|
Segment 5: On Track?
Complexities of Nearly 45-Mi. Project
Were Underestimated
by Scott Judy
Simply by its scope, the 43.5-mi. of "double-tracking"
contained within Tri-Rail's Segment 5 contract makes this
project one of the biggest ever undertaken in the state of
Florida. Even so, since joint-venture firm Tri-County Rail
Constructors first started work in January 2002, it's become
evident that the construction team failed to realize just
how big and complicated it would be.
"It's been more (challenging than we thought),"
said Dan Mazza, director of engineering and construction for
South Florida Regional Transportation Authority, the agency
that owns and oversees the Tri-Rail system. And because of
the length of the project - previous double-tracking contracts
measured about 7-8 mi. in length - "You've got more people
with their hands in the pie," he added.
Dave Mazzo, project manager for Tri-County Rail Constructors,
agreed. He said the interaction with third-party groups, such
as local municipalities, rail operators and utility providers,
proved to be more cumbersome than either entity had envisioned.
And most of these third-party groups had requirements that
impacted the phasing and construction of the project.
"The impact to the owner's operation versus the amount
of (utility) locations necessary to progress the massive amount
of work and to maintain schedule was seriously underestimated
when the contract was put together," Mazzo said. "It
had an impact on the schedule of virtually every activity.
"We expected it to be complicated but it was an order
of magnitude more difficult than expected," he continued
regarding the coordination effort.The project has required
a lot: laying nearly 45 mi. of a second mainline track; upgrades
and replacement of existing track; upgrades to the northern
maintenance and layover facility; construction and rehabilitation
of bridges over 12 canal crossings; renovation of nine existing
stations; construction of a new Boca Raton Station and demolition
of the existing facility; acquisition of new locomotives/cab
cars; and upgrades to passenger information systems.
The major effort also meant more than 1 million cu. yds.
of excavation and fill; 270,000 railroad ties; 72 at-grade
traffic crossings; 10 station upgrades; 30,000 lin. ft. of
various retaining wall and crash walls; 300,000 tons of railroad
ballast; 18 bridges; and associated signal work.
All Aboard
Before 1999, when the Tri-Rail Commuter Rail Authority (now
SFRTA) began moving forward with plans for Segment 5, the
owner had been progressing on its double-tracking effort in
much smaller increments of about 7-8 mi. in length - as much
as the agency's budget would allow.
These were relatively small steps in the authority's long-range
effort to double-track the entire length of its 72-mi.-long
system. With a totally dual-tracked system, the authority
could provide 20-minute headways between trains. According
to studies, the ability to provide this frequency would greatly
improve ridership and perhaps triple it within several years.
During this planning period, design-build was growing in
popularity, and the state had even approved the use of the
delivery method by public agencies. When the federal government
provided guaranteed funding for the entire remainder of the
system, the owner opted to finish out the double-tracking
with one massive design-build contract - Segment 5 - and meet
its goal of 20-minute headways.
"They wanted to get this done in a short period of time,"
Mazza said. "We did all of the other ones as design-bid-build,
and it would take right around two years to do an 8-mi. section.
The fastest way they thought they could do that was by doing
it design-build."
Tri-County Rail Constructors - a joint venture between Herzog
Contracting Corp. of St. Joseph, Mo.; Granite Construction
Co. of Tampa; and Washington Group International of Boise,
Idaho - won the project with a $231 million cost figure.
Herzog, the joint venture's lead contractor, is providing
project management and overseeing track installation and related
civil work. Granite is building all structures, including
numerous stations and bridge crossings. WGI is providing design
and quality assurance/quality control.
Herzog Contracting is part of the same firm that also owns
Herzog Transit Services, which operates the Tri-Rail system.
Third-Party Issues
From the beginning, the sheer size of Segment 5 made it a
different ballgame. Mazza said that previous projects "were
small enough that we were kind of under the radar. And we
could get (some) things done with just the field crew."
Segment 5's radically higher profile has invited closer scrutiny
by all manner of groups, most notably CSXT, the rail-car provider
and operator for Tri-Rail, which has been given project review
and approval authority.
"It just seems like there's a lot more steps that we
have to go through to get CSXT's approval," Mazza said.
"They're basically approving everything."
But it's not just CSXT. "It's the learning curve of
getting everybody onboard who wasn't involved with these projects
in the past," Mazza said. "When you have to get
approval from more people, it makes things harder to manage."
For example, input from the third parties led to a complete
reshuffling of the work plan, Mazzo said.
"The general plan was to build and cut-over new sections
of track before proceeding to take other sections away for
reconstruction/upgrades," he said. "However, the
additional constraints due to third-party requirements dictated
that we resequence the entire schedule." In short, the
contractor had to work where it could, when it could, according
to these third-party requirements.
Generally speaking, crossings and bridges were independently
progressed with the intention of having them ready so as to
not impede the earthwork and track work. Also, the contractor
had as many as eight stations progressing simultaneously.
Additionally, the contractor experienced another hinderance
to the original schedule when new water-retention rules enacted
by the South Florida Water Management District mandated a
recreation of the drainage structure for the entire Tri-Rail
right-of-way. This impacted the excavation portion of the
contract.
"There was considerable cut/fill required in order to
accommodate the retention requirements of South Florida Water
Management District, Lake Worth Drainage District and Army
Corps," Mazzo said.
Design-Build Impact
With these hurdles and others - including the discovery and
necessary relocation of an endangered species of gopher tortoises,
plus DOT-added extras such as sound-barrier walls in Palm
Beach County - both project cost and schedule have grown.
Instead of the original $231 million figure, both owner and
contractor are using $261 million as the new cost. And that
probably won't be enough, Mazza said. "We have $15 million
of contingency, and I envision us using every bit of that,"
he added.
As for the schedule, that's shifted from the original March
'05 deadline to November - though the March target still stands
as the contractual deadline. "Whether it ends up being
liquidated damages to the contractor, or whether we end up
negotiating days, is yet to be seen," Mazza said.
Mazzo insisted that TCRC is making up lost time.
"The completion of the north end of the project will
be accomplished by beginning of 2005, and coordination of
remaining work as well as subsequent impact to operations
will be greatly improved," he said.
SFRTA's Mazza also has seen improvements here.
"It could probably be said that early on in this project
there wasn't enough communication going back and forth,"
he said. "But I think now all of the parties have the
same goal, and that's trying to get this project finished
and trying to minimize delays. Everybody's working well together
now, including CSXT."
Meanwhile, opinions differ on the impact of using design-build.
Mazza, who previously worked with Florida DOT, said he is
unconvinced as to its benefits, indicating this project may
not have been well-suited to the delivery method.
"The jury's still out," he said. "The problem
with design-build in this corridor is you have so many (involved)
parties."
Mazzo agreed there were third-party impacts, but argues they
were less under a design-build situation than they would have
been otherwise.
"The (design-build) process probably mitigated what
otherwise would have been much worse impacts to the project
schedule," he said. "The ability to remain flexible
and develop work-arounds for delays/changes is probably the
greatest plus of (design-build) for this project."
There is no disagreement as to the quality of work performed
to date, though.
"That's one thing we feel comfortable with," Mazza
said. "This contractor does quality work, and the quality's
been there."
There's still plenty of work left to do, and Mazzo said there
will not be any more underestimating of the remaining workload.
"It will be a challenge until the end," he added.
|