|
A Race to the Finish
Interior Finishes Challenged ChampionsGate
Project Contractors
By Debra Wood
A cornerstone of a new master-planned community, the $175
million Omni Orlando Resort at ChampionsGate, boasts upscale
amenities and high-end finishes in the public areas.
"One of the major challenges has been procuring some
of the exotic finish materials that the interior designer
selected for the ornate finishes in the lobby and lower-lobby
levels," said David K. Pendergraft, senior project manager
for Cesari Construction Group of Orlando, the owner's representative.
Interior designer Looney & Associates and architects
at RTKL Associates, both of Dallas, designed the hospitality
complex. ChampionsGate includes residential condominium units,
a retail center, two golf courses and a separate golf clubhouse.
"The whole concept is a relaxed elegance, similar to
an upscale country club," said Jim Looney, principle
with Looney & Associates. "It retains a resort feeling
that is appealing to different groups."
When contractors learned the originally selected imported
natural stones were in short supply, they met with designers
to select alternative materials. Italian marble in three hues
now cover the lobby floor.
"We did an extensive review with the interior designer,
architect and owner, selecting and approving the different
types of marble and granite, porcelain tiles, species of wood
and the stains and finishes on those woods so they have the
high-grade quality needed for a [AAA] four-diamond resort,"
said Neal Blackketter, operations manager for WELBRO Building
Corp. of Maitland, the general contractor.
Water-jet art-marble medallions in an array of colors come
together in an elaborate custom design in the lobby. Many
of the irregular, handcrafted tiles used at the hotel required
a higher degree of installation expertise than normally encountered
in a commercial project.
"There has been a ratcheting up of scrutiny of all issues
of quality workmanship, and that has kept all the installing
trades on their toes," Pendergraft said.
Millwork in the lobby has a furniture-grade finish. The sports
bar contains African mahogany and Brazilian cherry wood and
has a subtle golf motif.
"When contractors go into a project like this and talk
about what a four-diamond hotel is, they have different ideas,"
Pendergraft said. "As the owner's, developer's and operator's
intentions behind the quality expectations are made obvious,
there can be a wake-up call. People are not normally held
to that standard."
Cesari and design consultants routinely inspected the workmanship
to ensure everything was up to standards. "When you walk
the property now, the effort really shows," Pendergraft
said,
The building process
The 730-room, 16-story hotel includes 70,000 sq. ft. of ballroom
and meeting space, five restaurants, an adult pool and children's
water center, a whirlpool spa, and an 850-ft.-long lazy-river
water feature. Weller Pool Constructors of Apopka completed
all of the water features.
WELBRO began the project in December 2002 and was on track
to complete it in September. The company incorporated many
techniques to speed construction and self-performed the masonry
and concrete framework.
"It helps us maintain control of the schedule because
the frame going up really drives the schedule," Blackketter
said.
WELBRO used a flying-table, suspended-slab forming system
that eliminated the need for shoring on the slabs. A stud-rail
system in the slabs increases the resistance to the punching
sheer of the supporting columns.
"It allows you to have a flat-plate slab on the bottom,
which is easier to form and have tables that slide in and
out easier," Blackketter said. "It also helps reduce
the amount of rebar you have in that slab around the column.
It worked out very well."
The company used a concrete that cured within 72 hours and
conventionally reinforced it to give mechanical, electrical
and plumbing greater flexibility in running utilities and
pipes. For the toilet exhaust, WELBRO used an autoclaved,
aerated concrete block shaft instead of a drywall shaft.
"It allows you to make the shaft wall out of a lightweight
concrete block, so you are able to get that in before the
exterior walls are up," Blackketter said. "Typically,
you would have to wait until you are dried in from the elements
before you could put any drywall in."
The exterior has a metal-stud frame with an EIFS skin and
glazing system. The exterior of the ballroom space is tilt-up
concrete, with structural steel joists, trusses and beams.
WELBRO finished the rooms from the top down. As crews completed
each floor, the owner began moving in furniture and other
hard goods.
Crews worked weekends and evenings to keep the project on
time.
Finishing Touches
Owners refined plans for the Omni's food and beverage outlets
and retail after construction began. Because of market forces,
plans for one of the base-building restaurants, an Asian-themed
eatery, changed late in the project.
"We got thrown a few curves late," Pendergraft
said. "Any time you develop a property like this, regardless
of what effort you put in during design and development, there
is always a tendency among competent people to go back and
scrutinize what you've done."
Design and procurement efforts for these retail and restaurant
spaces were fast-tracked. Those spaces were permitted separately,
with the permit for the Asian restaurant not coming through
until mid-July.
Adjustments also were made to the property after owners and
architects walked through the site. Owners tweaked with areas
to improve efficiency, particularly in the pool's food and
beverage service area.
"We have been able to accommodate the owner's wants
and wishes," Blackketter said. "You have to role
with the punches, take those into account and incorporate
those and not let it be too disruptive."
Useful Sources:
ChampionsGate
http://www.omnihotels.com/hotels/default.asp?h_id=65
Project Team:
Owner: Omni-ChampionsGate
Resort Hotel, LP, Houston
Owner's Representative:
Cesari Construction Group, Orlando
Construction Manager: WELBRO
Building Corp., Maitland
Architect: RTKL Associates,
Dallas
Interior Designer: Looney
& Associates, Dallas
Civil Engineer: Dyer, Riddle,
Mills & Precourt, Orlando
Structural Engineer: Burton
Braswell Middlebrooks Associates, Longwood, Fla.
Electrical Contractor: Morgan
Electric, Lakeland, Fla.
Plumbing Contractor: Progressive
Plumbing, Clermont, Fla.
HVAC Contractor: S.I. Goldman,
Longwood, Fla.
|