Good Times, Tough Times
Concrete contractors in South Florida
deal with cement shortage amidst record volume
By Scott Judy
The cement shortage has slowed down many South Florida projects
and delayed the start of others, but three of the area's biggest
concrete-forming contractors - Southland Forming of West Palm
Beach, Fort Lauderdale-based Form Works and Commercial Forming
Corp. of Pompano Beach - either have kept their projects on
track, or are doing what they can to make up lost time.
Either way, the impact has been real.
On Form Works' 42-story Ocean Palms project in Hollywood,
for example, the concrete contractor lost about three weeks
on its schedule during a six-week period starting around mid-May.
"There were certain days we just couldn't get concrete,"
said Don Marks, the firm's president. That changed when concrete
supplier Tarmac opened its new cement plant in June, he added.
"We're still seeing some impact," added Darrell
Whiteside, president and CEO of Southland Forming. "I
don't think we're going to see a lot of improvement in the
current conditions for the next 12 months."
At the same time, Thomas Prieur, vice president of Commercial
Forming, said his firm had experienced "no problems,"
including on its highest-profile project, Trump Palace in
Sunny Isles Beach.
"The projects we were on were not affected," he
said. Prieur added that one time they had to switch concrete
suppliers when the original one was unable to supply the project
adequately. He said that overall, the shortage was "sort
of leveling off."
Project Reports
Following are brief reports on these firms' biggest and brightest
projects.
Ocean Palms - This luxury condominium in Hollywood transitions
from a peak of 35 stories at one end to 42 stories at the
other. Form Works has a roughly $20 million contract with
Coastal Construction Services of Miami covering excavation,
form work, reinforcing steel, concrete placement and finishing,
as well as supplying the cranes and pumps.
The project was about halfway up in August, and the company
was "seeing what we can do to catch up" on its three-week
delay, Marks said.
Form Works started its concrete work for the foundations
in late January and expects to complete its contract by March.
The contractor is back on a floor-per-week schedule, with
three pours of about 220 yds. each used to build the 24,000-sq.-ft.
slabs.
Typical floors began on the fourth story. Form Works used
7,500-psi concrete for the slabs up to the 11th floor, and
a 6,000-psi mix for the floors above that. There is an estimated
50,000 yds. of concrete on the job.
One Miami - Southland Forming's One Miami project in downtown
Miami - which features two towers, one 43 stories and the
other 44, plus an 11-story parking garage - felt virtually
no impact from the cement shortage.
"(General contractor) John Moriarty & Associates
really made it happen," said Tim Anderson, superintendent
for Southland Forming. "The Related Group is the owner,
and they're both known for completing their projects either
early or on time. They decided where they needed their concrete
the most, and we poured 1,100 to 1,200 yds. a week all through
the shortage."
The company has completed the garage and in August was on
the 23rd floor of the east tower and the 19th floor of the
west tower. The towers are scheduled for completion in January
and February, he added.
"It's a pretty hectic schedule," Anderson said.
The contractor pours five slabs every six days. Each tower
requires two pours per floor slab, so that's slightly more
than one floor per week for both towers. In fact, with five
slabs per week, that works out to five floors for each tower
every month, Anderson said.
Tarmac and Super Mix tag-teamed to keep this high-profile
project supplied with concrete and on schedule.
Despite the positive progress, Anderson is frustrated with
One Miami's tight site conditions.
"There's no room for anything," he said, adding
the company was using One Miami's parking garage as its staging
area for its materials.
Trump Palace - One of Commercial
Forming's biggest recent projects was this project for Donald
Trump in Sunny Isles Beach. The company began its work in
February 2003 and concluded its activity in August.
General contractor Coscan Construction LLC of Fort Lauderdale
has the 551-ft.-tall, 43-story, ultraluxury condominium building
scheduled for a June completion.
Commercial Forming's scope of work included formwork, layout,
rebar placement and concrete pumping. Again, Prieur said the
material shortage didn't impact the project's schedule at
all, and the company was able to keep to its floor-per-week
timetable.
"There was more vertical concrete than horizontal concrete,
making it difficult to pour a floor each week," Prieur
said.
Still Booming
Despite any dampening effect from the materials shortage,
the South Florida construction economy appears as strong as
ever, these contractors say, and it may be preparing to escalate
even further.
"It's the fullest I've ever seen the pipeline,"
Marks said. "It's always possible that they'll have us
bid jobs that will never get going. But right now we've never
had this big of a backup on bidding."
Whiteside agreed. "The current level of activity is
as high as we've seen it," he added. "There's still
a lot of projects coming out of the pipeline. The backlog
is greater than it's ever been."
Prieur with Commercial Forming described the current workload
as similar to the past couple of years. "A lot of projects
are going to start toward the end of this year, the beginning
of next," he said. "We don't see a let-up."
This demand will continue to press the concrete suppliers.
"There's enormous demand," Marks said. "I
don't know if all of the concrete plants can produce all of
the concrete that we'll require if they all go at once."
|