|
5R and ATL's New Fifth Runway
$360 Million Excavation Project
a Model of Innovation, Safety
by Scott Judy
Some creative thinking has enabled joint-venture contractor
5R Constructors LLC to do something pretty incredible - mine,
move and place nearly 25 million cu. yds. of embankment material
for Atlanta International Airport's new Fifth Runway about
six months ahead of its original 30-month schedule.
With a $350 million contract, plus potential for an extra
$10 million in early-completion bonuses, 5R began mobilizing
a fleet of more than 85 units of all-new Caterpillar equipment
in September 2002.
That fleet size is even more impressive given that 5R's main
method of moving material was a 5.5-mi.-long conveyor system.
This method has proven to be the best - and really only -
choice, providing huge time and cost savings over other alternatives
and critical environmental and safety impacts as well.
Innovative Conveyor
When the project bid in 2001, 5R Constructors - comprised
of C.W. Matthews Contracting Co., APAC-Georgia and Michael
Thrasher Trucking, all of Atlanta - was the only bidder. A
lawsuit was filed challenging the award, but a court-appointed
arbitrator reaffirmed it in early 2002 after finding the city
had attempted to generate as much competition as possible.
A major factor in restricting the number of bidders may have
been the city's requirement that the bidder obtain some type
of control over 27 million yds. of dirt.
Frank Nichols, president with APAC Southeast and a project
executive with 5R Constructors, said the site the joint venture
controlled was the only one that could work well with a conveyor
system, and that hauling material with trucks from other sites
to the runway would have been cost- and time-prohibitive.
The conveyor concept "sold itself," Nichols said.
"It was high production, no pollution, no increase in
traffic, no noise and it didn't do any damage to the roadways.
And it moved the material faster than you could with any other
means. It made it a win-win situation for everyone."
Partly because the use of the conveyor eliminated the need
for many haul trucks - trucks that would likely be driving
in or near traffic from offsite - the project has been a safe
one without any serious injuries. In fact, 5R Constructors
has won the Mine Safety and Health Administration's annual
"Sentinels of Safety" awards two years in a row
for being the safest quarry site in the country.
5R planned to convey the material from the mining/quarry
site to several discharge bins located around the project.
In addition to the length, the conveyor is unusual in that
it travels through mostly well-developed areas, such as industrial
parks, and over Interstate 85 and Georgia Highway 85.
While C.W. Matthews would be more focused on placing the
material, APAC took responsibility for mining and loading
it onto the conveyor. Minority partner Michael Thrasher Trucking
assisted throughout the project.
Nichols said the company used three scalping plants, two
stationary crushers and two more portable crushers to feed
multiple loading points. The use of several loading points
- as well as the numerous crushing units - illustrated the
quantity that was required to keep on schedule.
"The production design is about 1 yd. per second,"
Nichols said. "(The conveyor) moves at about 800 ft.
a minute, so it's going down the line."
The contractor used three Caterpillar 5110 mining shovels
to initially excavate the quarry/aggregate material and then
10 Cat 773 65-ton haul units to feed it to the crushers. The
scalping plants processed soil material.
Unloading
While the concept of delivering material by conveyor was
not a novel one, the speed and quantities involved on this
project were unlike anything the contractors had ever encountered.
"The real question was 'What do we do when this material
gets to be filled and how do we take it off (the conveyor)
and how do we place it?'" said Bill Hammack, managing
director of 5R and executive vice president and COO for C.W.
Mathews Contracting.
Prior to bidding, Hammack and others with 5R began looking
at equipment options by utilizing Caterpillar's fleet production
software program. They considered belly dump trucks, articulated
trucks or rigid-frame haul trucks.
The team eventually opted to use 100-ton Caterpillar 777
rigid-haul units. With the considerations of cost and schedule,
the 5R team figured that it could maintain the pace needed
with just six trucks - if it restricted their travel radius
to no more than 750 ft. and kept them repeating through quick
loading cycles.
"If we could load one of those within 20 seconds, then
we didn't need but six trucks (on the placement side) to build
this job," Hammack said. "The trick was, how do
you load a 100-ton truck in under 20 seconds?"
