|
Standing Above the Rest
29-story Condo is Second-Tallest
Building in South Carolina
By Bea Quirk
Myrtle Beach-based Dargan Construction Co. reached high to
achieve its dreams with the 29-story Margate Tower, which
completed two months ahead of schedule.
"We had the wind at our back," said Harold G. Cushman
III, Dargan vice president.
The 329-ft. tall condominium tower is the second-tallest
building in South Carolina and sits on the ocean within the
upscale residential community of Kingston Plantation, at the
northern end of Myrtle Beach. It features 50,000 cu. yds.
of concrete, 60 mi. of wood trim and 5,000 tons of reinforced
steel.
The project was developed by FelCor Lodging Trust, a Texas-based
real estate investment trust. Earl Swensson Associates Architects
of Nashville was the project architect.
In addition to being the tallest structure Dargan has ever
built, Margate is the most expensive, with a construction
cost of $75 million. Typically, the company's projects average
between $20 million and $30 million, said Brice Harry, project
manager for Dargan.
The project showcased the variety of Dargan's skills, from
constructing a massive structure to installing carpets, flooring,
cabinetry and fixtures in 251 customized condominiums.
The project almost didn't get off the ground. Construction
was set to begin in November 2001, and the final meeting to
seal the deal between all the parties was scheduled for Sept.
11 of that year. As a result of the events that day, some
of the participants couldn't even get to the session, and
the project was put off for a year. Ground was broken in September
2002.
Before reaching for the sky, Dargan had to dig deep for a
solid foundation, using auger-cast drilled piles installed
45 ft. deep.
"We had to drill piles 15 ft. into the limestone rock
layer to get the loads required for a building of this size,"
Harry said. "That meant all the foundation work was done
below the water table and everything had to be dewatered.
We had a pumping system all around the site."
The residential nature of the surrounding area also posed
logistical hurdles. To keep the cars of the 500-plus workers
away from Kingston Plantation, crew members were bused in
from a nearby parking lot Dargan rented during construction.
Keeping noise to a minimum was another goal, and work always
ended by 6 p.m. Quieter electrical pumps were used instead
of diesel ones.
Keeping tight control over the quality of the cast concrete
was the toughest part of the job. The team opted to solve
that problem by asking the ready-mixed concrete company not
to allow any water on the trucks and no water to be added
onsite.
"After considerable thought and coordination with the
concrete supplier, we decided the best scenario was to have
a qualified technician onsite who had the power to adjust
the mix through the addition of admixtures in lieu of water,"
Harry said. "Only the expert dealt with it, and nothing
was tampered with onsite by unauthorized personnel. The guys
in the field could focus on their jobs - getting the tower
built."
The new procedure meant educating the drivers. When they
voiced concern about their inability to wash down their trucks
if they didn't carry any water, a special area was set up
for them where they could do that before they went back on
the road.
The system worked, and "we had no problems with concrete
strength," Cushman said.
He praised the concrete supplier, Ready Mixed Concrete Co.
of Myrtle Beach for its cooperation and knowledge, as well
as for keeping prices locked in. The only problem occurred
in the preplanning stage when domestic suppliers had to be
found for post-tension strand after foreign companies withdrew
from the U.S. market.
Often with condos, the general contractor isn't responsible
for individual unit finishes. But with Margate Tower, Dargan
also upfitted each of the condominiums, which Cushman said
were 99 percent sold before the company broke ground.
Again, logistical issues had to be solved, such as how to
get rolls of carpet that didn't fit into standard elevators
up 29 floors. Dargan staff also worked closely with the sales
team to make sure each unit was built to the owner's requirements.
Condo owners were able to order upgrades such as granite
countertops, surround-sound systems and marble flooring. And
each of the upgrades had options. For example, there were
three different marble flooring upgrades to choose from and
two kinds of wood - maple and cherry - for the cabinetry with
four different finishes.
"Coordination and meeting deadlines were the keys,"
Cushman said.
Cushman added that successful coordination at every phase
of the project led to the building being ready for buyers
in August, two months ahead of schedule. In addition to Harry,
the project manager, there was a general supervisor, two project
supervisors and three assistant supers. "We have a tight
organizational structure, and we have different supers for
the different phases," he said. "Hard work, good
subs, teamwork and good scheduling also helped us finish early."
That early completion also helped everyone breathe easier
when hurricanes hit in late August and September. Although
the South Carolina coast was not directly hit, the coast did
experience winds of up to 70 mph. "We still had men onsite
and made preparations," Harry said.
Project Team
Owner: FelCor Lodging Trust,
Irving, Texas
Operator: Hilton Hotels
Corp.
Architect: Earl Swensson
Associates Architects, Nashville
General Contractor: Dargan
Construction Co., Myrtle Beach, S.C.
|