|
MIA South Terminal
Structural Steel Sub Went Bankrupt
but Stayed Ahead of Schedule
by Natalie Keith
The construction team at Miami International Airport celebrated
a project milestone recently when Havens Steel Co. of Kansas
City, Mo., completed the connection of the new South Terminal
and Concourse J on budget and 21 days ahead of schedule.
The achievement was particularly noteworthy because Havens
Steel filed for bankruptcy earlier in the year as a result
of rising steel prices.
Gilberto Neves, Odebrecht Construction executive vice president
and construction manager of Parsons-Odebrecht Joint Venture,
praised Havens' work. Parsons-Odebrecht has a $658 million
construction-manager-at-risk contract for the airport project.
"What Havens accomplished was impressive," Neves
said. "We have a great team in place but we've got a
long way to go to complete the entire project."
By mid-September, the company had completed 90 percent of
the work at both the South Terminal and Concourse J. The remaining
10 percent of the work is miscellaneous metal work, Neves
said.
Despite having steel shipped from plants across the country
and China, Neves said, "the materials arrived like clockwork."
Havens Steel - which has steel fabrication plants in Kansas
City; Ottawa, Kan.; and Guangzhou, China - was awarded two
contracts totaling approximately $42 million. At a topping-out
ceremony held at the construction site Aug. 30, the final
piece of steel joining the South Terminal to Concourse J was
put into place.
Approximately 20,000 tons of steel, 45,000 individual steel
pieces, nearly 2 million sq. ft. of metal deck and more than
300,000 bolts were used to construct the South Terminal and
Concourse J. At its peak, Havens employed more than 200 ironworkers,
all members of the International Association of Bridge, Structural,
Ornamental and Reinforcing Iron Workers Local Miami 272.
Havens filed for bankruptcy midway through the job. Robert
Dunn, president and CEO of Havens Steel, said when the cost
of steel began rising last summer, it didn't cause much concern
for the company. But with surcharges driving up the cost of
steel further, the company began experiencing liquidity problems
in January.
Havens was able to fend off difficulty for a period of time
thanks, in part, to Parsons-Odebrecht's ability to accelerate
payments for completed work on the job. However, in March
when a bank prevented Havens from using cash or inventory
as collateral to obtain financing for the job, the company
was forced to file for bankruptcy.
"It was quite nerve-racking," Dunn said. "The
judge gave us two weeks to file a reorganization plan."
In the meanwhile, workers redoubled their efforts and focused
on getting the job done. Dunn praised workers for enduring
difficult circumstances such as payroll sometimes being a
few days late. At one point, the site was shut down for a
week, Dunn said.
"People hung in there with us and never gave up on us,"
Dunn said.
The Parsons-Odebrecht-led construction team broke ground
on the project in January 2002 and the job is expected to
be completed in March 2006.
While officials applauded the rapid completion of the steel
work, they stressed that much work still needs to be done
before the airport work is complete.
Among work that is progressing are two contracts held by
Hensel Phelps Construction Co. of Orlando.
Hensel Phelps began working in August 2003 on a $169 million
multitrade contract for the airport's South Terminal that
covers the general construction of the new five-story building
and renovations in an adjacent existing Concourse H building
at the southern end of the airport.
It is a two-phase project with the final phase being the
renovations of the existing terminal, according to Kirk Hazen,
project manager for Hensel Phelps.
The company also began working in April 2003 on a $73 million
contract for a new 14-gate Concourse J, which will handle
both domestic and international passengers.
The scope of the work consists of the completion of the South
Terminal, excluding foundations, underground utilities, structural
steel, curtain wall and baggage-handling systems, which were
awarded as separate trade contracts.
Hensel Phelps' responsibilities include all mechanical, electrical,
communications, plumbing, HVAC, fire protection, elevators,
escalators, power walks, concrete, roofing, interior finishes
and new bus station.
The architectural design and selection of materials are intended
to convey the exciting and tranquil feeling of flight, Hazen
said. The facility features a glass-enclosed skywalk that
transverses the building. Significant architectural features
include a standing-seam barrel roof, glass curtain wall, stainless
steel metal walls and ceilings, artistic terrazzo, artist
wall and a variety of dramatic building shapes and transitions.
The architects on the job are from a Miami joint venture
of Borelli & Associates Architects, Planners; Mateu Carreno
Rizo & Partners; and Rodriquez and Quiroga Architects
Chartered.
The 353,000-sq-ft. building is 900 ft. long by 120 ft. wide.
It has a 145-ft.-tall concrete gate control tower at the north
end.
There are 33 elevators, 18 power walks and 29 escalators
in both projects. Aircraft ground support equipment includes
ethylene glycol preconditioned air and 400 hertz power systems,
Hazen said.
The Concourse J project and the first phase of the South
Terminal project is expected to be completed in the first
quarter of 2006. The second phase of the South Terminal project
is expected to be completed in 2007.
As of June, Hensel Phelps had completed 10 percent of the
South Terminal project and 21 percent of the Concourse J project,
according to Neves with Parsons-Odebrecht.
Hazen said the South Florida market is new for Hensel Phelps.
"Along with entering new territory, come the challenges
involved with the hiring of new craft employees," he
added. "We have hired over 250 craftspeople and have
placed over 80,000 cu. yds. of concrete and built the Concourse
J gate control tower."
Hensel Phelps also had to coordinate the prime contractors
working on the job.
"Due to the size, constant changes and complexity of
the projects, coordination between all trade contractors is
critical," Hazen said. "This constant coordination
and communication is the only way to facilitate schedule,
quality and safety issues that may impact the overall completion
of the project."
When finished, the South Terminal will measure 1.7 million
sq. ft. and includes eight design projects consisting of baggage-claim
areas, a baggage sorting system, security screening system,
a cruise and tour bus depot, 142 ticketing positions, approximately
50,000 sq. ft. of concession area and a federal inspection
services facility.
By mid-September, 35 percent of the project had been completed,
"but we've got a long way to go," Neves said.
Three Hurricanes Disrupt MIA
Contractors
|