|
Tilting at Cornerstone
Contractor places two-story panels
for five-story tilt-up office building
By Scott Judy
On Aug. 11, crews with Tilt-Con Corp. of Altamonte Springs
undertook an unusual effort as they erected two-story concrete
panels to top off the company's first-ever five-story tilt-up
concrete project.
The panels, measuring 18 ft. wide by 26 ft. high and weighing
in at roughly 60,000 pounds each, were lifted into place by
Miami Crane for the 113,700-sq.-ft. Cornerstone II building,
located in Plantation.
That day, Tilt-Con crews erected 15 of the 21 two-story panels,
and then finalized placement of the remaining sections on
Aug. 13.
The company began erecting the lower, three-story panels
in mid-July. Column and fourth-floor slab construction followed,
in preparation for the placement of the upper-floor panels.
Lifting the two-story panels to atop the in-place three-story
sections was a challenge, especially considering the layout
of the panels. With so many windows, the contractor and Miami
Crane had to utilize more lifting points than usual for each
panel.
Jeff Chalk, project manager for Tilt-Con, credited close
coordination for the smooth Aug. 11 effort.
"It takes a lot of planning, because the first lift
of panels has rebar sticking out of the top," he said.
"The second lift panel has a sleeve to receive that rebar.
So you have to make sure everything lines up. We thought it
was going to be a little more difficult to line panels up,
but it was very smooth."
Itasca Construction Associates of Boca Raton is the project's
general contractor. Retzsch Lanao Caycedo Architects, also
of Boca Raton, was the architect.
|