For that, 5R went to Astec Industries and told the manufacturer
of material processing equipment exactly what it needed -
bins that could contain enough material to discharge it into
the 100-ton 777s in just a few seconds.
"The trick is, when those gates open, that material's
got to come out," Hammack said, adding that the first
truck loaded in a much-too-fast five seconds.
"That's not a good thing," he said. "(The
777) came off the ground from the impact. So we slowed down
the opening of the (bin) gates a little (and) averaged about
12 seconds in loading a truck."
From there, the 777s drove downhill no more than 750 ft.
- the discharge bins were always situated on a hill - and
dumped the material, where a fleet of loaders, dozers, scrapers,
motor graders, rollers and other types waited to move the
material into place.
Significantly, the crews used no stakes to place the material.
All dozers and motor graders were equipped with GPS units
that assisted in controlling the grade.
"They know exactly how to cut the grade based on that
information," Hammack said. "We're actually paid
off of that GPS information. Very few stakes have been put
on the job."
Placing
And there was plenty of material to move. The site of the
future 9,000-ft.-long runway - which will span Interstate
285 when completed - was much too low. The average fill depth
for 5R's contract was 90 ft., and it reached as much as 110
ft. in spots.
To meet the project schedule, the 5R team needed to keep
the material moving nearly seven days a week. The contractor
was mostly able to do this - even during an exceedingly rainy
2003 - despite the material being made up of a considerable
amount of Georgia red clay. The construction team was able
to do that because between 25 and 30 percent of the material
is rock.
"With the weather conditions, that (rock) turned out
to be a real blessing for us, because we were able to adjust
the percentage of rock and run when a traditional project
would have to shut down," Hammack said.
During the wet and cold weather, Nichols said, "We were
mixing rock and soil together the whole time to try to keep
a flowable mixture. (Some days) it was like either rocky dirt
or dirty rock that we were running."
The project specifications were such that 5R simply had to
deliver material that was no bigger than 7 in. in size (or
"minus 7-in.") and meet the moisture and density
requirements. "We were able to selectively switch from
say 80 percent minus-7-in. (rock aggregate) to maybe no minus-7-in.
material, depending on weather conditions," Hammack said.
"So we maybe wouldn't ship any rock when we had long
dry periods and simply load dirt."
Nichols added that because of the versatility of the design,
work could continue through the winter. "Of course, if
you can run a full rock fill, you can make a wonderful product,"
he said. "But you have to run enough dirt to fill the
voids, and that's what we were demonstrating we could do."
The top 7 ft. of the embankment will contain mostly dirt.
Innovative Equipment Monitoring
Another innovative part of this project can be found in the
equipment running around the site. Made up almost entirely
of new Caterpillar construction and mining units, the 5R fleet
represents a capital investment of more than $30 million -
and was a critical component to keeping the job on schedule.
Many of these units, such as the 777s and D10 dozers, couldn't
be replaced easily because they are so large that they are
shipped from the plant in pieces, on several tractor/trailer
loads.
To keep them up and running, 5R Constructors entered into
a partnering agreement with Caterpillar and Yancey Bros.,
the Atlanta-based Cat distributor. Caterpillar would supply
the equipment and Yancey Bros., working onsite and utilizing
state-of-the-art satellite-based monitoring equipment, would
manage and service the huge fleet.
Yancey Bros. was able to keep track of the most critical
data about each machine.
"They could tell if we had an engine running hot, a
transmission slipping - they could even tell us if we had
a driver incorrectly shifting the transmission," Hammack
said. "It was amazing. They really minimized the downtime
of the equipment."
The bottom line, of course, is that this contract is turning
into a huge success story - on time and under budget. 5R's
Hammack said the team expects to conclude its work and be
completely demobilized by Christmas. The original "early"
completion date was June 27, 2005.
Airport officials are highly pleased with 5R's work to date.
"5R's performance has been very impressive," said
Ben Decosta, airport manager. "The innovative use of
the conveyor has exceeded the expectations of all associated
with the project. Additionally, we have been impressed by
their attention to detail, such as special maintenance programs
necessary to keep the conveyor and the fleet of construction
equipment operational, and their willingness to address public
concerns pertaining to temporary construction impacts."
|