary due to the existing space.

To date, the project is under budget and remains on track for the original May completion date. That's music to Cobb's ears.

"If you can say that, you've said a lot," he said. "We're very excited about being able to utilize this new facility."

Meadows said he's pleased that a project that is as personally meaningful to him is heading for a happy ending.

"It's been very fulfilling," he added.

Useful Sources:

 

Click here for past Features >>





 


Network Sponsors

© 2009 The McGraw-Hill Companies, Inc.
All Rights Reserved