|
Tampa's Airside C
Project is Second New Terminal
to be Design-Built at Tampa International Airport
By Scott Judy
Another new terminal at Tampa International Airport. Another
new team of contractor and designer. And, so far, another
design-build success story.
That's the situation as general contractor Beck and Tampa
design firm Alfonso Architects lead the construction of TIA's
latest new airside terminal, the 315,000-sq.-ft. Airside C.
Following on the heels of the award-winning, $70 million Airside
E terminal, which was completed by Skanska USA two years ago,
the Beck/Alfonso team had the goal of delivering an even better
- and unique - facility.
"We had the advantage of having (Airside E) already
done, so we were able to learn from it," said Albert
Alfonso, president of Alfonso Architects and the project's
lead architect. "This one is going to stand on its own."
Ed Jenkinson, vice president and senior project manager for
Beck, agreed.
"It's going to be unique out here," he said, adding
it will be the first building at TIA to incorporate an all-glass
curtain wall exterior. "Aesthetically this building is
going to look a lot different."
Owner TIA, however, wasn't as intent on having the new facility
be different from Airside E as much as it wanted it up and
running as quickly as possible.
"Our expectations were to complete a building from design
to construction in 18 months," said Lou Russo, TIA's
senior director of planning and development. "That was
what we were looking at. We thought we could do it as well
as (Airside E), if not better."
Designing It
Beck and Alfonso first agreed to work together in late 2002,
and then won a $3.5 million design-development contract the
following February. A $71 million contract signed in August
2003 covered design completion and construction and set an
April 2005 completion date. Demolition and sitework began
in September, and Beck/Alfonso submitted a guaranteed maximum
price contract two months after that.
Jenkinson said the project was on target. By July, the contractors
were finishing the superstructure and were about to start
installation of the exterior curtain wall. Interior rough-ins
were getting started, and mechanical, electrical and plumbing
work was well under way.
A close working relationship was necessary to move as quickly
as necessary. In fact, during the first six months of their
effort together, Jenkinson and other Beck staffers actually
worked from Alfonso's offices.
Alfonso and Beck chose a curvilinear layout to accommodate
the terminal's 16 gates within the building footprint. Airside
C will be TIA's largest airside to date and will provide 10
dedicated gates to Southwest Airlines, two to Spirit and others
that will do double-duty as swing gates for both airlines
and charter flights. The terminal also will include eight
security stations for TSA passenger screening, with capacity
for two more.
The roof gradually curves from a height of roughly 15 ft.
at both ends to 30 ft. high at its peak. This curvilinear
aspect helped Alfonso in his quest to evoke a sense of aviation's
romantic history with his Airside C design. He mentioned Eero
Saarinen's iconic TWA terminal at New York's Kennedy Airport
as an inspiration.
"We tried to do a project that brought back the enjoyment
of the flying experience, which has been sort of lacking of
late," he said. "We tried to create a piece of architecture
that harkened back to that era of the early 1960s when it
was a real adventure to go on an airplane."
The curtain-wall exterior is intended to further heighten
the sense of adventure and connection to the outside by providing
expansive views of the planes and surrounding airport.
"We tried to make the roof plane - which sort of has
this long curving arch - as simple and as uncluttered as possible,"
Alfonso said. "It's like you have this floating wing
that floats over the building."
Inside, the ceiling will be a solid, smooth, white surface.
From outside, the roof will "float" by Alfonso's
use of a semitransparent green glass for the curtain wall
that visually "disengages the roof plane from the floor
plane."
Other Differences
The new terminal also differed from its predecessor in other
ways. Because it was designed post-Sept. 11, the architect
could better accommodate security issues, such as the location
of passenger screening. Also, the terminal's entry area from
the passenger tram was brought into the building at a lower
angle - to eliminate any incline, as found at E, and thereby
improve wheelchair accessibility.
More challenging, though, was the coordination with Skanska
USA's ongoing $120 million security and baggage screening
project, which ties into Airside C's lower level. Skanska
USA is scheduled to start erecting the baggage system in October
and conclude in time for Airside C's opening.
Jenkinson said Skanska has been cooperative throughout the
course of the project.
"They gave us all of their baggage shop drawings, and
we coordinated all of our mechanical, electrical and ductwork
around it," he added.
Like Airside E, Beck has to deal with other GCs, such as
Bombardier and its people-mover work, as well as John Carlo
Inc., which is building the apron and fuel system surrounding
the new terminal, starting at just 30 ft. from the new structure.
Additionally, the airport plans to shutter the old, neighboring
Airside D within 30 to 60 days of Airside C's completion,
which adds to the coordination workload.
"This is a more difficult project than Airside E,"
Russo said. "There's a lot more coordination involved
with building this facility and relocating everybody out of
D."
Building It
One advantage the Beck/Alfonso team had was in the group
of subcontractors it signed up for the job. The vast majority
had worked on Airside E and knew the owner's expectations.
"The only people who are different from E, design-team-wise,
are Beck and Alfonso," Jenkinson said. "The electrical,
mechanical, sprinkler contractors - they're all from E. So
they know what the airport's expecting." For those reasons,
Beck and Alfonso brought numerous subs and suppliers in early
to assist with design.
"We got a lot of manufacturers and subcontractors involved
with our decision-making process - which was very helpful
for establishing schedules and budgets early on," Jenkinson
said.
The schedule for building this mostly concrete building was
impacted slightly due to the current concrete shortage. Concrete
deck work started in January and had been scheduled to wrap
by June, but it was pushed a few weeks past that.
"Luckily we were past our critical-path points,"
Jenkinson said. "If (the shortage) would've happened
three months earlier, then it really would have affected our
critical path and sequencing. We were used to getting 400-500
yds. a day, then all of a sudden it was 200 yds. maximum."
Pours shrank from an expected 10,000 sq. ft. per day to half
that.
S.B. Ballard of Virginia Beach, Va., was the main concrete
contractor, but it subbed the formwork and pan slabs to Southern
Pan Services Co. of Lithonia, Ga. United Forming of Orlando
placed the 220 spread-footing foundations and poured the first
lift of columns. RMC/Ewell was the concrete supplier.
The roof is built of structural steel, supplied by SteelFab
of Norcross, Ga., and erected by Williams Erectors, Atlanta.
Curtain wall work began in early July. Harmon Inc. of Tampa
is supplying the system in unidized panels that are preassembled
in its Orlando facility and hauled to the site and erected
daily. The contractor plans an 18-week erection schedule.
Design-Build Results
The essence of design-build is collaboration, and that's
been prevalent at Airside C.
"Usually a contractor and an architect are sort of pitted
against each other," Alfonso said. "Beck is very
respectful of the concept of the design. So they're always
very hesitant to go after things without us buying into it.
So there's a true partnership with how we work with Beck.
That's how a true design-build should work."
John Allen, director of construction management for TIA,
said the airport was pleased with the results to date.
"We're happy with the quality of the buildings and with
the management team they have out here - and the way they
operate as a team," he added. "They're a true design-build
team, and that's been nice. Overall, so far, it's a very easy
job for us."
USEFUL SOURCES:
For information and photos of the project:
http://www.tampaairport.com/news_events/projects/airside_c.html#photos
Airside C Project
Team
Owner: Tampa International
Airport, Tampa
Contractor: Beck, Tampa
Designer: Alfonso Architects,
Tampa
|