Features
 Current Features
 Past Features





Features - November 2004

Pelham Wastewater Treatment Plant

$88 million project will triple capacity of Greenville facility

By Debra Wood

The Western Carolina Regional Sewer Authority's expanded and upgraded Pelham Wastewater Treatment plant will enable the agency to consolidate operations at two plants and upgrade facilities to meet all environmental regulations.

"It's increasing the permitted capacity from 7.5 million gallons a day to 22.5 million gallons a day," said John Langley, the authority's project manager. "Growth in the area is the main reason."

At the Pelham plant, crews from Pizzagalli Construction Co. of South Burlington, Vt., are adding influent pumping capacity, new headworks and screening facilities, primary clarification and anaerobic digestion equipment, a 15-million-gallon holding basin, effluent filters and ultraviolet disinfection, and odor-control systems.

advertisement

The company also will modify the aeration basins, transitioning from a mechanical oxidation ditch to a diffused-air system. And it is moving the plant outfall downstream to eliminate the need to pump effluent during high-water conditions. The former Taylor wastewater facility will be converted to a pump station and holding facility.

Black & Veatch Corp. of Shawnee Mission, Kan., designed and engineered the $88 million expansion. The company also serves as the owner's representative during construction.

All work takes place on an existing wastewater-treatment site and has required extensive sequencing, with four main phases, each dependent on elements in prior phases. The plant must maintain operations and meet government standards.

"It is a very complicated sequence," said Jeff Wells, project manager for Black and Veatch. "It is online and has to meet limits every day, and we are in the middle of that plant. We're not off to the side."

Pizzagalli broke ground in June 2003 and expects to complete the work in June 2007. At the beginning of September, the project was six months ahead of schedule. Art Seymour, project manager for Pizzagalli, said the schedule has been aggressive and crews have worked five to six 10-hour days. Wells estimates the schedule has about a year of time built in to handle the sequencing.

"This job is incredibly complex," Seymour said. "We have every inch of ground destroyed here."

Pizzagalli shaved some time off the schedule through innovative techniques. Rather than pouring the seven, concrete clarifier holding tanks and troughs around tank perimeters separately, as is customary, Pizzagalli purchased a proprietary forming system to pour the trough with the wall.

"It was a whiz-bang neat thing," Seymour said. "It saved us about a month on each one of them. It worked out really good for us."

Western Carolina has moved into the new operations building. The balance of the first phase, influent pumping facilities, was scheduled to go online at the end of October. Crews also dug 37-ft. deep between the river and an existing pump station for the new influent pump station. Pizzagalli put in some taps and plugs and bypassed to the existing lines.

"The influent is deep because it is the low spot in the system," Seymour said. "At one time, we thought we might have to pump across the river, but we worked out a way not to do that. That would have been risky with temporary lines."

Pizzagalli self-performed the grading, excavating, backfill, concrete and piping. It subcontracted electrical, instrumentation and specialty work.

Crews are converting aeration basins, one at a time, to a time-bubbled, diffused air process. Once that is completed, all the sewage can flow through the new basin and contractors can work on the old basins.

Crom Corp. of Gainesville, Fla., is building the 15-million gallon, prestressed-concrete holding tank. It is 250 ft. in diameter with 40-ft. sidewalls. The company will build the tank onsite and attach it to 688 rock anchors Pizzagalli has installed.

This will be the first Western Carolina plant to incorporate odor-control systems, which were added because the plant is near residential areas. The headworks and primary clarification areas will be covered and any fumes coming off will pass through a scrubber device.

WEDECO Ideal Horizons of Charlotte, N.C., will manufacture and install the UV-light disinfection system, which will take the place of chlorine. The water will flow through a channel and pass special UV bulbs encased in sleeves. The Pelham facility will be one of the largest UV installations in the Southeast.

"Part of the reason we are going to UV disinfection is the state regulatory agency is adding to our permit limitations on chlorine byproducts," project manager Langley said. "These limits are low enough that it's not practical for us to use chlorine anymore."

Western Carolina moved its outfall defuser down river, below a rock dam listed on the National Register of Historic Places. The work required digging a ditch and placing the line through an area that included riverbed and an 1800s textile mill.

"We were between a new bridge pier and an old historical monument," Seymour said. "It was all rock in the river."

Pizzagalli built a berm, pumped the water out and completed the job in sections. It hammered the rock to avoid blasting, which could have damaged the historic structures. It took the crew about two weeks to put in the 80-ft. header in the river.

Throughout it all, there have been no spills, and state inspections have turned up no leaks or permit violations.

Project Team:

Owner: Western Carolina Regional Sewer Authority, Greenville, S.C.
General Contractor: Pizzagalli Construction Co., South Burlington, Vt.
Engineer: Black & Veatch Corp., Shawnee Mission, Kan.

Useful Sources:

Click here for past Features >>





 


Network Sponsors

© 2009 The McGraw-Hill Companies, Inc.
All Rights Reserved