|
Raleigh-Durham: New $350
Million Terminal
Though related demolition work is just beginning, Raleigh-Durham
International Airport's new $350 million Terminal C will be
one of the next shiny, new terminals in the Southeast.
Designed by Fentress Bradburn Architects of Denver - designers
of Denver International Airport - it is envisioned as reflecting
the rolling hills of North Carolina. The architect's plan
for the project was unveiled in March.
"Technology and airports' needs rapidly change, and
security procedures, in particular, are now more than ever
in a state of flux," architect Curtis Fentress said in
a released statement. "Having a facility that accommodates
change is the key to a successful airport terminal building."
In mid-September, the Raleigh-Durham Airport Authority awarded
a $4.6 million contract to D.H. Griffin Construction Co. of
Raleigh for the demolition of approximately 150,000 sq. ft.
of the existing terminal concourse and 30,000 sq. ft. of the
ticketing and baggage claim areas.
The airport authority said construction of the new terminal
was scheduled to begin in mid-2005. The redevelopment of the
north concourse will be completed in 2008, with all construction
completed in 2009.
Meanwhile, Lane Construction Corp. of Meriden, Conn., was
moving forward with its $24.7 million Taxiway D relocation
and apron work for Terminal C. URS Corp. of Morrisville, N.C.,
was the project's civil engineer.
JetBlue: New Training Facility
in Orlando
JetBlue Airways broke ground in May at Orlando International
Airport for the construction of its flight-training center
and a new hangar for aircraft maintenance and LiveTV installation
and maintenance. The company split the work with a pair of
general contracts.
Hensel Phelps Construction Co. of Orlando will handle the
hangar facility, while Suitt Construction Co. of Maitland
is building the training center.
Hensel Phelps is design-building the 70,000-sq.-ft. hangar
and accompanying 29,000 sq. ft. of office and shop space.
The hangar, scheduled to be complete by early 2005, is a pre-engineered
metal building. In September, the contractor was progressing
with structural work as concrete slabs were being poured.
The hangar will be used for aircraft maintenance as well
as the installation and maintenance of the airline's LiveTV
in-flight satellite television system.
Suitt's 80,000-sq.-ft. training center project has the capacity
for eight flight simulators and two cabin simulators, plus
classrooms, cabin crew training equipment, training pool,
firefighting training station and administration areas. The
airline will use the facility for the initial and continuous
training of all JetBlue pilots and in-flight crew, plus support
training for its technical operations and customer service
crew. Construction of the training center is scheduled to
be completed in late 2005.
At the groundbreaking ceremony, Orlando Mayor Buddy Dyer
said: "I am proud that JetBlue chose the city of Orlando
for this expansion project. JetBlue assists the city and metro
Orlando community in our efforts to diversify our economy,
create high paying jobs and grow our simulation industry."
The architect for the training center is Rubin & Rotman
Architects of Quebec. According to JetBlue, the combined cost
for the two facilities will be approximately $160 million.
TIA's Airside C: Curtainwall
System
Subcontractor Harmon Inc. of Tampa began erecting the curtain-wall
system at Tampa International Airport's Airside C in July.
The anticipated 18-week erection schedule would give the contractor
a late 2004 timetable for its work.
Harmon manufactured and assembled the units at its Orlando
facility and then trucked them into the site as they were
required for erection. Project officials expected to reach
an erection pace of roughly eight sections per day.
It's a unique use of materials at TIA, said Ed Jenkinson,
former project manager for general contractor Beck Group.
"It's going to be the first building (at TIA) that's
all glass, with clear, anodized aluminum frames," he
said. "Aesthetically this building is going to look a
lot different."
Albert Alfonso, president of project architect Alfonso Architects
of Tampa, explained his selection of a glass curtain-wall
system.
"We tried to make the roof plane - which sort of has
this long curving arch - as simple and uncluttered as possible,"
he said. "So it's like you have this floating wing that
floats over the building."
He added that by going with a more transparent glass, "We
tried to disengage the roof plane from the floor plane, and
one of the ways to do it was to make the building seem more
transparent."
New Garage at Charleston
International
Gulf Stream Construction Co. of North Charleston, S.C., began
its work on a $22.5 million, 1,200-plus-space parking garage
at Charleston International Airport early this year. The new
facility will also provide curbside rain cover and covered
crosswalks.
The project was funded by a federal grant that the authority
credited U.S. Sen. Ernest F. Hollings, D-S.C., for helping
to secure.
The garage has been designed by HNTB's Atlanta offices and
LS3P Associates of Charleston. A fall 2005 completion is expected.
Return to Ready for Takeoff?
|