|
Reaching for the Sky
New Air Traffic Control Tower will
be Tallest in the Country
by Sheila Bacon
Talk about high-profile.
When the new air traffic control tower at Hartsfield-Jackson
International Airport in Atlanta is finished, it will be the
nation's tallest. Flanked in 680 precast panels, it represents
a sizable concrete job as well.
The 398-ft.-tall tower - scheduled for completion in October
2005, with the Federal Aviation Administration occupying it
five months later - will replace the airport's current 232-ft.
tower. The existing tower sits in the path of the airport's
future international terminal, one part of Hartsfield-Jackson's
long-term expansion plans that also include a fifth runway
and another terminal.
Jacksonville-based Gate Precast is the precast subcontractor
on the 81,000-sq.-ft. project, casting the panels at its Monroeville,
Ala., plant. The panels range in size and shape, with the
largest measuring more than 9 ft. tall, 13.5 ft. wide and
3 ft. thick and weighing nearly 49,000 lbs., said Joey Langham,
Gate's project manager.
Casting efforts for the tower consumed 20 percent of the
Monroeville Plant's capacity, Langham said. Luckily, material
for the job was allocated before the current concrete shortage
could impact cost and delivery.
Plenty of Panels
The 6,000-psi precast panels define the structural system
of the tower's stem. Starting at level four, each 30-ft. level
of the stem is made up of 40 panels: 12 outside flat panels,
12 for radius corners panels and 16 interior wall panels.
The stem continues up through the cab, which will house air
traffic controllers and associated equipment. Steel forms
the structural support system for the cab, which is also flanked
in architectural precast panels.
Since precast is such a large and crucial part of the job,
Gate Precast started working closely with general contractor
Hensel Phelps within two weeks of the general's notice to
proceed. Six months of meetings, approvals of drawings and
panel fabrication preceded the start of precast installation.
Sequencing of work on a job such at this is critical, said
operations manager Allan Bliesmer from Hensel Phelps' Dallas,
office. If a construction or scheduling glitch occurs in one
area of a large office complex, for example, crews can shift
gears and continue working on another part of the job. On
the ATCT, however, the only way to go is up. If a piece of
precast doesn't fit, the entire project is halted.
Fortunately, efforts to keep the job on track paid off.
"Gate has done a tremendous job," Bliesmer said.
"They've worked with us on a buildable and aggressive
schedule."
Hensel Phelps is no stranger to challenging projects. The
general contactor built Orlando International Airport's ATCT
- until now, the nation's tallest at 345 ft.
Tower Teamwork
Gate Precast and Precast Erectors of Hurst, Texas, started
erecting panels at the Atlanta tower's fourth level March
24, finishing at level 10 before the flare of the cab on June
7 - a pace that could be met only by closely coordinating
schedules and working in tandem with the rest of the project
team.
Mark Ledkins, Gate vice president of operations, expected
complete erection of the tower's precast to be finished in
late November or early December - before the originally scheduled
date of Dec. 15.
Hensel Phelps crews constructed the first three levels of
the tower's stem with poured-in-place concrete, requiring
extensive coordination with Gate to ensure a smooth transfer
to the precast system. Gate created full-size templates of
the cast-in-place building footprint that included all rebar
locations so crews could easily blend the two systems.
Both contractors used the carefully drafted templates to
design the cast-in-place and precast forms. The transfer went
smoothly, despite as little as .25-in. tolerance at the connection
points, Langham said.
The stem and cab panels are lightly sandblasted to provide
an enhanced surface for paint adhesion.
Gate is the precast subcontractor on two other related structures:
a three-story base building at the bottom of the ATCT, which
will house offices, administration space and the tower's mechanical
and electrical services, and a one-story engine generation
building housing emergency power. Gate subbed out the precast
work for a 120-vehicle parking structure for FAA employees.
Hensel Phelps is the general contractor on all three projects.
Project Team:
Owner: City of Atlanta's
Department of Aviation
General Contractor: Hensel
Phelps Construction Co., Orlando
Precast Subcontractor: Gate
Precast, Jacksonville, Fla.
Erection Subcontractor:
Precast Erectors, Hurst, Texas
Useful Sources:
For more information on other projects under way at the airport
in support of the fifth runway can be found by visiting the
following:
http://www.atlanta-airport.com/default.asp?url=http://www.atlanta-airport.com/sublevels/airport_info/fifth.htm
|